Court Finds That Limitation on Conditional Use Permit Results in Covered Property Damage Due to Loss of Use
November 06, 2018 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Thee Sombrero, Inc. v. Scottsdale Ins. Co. (No. E067505, filed 10/25/18), a California appeals court held that a property owner’s loss of the ability to use his property as a nightclub, based on revocation of a city’s conditional use permit (“CUP”), constituted covered property damage.
In Sombrero, lessees operated a nightclub under the property owner’s conditional use permit from the City of Colton. A company hired to provide security negligently allowed admission to an armed patron, who shot and killed another patron. The City revoked the owner’s permit, and the owner was only able to negotiate the reinstatement of a limited permit, for use as a banquet hall only.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Taking the Stairs to Human Wellness and Greener Buildings
June 22, 2016 —
Rob Finch – Construction Informer BlogIf taking the stairs catches on, buildings with elevators could automatically get greener. The people working in them also stand a good chance of getting healthier. However, designers and builders working for owners who want to reap these advantages, will need to learn a few new tricks when it comes to how stairs get placed and promoted. They also get a chance to unleash creativity in how they are finished.
Read the court decisionRead the full story...Reprinted courtesy of
Rob Finch, Construction Informer Blog
Beware of Personal-Liability Clauses – Even When Signing in Your Representative Capacity
January 31, 2018 —
David R. Cook Jr. – Autry, Hall & Cook, LLPWhen a contract is drafted by a party, the other party expects some level of one-sidedness in favor of the drafter. But there are times when a contract goes too far. There are certain provisions that most persons in the construction industry would find unacceptable, unfair, and beyond the pale – even for a one-sided contract. Such a provision was arguably found in an electrical subcontract at issue in a 2014 opinion by a three-judge panel of the Georgia Court of Appeals. Unfortunately, due to long-standing Georgia law, the panel was forced to apply the provision as written.
In the case, a contractor hired a subcontractor to perform the electrical scope of work. When the subcontractor failed to pay a sub-subcontractor, the sub-subcontractor filed suit against the subcontractor, contractor, and the payment-bond surety. The contractor asserted a claim of indemnity against the subcontractor based on the sub-subcontractor’s claim.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
You Cannot Arbitrate Claims Not Covered By The Arbitration Agreement
March 16, 2020 —
David Adelstein - Florida Construction Legal UpdatesRegardless of the type of contract you are dealing with, “[a]rbitration provisions are contractual in nature, and therefore, construction of such provisions and the contracts in which they appear is a matter of contract interpretation.” Wiener v. Taylor Morrison Services, Inc., 44 Fla. L. Weekly D3012f (Fla. 1st DCA 2019). This means if you want to preserve your right to arbitrate claims you want to make sure your contract unambiguously expresses this right. Taking this one step further, if you want to make sure an arbitrator, and not the court, determines whether the claim is arbitrable if a dispute arises, you want to make sure that right is expressly contained in the arbitration provision.
For example, in Wiener, a homeowner sued a home-builder for violation of the building code – a fairly common claim in a construction defect action. The homeowner’s claim dealt with a violation of building code as to exterior stucco deficiencies. The home-builder moved to compel the lawsuit to arbitration based on a structural warranty it provided to the homeowner that contained an arbitration provision. The structural warranty, however, was limited and did not apply to non-load-bearing elements which, per the warranty, were not deemed to have the potential for a major structural defect (e.g., a structural defect to load-bearing elements that would cause the home to be unsafe or inhabitable). The trial court compelled the dispute to arbitration pursuant to the arbitration provision in the structural warranty.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Toll Brothers Report End of Year Results
December 11, 2013 —
CDJ STAFFThe largest luxury home builder in the U.S. saw some significant gains in their final quarter for 2013. Their pre-tax income for the year was $150.2 million, up from last year’s $60.7 million, more than doubling. The firm’s revenues went up 65% to $1.04 billion, and the average price of homes was up as well. Toll Brothers is currently selling homes in 232 communities, also increasing over 2012. Due to the upcoming acquisition of Shapell, Toll Brothers projects that at the end of 2014 they will be selling in 250 to 290 communities.
