Product Liability Alert: “Sophisticated User” Defense Not Available by Showing Existence of a “Sophisticated Intermediary”
November 26, 2014 —
R. Bryan Martin & Kristian B. Moriarty - Haight Brown & Bonesteel LLPIn Gottschall v. Crane Co., (No. A136516, Filed 10/8/2014, published 10/22/2014), the Court of Appeal, First Appellate District, held a company that manufactured and sold asbestos-containing products could not prevail under the “sophisticated user” doctrine based on the contention that a “sophisticated intermediary” existed, in an action brought by the end user of the products.
Decedent Robert Gottschall worked in a variety of shipyards for the U.S. Navy between 1957 and 1989. Defendant Crane Co. (“Crane”) manufactured and sold products containing asbestos to the Navy during that time. During his work at the various shipyards, decedent was exposed to asbestos and contracted mesothelioma.
Reprinted courtesy of
R. Bryan Martin, Haight Brown & Bonesteel LLP and
Kristian B. Moriarty, Haight Brown & Bonesteel LLP
Mr. Martin may be contacted at bmartin@hbblaw.com; Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Supreme Court Weighs in on Timeliness of Claims Against Subcontractors in Construction Defect Actions
March 16, 2017 —
Jean Meyer - Colorado Construction LitigationOn February 27, 2017, the Colorado Supreme Court announced its decision in the Goodman v. Heritage Builders, No. 16SA193, 2017 CO 13 (Colo. February 27, 2017) case. In ten short pages, the Colorado Supreme Court completely reshuffled Colorado construction law with respect to application of the statutes of limitation and repose on third-party claims in construction defect cases. Specifically, the Colorado Supreme Court overruled a series of earlier Court of Appeals' decisions that found C.R.S. § 13-80-104(1)(b)(II) (“104(1)(b)(II)”) had no effect on the six-year statute of repose. For context, 104(1)(b)(II) permitted third-party actions for indemnity and contribution to toll until ninety days after the claims in the underlying action were resolved by settlement or judgment. In the construction context, 104(1)(b)(II) was intended to allow a general contractor’s claims against liable subcontractors to toll for the statutorily defined period. This allowed the general contractor to first focus its attention on defending the claims against and thereafter to pursue its claims against the subcontractors.
However, beginning in 2008, in the Thermo Dev., Inc. v. Cent. Masonry Corp., 195 P.3d 1166 (Colo. App. 2008) case, the Colorado Court of Appeals began chipping away at the force of 104(1)(b)(II). This trend continued in the Shaw Constr., LLC v. United Builder Servs., Inc., 2012 COA 24, 296 P.3d 145 decision, the Sierra Pac. Indus., v. Bradbury, 2016 COA 132, _ P.3d_ decision, and culminating in the Sopris Lodging, LLC v. Schofield Excavation, Inc., 2016 COA 158, reh'g denied (Nov. 23, 2016) decision. Effectively, in these decisions, the Colorado Court of Appeals determined that third-party claims could not be brought beyond Colorado’s six-year statute of repose, regardless if they were brought within the ninety day tolling provision set forth in 104(1)(b)(II).
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
Factual Issues Prevent Summary Judgment Determination on Coverage for Additional Insured
May 01, 2014 —
Tred R. Eyerly – Insurance Law HawaiiNumerous factual issues prevented the court from deciding at the summary judgment stage whether the additional insured was covered for a personal injury claim that happened on a construction site. Paynes Cranes v. Am States Ins. Co., 2014 U.S. Dist. LEXIS 40485 (E.D. N.Y. March 26, 2014).
Intermetal Fabricators, Inc. hired Paynes to provide a crane and driver for the construction of a store. A construction worker was injured while working with the crane. The injured worker sued several defendants, including Paynes.
Intermetal had coverage for the project that included additional insureds. The policy provided, “Any person or organization . . . for whom you [Intermetal] are required by written contract, agreement or permit to provide insurance is an insured, subject to the following additional provisions: a. The contract, agreement or permit must be in effect during the policy period . . . and must have been executed prior to the ‘bodily injury,’ ‘property damage,’ 'person and advertising injury.’”
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Orlando Commercial Construction Permits Double in Value
October 01, 2013 —
CDJ STAFFThis August, permits were taken out for $102.3 million of commercial construction projects, a 95% increase over last August’s $52.4 million. Meanwhile, residential construction was up by a third, jumping from $205.6 million to $274.1 million. Overall that sent construction up by 46% in the Orlando area.
The construction industry is a major one in the Orlando area and its recovery provides some hope for the region.
