Changes to Va. Code Section 43-13: Another Arrow in a Subcontractor’s Quiver
November 02, 2020 —
Christopher G. Hill - Construction Law MusingsAs is always the case here in Virginia, our General Assembly has made some legislative changes that affect construction contracting. One of these changes is an amendment to Va. Code 43-13 found in the mechanic’s lien section of the Virginia Code.
This section of the code has always required that any money paid to a contractor must first go toward paying its subcontractors, suppliers and laborers prior to being used for any other purpose. Prior to 2020, the only remedy for violaiton of Va. Code 43-13 was to go to the local Commonwealth’s Attorney and request a prosecution of the wrongdoer. For various reasons, including that such action did not get the subcontractor or supplier that remained unpaid under this section paid, this remedy was not often pursued except in the most egrigious cases.
A key change in the statute occurred during the 2020 legislative session states as follows:
Any breach or violation of this section may give rise to a civil cause of action for a party in contract with the general contractor or subcontractor, as appropriate; however, this right does not affect a contractor’s or subcontractor’s right to withhold payment for failure to properly perform labor or furnish materials on the project. Any contract or subcontract provision that allows a contracting party to withhold funds due under one contract or subcontract for alleged claims or damages due on another contract or subcontract is void as against public policy.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Practical Distinction Between Anticipatory Breach and Repudiation and How to Deal with Both on Construction Projects
June 10, 2024 —
Devon Griger - ConsensusDocsWhen a multilevel construction project is underway and a contractor or subcontractor isn’t performing as expected, it can be difficult to know how to address the low performance without putting the parties’ contract and good working relationship at risk. However, there may come a time when poor performance lapses into a something much worse: an anticipatory breach or repudiation of the subject contract.
Imagine Scenario One: You are a general contractor managing a large-scale construction project and one of your subcontractors is falling behind on their work. The project manager for the subcontractor calls you and says, “Look, I don’t think we’re going to be able to hit our next milestone, and probably not the next one after that.” A conversation like this would generally trigger concern for most general contractors, but it would not necessarily invoke panic. These types of delay conversations are not uncommon on large scale projects.
Compare that example, however, with Scenario Two, where the subcontractor instead says, “We received an offer to work another job for much more money, so we’re leaving the project site today and will not be returning.” This is obviously different (and potentially worse) than Scenario One, and likely cause for much greater concern.
Read the court decisionRead the full story...Reprinted courtesy of
Devon Griger, Jones WalkerMs. Griger may be contacted at
dgriger@joneswalker.com
Alabama Limits Duty to Defend for Construction Defects
October 10, 2013 —
CDJ STAFFWhile supreme courts in several states have expanded what is covered under a commercial general liability policy, Alabama has bucked the trend. Martha P. Brown and David L. Brown discuss this in a post on the site of their firm, Nelson Levine de Luca & Hamilton. They note that in a recent case, Owners Insurance Company v. Jim Carr Homebuilders, “the court held that liability for defective construction resulting in water intrusion damage to otherwise properly constructed component parts is not covered under a general contractor’s commercial general liability (CGL) policy because such damages are not caused by an ‘occurrence.’”
The background of Owners v. Jim Carr was that the work of the subcontractors was found not only to be defective, but responsible for damage to correctly performed work. The court held, however, that it was all part of the same project. The court “distinguished the present case from a situation where the insured’s work results in damages to other property outside the scope of the insured’s work,” which they noted could be covered under a CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
California Case That Reads Like Russian Novel Results in Less Than Satisfying Result for Both Project Owner and Contractors
May 01, 2019 —
Garret Murai - California Construction Law BlogSometimes you can see a train wreck coming a mile away. The next case, Design Built Systems v. Sorokine, Court of Appeal for the First District, Case Nos. A151264 and A152059 (February 26, 2019), is one of those cases. It also happens to read like a Tolstoy novel.
The Beginning of the Train Wreck
Alexei Sorokine and Elena Koudriavtseva, husband and wife, owned a single family home in San Rafael, California. Sorokine had acquired the house prior to his marriage to Koudriavtseva. In 2010, he traveled to Russia and, for reasons unexplained, has not been able to return.
Following a landslide on the property in 2006, Sorokine entered into a construction contract with Design Built Systems to design and build a series of retaining walls. DBS was also retained to remedy a stop work notice issued by the City of San Rafael following work performed by others.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at
gmurai@wendel.com
The Other Side of the North Dakota Oil Boom: Evictions
May 13, 2024 —
Sarah Holder - BloombergWilliams County, North Dakota, is one of the biggest beneficiaries of the state’s fracking boom. In the past decade, millions of barrels of oil have been pumped from its land, and the population of its largest city, Williston, has doubled.