Read the court decisionRead the full story...Reprinted courtesy of
Federal Lawsuit Accuses MOX Contractors of Fraud
March 04, 2019 —
Scott Judy - Engineering News-RecordA subcontractor employee working on the now-canceled MOX project in South Carolina used football tickets, automobile tires, barbecue grills and other gifts to persuade employees of CB&I AREVA MOX Services and other vendors to help approve thousands of fraudulent invoices cumulatively valued at more than $6.4 million, according to a Dept. of Justice lawsuit filed Feb. 14 that names both companies as defendants. The controversial project at the Savannah River Site in Aiken, S.C., originally scheduled for completion in 2016, was canceled in January after cost and schedule estimates increased significantly.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Judy, ENRMr. Judy may be contacted at
judys@enr.com
Colorado House Bill 17-1279 – A Misguided Attempt at Construction Defect Reform
March 29, 2017 —
David McClain - Colorado Construction LitigationOn March 17th, House Bill 17-1279, concerning the requirement that a unit owners’ association obtain approval through a vote of unit owners before filing a construction defect action, was introduced and assigned to the House State, Veterans, and Military Affairs Committee. The bill is currently scheduled for its first committee hearing on March 29th, at 1:30 in the afternoon. While, on its face, this appears to be a step in the right direction towards instituting “informed consent” before an HOA can file a construction defect action, the bill actually restricts the ability of developer to include more stringent requirements in the declaration of covenants, conditions, and restrictions for an association, thereby lowing the threshold of “consent” required to institute an action.
House Bill 17-1279 would amend C.R.S. § 38-33.3-303.5 to require an association’s executive board to mail or deliver written notice of the anticipated commencement of a construction defect action to each unit owner and to call a meeting of the unit owners to consider whether to bring such an action. Any construction professional against which a claim may attend the unit owners’ meeting and have an opportunity to address the unit owners and may include an offer to remedy any defect in accordance with C.R.S. § 13-20-803.5(3). The conclusion of the meeting would initiate a 120-day voting period, during which period the running of any applicable statutes of limitation or repose would be tolled. Pursuant to this bill, an executive board may only institute a construction defect action only if authorized by a simple majority of the unit owners, not including: 1) any unit owned by any construction professional, or affiliate of a construction professional, involved in the design, construction, or repair of any portion of the project; 2) any unit owned by a banking institution; 3) any unit owned in which no defects are alleged to exist, and/or 4) any unit owned by an individual deemed “nonresponsive.”
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Not Pandemic-Proof: The Ongoing Impact of COVID-19 on the Commercial Construction Industry
December 06, 2021 —
George B. Green Jr. - Construction ExecutiveThe impact of COVID-19 has been felt in nearly every industry and arena across the country, with the exception of construction—or so that is the general perception. Perceptions are often wrong though, and this one is no different. The truth is that the construction industry has been hit just as hard, if not harder, than every other industry.
As the COVID-19 pandemic struck in the spring of 2020, construction projects plowed forward full steam ahead. Roadwork seemed to increase and developers continued to systematically acquire property and initiate large-scale projects. Perhaps it was these observations that led many to the conclusion that construction was pandemic-proof as the rest of society attempted to cobble together something that vaguely resembled a normal business year. But the construction industry has endured many challenges over the last 18 months, and unfortunately, the challenges do not appear to be evaporating anytime soon.
The industry has been primarily affected in the areas of scheduling, manpower and permitting, which has ultimately affected pricing. The entire way jobs are scheduled has been turned upside down. The supply chain issues that many have experienced for everyday household items have hit the construction industry as well.
Reprinted courtesy of
George B. Green Jr., Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Green may be contacted at
ggreen@wwhgd.com