Read the court decisionRead the full story...Reprinted courtesy of
Event-Cancellation Insurance Issues During a Pandemic
September 07, 2020 —
Lorelie S. Masters & Latosha M. Ellis - Hunton Andrews KurthAs the effects of coronavirus continue, organizations and companies now are considering whether events in late 2020 and early 2021 can take place or need to be converted to virtual events. What insurance effects will those changes and cancellations have? Consideration of these important decisions requires a review of both event-cancellation insurance and a consideration of force majeure and other such issues.
On the insurance front, years ago, many policyholders purchased event-cancellation insurance for events in 2020, 2021, and even as far out as 2024. Such policies, purchased before the middle of March 2020, generally contain explicit coverage “buy-backs” for losses from “communicable disease.” That is, the policyholders paid an extra, specifically identified premium to remove any exclusion for communicable disease from these policies. Typically, these policies do not use the word, “virus”, but rather use “communicable disease”; and exclude neither. Those policies typically cover a specified amount of net profit and include additional coverages for “Cost of Remedial Action”, “Future Marketing Expense”, etc., over and above that specified amount of coverage.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Latosha M. Ellis, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Ms. Ellis may be contacted at lellis@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Lien Waiver Provisions Contractors Should Be Using
January 06, 2020 —
Jason Lambert - Construction ExecutiveIt is common in construction for a subcontractor or material supplier of any tier to be required to provide a lien waiver when receiving payment. But not all lien waivers are created equal. While at a minimum, a lien waiver, by definition, needs to include a release of liens, it can also include many other terms that can tie up loose ends or resolve potential problems before they begin.
Additional Releases
A typical lien release is going to release any liens and right to claim liens on the subject property. But a lien waiver can also include releases of any claims against surety bonds, other statutory rights or claims, and at its broadest, claims against the paying party. One example of a provision that could help accomplish this is a release of “any right arising from a payment bond that complies with a state or federal statute, any common law payment bond right, any claim for payment, and any rights under any similar ordinance, rule, or statute related to claim or payment rights.” Broad release language can also be used to effectively preclude any claims arising prior to the date of the release.
Payment Representations and Warranties
A typical lien release has no representations or warranties about payment to subcontractors or material suppliers of a lower tier. But contractors can include language requiring the company receiving payment to represent and warrant that all subcontractors of a lower tier have been paid or will be paid within a certain timeframe using the funds provided and that these are material representations and inducements into providing payment. On a related note, if the contract requires subcontractors to provide lien releases from lower tier subcontractors in addition to their own release when seeking payment, contractors can require the sub-subcontractor releases to include representations that they have been paid by the subcontractor to try and tie up payment loose ends all around.
Reprinted courtesy of
Jason Lambert, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Lambert may be contacted at
jason.lambert@nelsonmullins.com
While You Were Getting Worked Up Over Oil Prices, This Just Happened to Solar
October 29, 2014 —
Tom Randall – BloombergEvery time fossil fuels get cheaper, people lose interest in solar deployment. That may be about to change.
After years of struggling against cheap natural gas prices and variable subsidies, solar electricity is on track to be as cheap or cheaper than average electricity-bill prices in 47 U.S. states -- in 2016, according to a Deutsche Bank report published this week. That’s assuming the U.S. maintains its 30 percent tax credit on system costs, which is set to expire that same year.
Even if the tax credit drops to 10 percent, solar will soon reach price parity with conventional electricity in well over half the nation: 36 states. Gone are the days when solar panels were an exotic plaything of Earth-loving rich people. Solar is becoming mainstream, and prices will continue to drop as the technology improves and financing becomes more affordable, according to the report.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Randall, BloombergMr. Randall may be contacted at
trandall6@bloomberg.net
Appeals Court Affirms Carrier’s Duty to Pay Costs Taxed Against Insured in Construction Defect Suit
November 03, 2016 —
Jesse Howard Witt – The Witt Law FirmOne of the key reasons for builders to maintain liability insurance is to cover the cost of hiring defense counsel and paying litigation costs in the event of a construction defect lawsuit. If a builder loses a lawsuit, it will typically be responsible for paying the plaintiff’s litigation costs. Today, the Colorado Court of Appeals clarified that the “supplementary payments” section of a standard Commercial General Liability (CGL) insurance policy covers such costs, even if the carrier has reserved the right to dispute whether it has a duty to indemnify the actual damages awarded. This may seem counter-intuitive, insofar as a carrier may owe costs even if it does not cover the underlying loss, but the court’s decision is consistent with the plain language of the CGL form that most carriers use.
Reprinted courtesy of
Jesse Howard Witt, The Witt Law Firm
Mr. Witt may be contacted at his website www.witt.law
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of