But as the oil flowed and workers poured in to staff the rigs, housing options quickly ran dry. The region’s uneven expansion has led to an eviction crisis for the county’s 39,000 residents, according to a recent paper from a group of sociologists affiliated with Princeton University’s Eviction Lab.
Williams County saw its eviction rate go from “nearly non-existent” in 2010 to over 7% a decade later, the study found. By 2019, at the height of its oil boom — when the state accounted for 11% of the country’s oil production — its eviction filing rate was comparable to that of large, renter-heavy cities like New York City or Philadelphia, according to Eviction Lab. Though oil production peaked in 2019, the problem hasn’t abated: From January through November 2023, more than 550 evictions were recorded by the Williams County Sheriff’s office, up around 30% from the previous full year.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah Holder, Bloomberg
How the Cumulative Impact Theory has been Defined
November 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesLargely in the federal contract arena, there is a theory referred to as “cumulative impacts” used by a contractor to recover unforeseeable costs associated with a multitude of changes that have an overwhelming ripple effect on its efficiency, particularly efficiency dealing with its original, base contract work. In other words, by dealing with extensive changes, there is an unforeseeable impact imposed on the contractor relative to its unchanged or base contract work. Under this theory, the contractor oftentimes prices its cumulative impact under a total cost approach with an examination on its cost overrun. However, this is not an easy theory to prevail on because there needs to be a focus on the sheer number of changes, causation supporting the impact, and whether there were concurrent impacts or delays that played a role in the ripple effect. See, e.g., Appeals of J.A. Jones Const. Co., ENGBCA No. 6348, 00-2 BCA P 31000 (July 7, 2000) (“However, in the vast majority of cases such claims are routinely denied because there were an insufficient number of changes, contractor-caused concurrent delays, disruptions and inefficiencies and/or a general absence of evidence of causation and impact.”).
To best articulate how the cumulative impact theory has been defined, I want to include language directly from courts and board of contract appeals that have dealt with this theory. This way the contractor knows how to best work with their experts with this definition in mind–and, yes, experts will be needed–to persuasively package and establish causation and damages stemming from the multitude of changes. While many of these definitions are worded differently, you will see they have the same focus dealing with the unforeseeable ripple effect of the extensive changes.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Inverse Condemnation and Roadwork
October 09, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPThe following case, issued yesterday by the Georgia Supreme Court, addresses the accrual of the statute of limitations on a claim of inverse condemnation based on nuisance.
Wise Bus. Forms, Inc. v. Forsyth Cnty., S22G0874, 2023 WL 6065278 (Ga. Sept. 19, 2023)
We granted certiorari in this case to clarify the standards for determining when a claim for inverse condemnation by permanent nuisance accrues for purposes of applying the four-year statute of limitation set forth in OCGA § 9-3-30 (a).
[. . .]
Permanent nuisance cases vary in relation to when the alleged harm to a plaintiff’s property caused by the nuisance becomes “observable” to the plaintiff. Forrister, 289 Ga. at 333 (2), 711 S.E.2d 641. In some cases, the harm to the plaintiff’s property is immediately observable “upon the creation of the nuisance.” Id. For example, where a landowner or governmental agency “erects a harmful structure such as a bridge or conducts a harmful activity such as opening a sewer that pollutes a stream,” and it is immediately obvious that the structure or activity interferes with the plaintiff’s interests, the plaintiff must file “one cause of action for the recovery of past and future damages caused by [the] permanent nuisance” within four years of the date the structure is completed or the harmful activity is commenced. Id. at 333-336 (2) and (3), 711 S.E.2d 641 (citing Restatement (Second) of Torts §§ 899 and 930). Phrased another way, where the “construction and continuance” of the permanent nuisance at issue is “necessarily an injury, the damage is original, and may be at once fully compensated. In such cases[,] the statute of limitations begins to run upon the construction of the nuisance.” City Council of Augusta v. Lombard, 101 Ga. 724, 727, 28 S.E. 994 (1897).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Change #7- Contractor’s Means & Methods (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaFirst, a little history: as you know, means, methods, techniques, sequences, and procedures are all part of the Contractor’s responsibility on a construction site. However, when the AIA A201 was last revised, in 2007, there was a provision put in for that rare time when the Contract Documents gave specific instructions concerning a particular construction method. If the Contractor viewed such instructions as unsafe, he was to give notice to the Owner and Architect, and was not to proceed with that portion of the Work without further written instructions from the Architect. If the Architect directed him to proceed, the Contractor was absolved from any risks with following that instruction. Instead, the Owner assumed the responsibility for any loss or damage.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina