Georgia Legislature Passes Additional Procurement Rules
May 30, 2018 —
David R. Cook Jr. - Autry, Hall & Cook, LLPOn May 3, 2018, Governor Nathan Deal signed HB 899 into law, officially making it Act 389. Act 389 modifies O.C.G.A. § 13-10-4 and § 36-91-23 relating to public works bidding and contracts of state and local governments, respectively. Both sections are modified in the same bill because they contain the same language. The bill prohibits the disqualification of bidders based upon lack of previous experience with the project’s desired construction delivery method.
Before the modifications, the code protected a contractor from disqualification only for lack of previous experience on a job of comparable size. After the modification, the law expands to prohibit disqualification based on lack of previous experience with comparable job size and lack of previous experience with the construction delivery method.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Hunton Insurance Practice Again Scores “Tier 1” National Ranking in US News Best Law Firm Rankings
December 05, 2022 —
Hunton Insurance Recovery BlogOn November 3, 2022, US News announced its
annual law firm rankings, where Hunton Andrews Kurth LLP garnered the highest (Tier 1) ranking among national insurance law practices. Hunton’s insurance team also received Tier 1 honors for “Insurance Law” in three regions (Washington, DC, Atlanta and San Francisco) and Tier 2 honors for “Litigation – Insurance” in Washington, DC. US News ranks law firms in tiers from 1 (highest) to 3 (lowest) based on quantitative data that speaks to general demographic and background information on the practice group, attorneys and other data that speaks to the strengths of a law firm’s practice, as well as qualitative client feedback about:
- the practice group’s expertise,
- responsiveness,
- understanding of a business and its needs,
- cost-effectiveness,
- civility, and
- whether the client would refer another client to the firm.
Read the court decisionRead the full story...Reprinted courtesy of
Hunton Andrews Kurth LLP
Condominium Exclusion Bars Coverage for Construction Defect
August 17, 2011 —
Tred R. Eyerly - Insurance Law HawaiiCoverage was denied under the policy’s condominium exclusion in California Traditions, Inc. v. Claremont Liability Ins. Co.,2011 Cal. App.LEXIS912 (Cal. Ct. App., ordered published July 11, 2011).
California Traditions was the developer and general contractor for a housing development. California Traditions subcontracted with Ja-Con to perform the rough framing work for 30 residential units. The project had 146 separate residences that were freestanding with no shared walls, roof, halls, or plumbing or electrical lines. To allow a higher density development, the project was developed, marketed and sold as condominiums.
The purchaser of one of the units filed a complaint against California Traditions alleging property damage from the defective construction. California Traditions cross-complained against Ja-Con.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Ohio Court of Appeals Affirms Judgment in Landis v. Fannin Builders
April 20, 2011 —
Beverley BevenFlorez CDJ STAFFThe Ohio Court of Appeals affirmed the judgment in Landis v. William Fannin Builders. Landis contracted Fannin Builders to build their home. The case involved staining problems on the T1-11 siding chosen by the plaintiffs.
After a year and a half of discussion on how to resolve the problem of uneven staining on the siding, Landis filed suit “against Fannin Builders, alleging claims for breach of contract, breach of the express limited warranty, and violation of the Ohio Consumer Sales Practices Act (“OCSPA”). Fannin Builders, in turn, filed a third-party complaint against 84 Lumber, alleging claims for breach of contract and indemnification. With the trial court’s leave, Fannin Builders also later amended its answer to add a counterclaim against appellees for breach of contract and unjust enrichment. In the counterclaim, Fannin Builders alleged that appellees still owed it $3,908.98 for the construction of appellees’ home.”
“In its decision, the trial court found in appellees’ favor on their breach of contract claim and against appellees on their claims for breach of the express limited warranty and violation of the OCSPA. Additionally, the trial court found in Fannin Builders’ favor on its counterclaim for breach of contract and against Fannin Builders on its third-party claims for breach of contract and indemnity. The trial court determined that appellees’ damages amounted to $66,906.24, and after setting off the $3,908.98 that appellees owed Fannin Builders under the construction contract, the trial court awarded appellees $62,997.26. The trial court reduced its decision to judgment on May 18, 2010.”
Fannin Builders appealed this judgment and assigned the following errors:
[1.] The Trial Court Erred as a Matter of Law by Concluding that Appellant Breached its Contract with Appellees when it provided a Semi-Transparent Oil-Based Stain that Simply did not Meet their Approval.
[a.] The Contract does not Contain a Satisfaction Clause.
[b.] Even if the Court Implies a Satisfaction Clause, the Court Should Apply an Objective Standard.
[2.] The Trial Court Erred as a Matter of Law by Failing to Consider Appellant’s Right to Cure.
[3.] The Trial Court committed Reversible Error by not Assessing Damages Using “Diminished Value Standard,” and by Creating a Remedy that Constitutes Economic Waste.
[4.] The Trial Court Erred as a Matter of Law by Concluding that Appellant is Barred from Seeking Indemnification When 84 [Lumber] Never Fulfilled its Obligations Pursuant to the Settlement Agreement Entered on August 2, 2005.
In response to the first assigned error, the Court of Appeals stated: “Because the failure to provide siding of a uniform color, not appellees’ displeasure, breached the contract, we reject Fannin Builders’ contention that the trial court implied a satisfaction clause into the contract and found a breach of that clause. Accordingly, we overrule Fannin Builders’ first assignment of error.”
The Court of Appeals overruled the second assignment of error and provided the following reasoning: “Although Fannin Builders depends upon a term of the limited warranty for its right to cure, the trial court concluded that no breach of the limited warranty occurred. Fannin Builders breached the duty of workmanlike conduct implicit in the construction contract, not the limited warranty requiring it to satisfy the BIA’s Quality Standards. Consequently, the limited warranty does not apply to this case, and thus, it does not prevent appellees’ recovery of damages.”
The Appeals Court found “the trial court’s award of damages” was “both reasonable and supported by competent, credible evidence,” and therefore concluded “that the trial court did not err in setting appellees’ damages at $62,997.26.” The Fannin Builders third assignment of error was overruled.
The fourth and final assignment of error was also overruled by the Court of Appeals. “While Fannin Builders correctly asserts that 84 Lumber never installed the replacement siding, it ignores the fact that it ordered 84 Lumber to remove the replacement siding from appellees’ property. Thus, Fannin Builders precluded 84 Lumber from completely performing under the August 2, 2005 letter agreement. […] Consequently, Fannin Builders cannot now claim that the letter agreement is unenforceable or that it is entitled to indemnification from 84 Lumber. Because Fannin Builders assumed all liability for the defective siding in the letter agreement, it is responsible for appellees’ damages.”
James A. Zitesman, Columbus, Ohio Business Attorney, compared the case to Jones v. Centex (Ohio App. 2010), which had a different verdict:
“The common thread is the implied warranty of good workmanship. In the Jones case, the Court found that the buyers had in fact waived all implied warranties, including the implied warranty of good workmanship. In the contract between Jones and Centex, the builder stated that it “…would not sell the property to Purchasers without this waiver.” Probably should have been a sign to the buyers.
In the Landis case, the Court stated, “Contracts for the future construction of a residence include a duty, implied by law, that the builder must perform its work in a workmanlike manner.” The Court gave significant weight to the concept of the implied warranty of good workmanship. The builder relied upon the BIA Warranty which limits builders’ liability and exposure to legal issues. The trial court concluded there was no breach of the limited warranty, rather the builder “breached the duty of workmanlike conduct implicit in the construction contract, not the limited warranty requiring it to satisfy the BIAs Quality Standards.”
The Supreme Court of Ohio has accepted the Jones v. Centex Homes case for review.
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
What Is the Best Way to Avoid Rezoning Disputes?
August 30, 2021 —
Collier Marsh - Construction ExecutiveConstruction companies and developers are accelerating projects in the southeast and throughout the country as the economy rebounds from the worst of the COVID-19 pandemic. Whether they are building commercial, industrial or residential projects, these developments often require rezoning to maximize an investment. But rezoning disputes can add significant delays and costs to a project and can even defeat the project altogether.
There are proactive steps construction companies can take to avoid disputes as they are working to secure rezoning approval, as well after the rezoning is complete. During the initial rezoning process, before a final municipal decision, one of the best practices is to anticipate opposition and address it head-on. As for post-approval disputes, those often come down to how carefully a company followed the local procedures and, where applicable, the local evidentiary requirements.
Reprinted courtesy of
Collier Marsh, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Marsh may be contacted at
colliermarsh@parkerpoe.com
Architectural Firm Disputes Claim of Fault
May 27, 2011 —
CDJ STAFFLake-Flato Architects has disputed the arbitration panel’s conclusion that problems with the home of Tom Hanks and Rita Wilson were due to design flaws. The firm settled with the couple for $900,000, however the Idaho Mountain Express reports that David Lake said, “the settlement in the case in no way represents that Lake Flato was responsible for faulty design.” The Express reported that “the arbitrators found that problems at the home were attributable to design errors that did not take into account the cold winter climate of the Sun Valley area.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
The COVID-19 Impact: Navigating the Legal Landscape’s New Normal
July 27, 2020 —
Amanda Mathieu - Lewis BrisboisWhile most of the country has been at a standstill since March, you might be wondering, what about my lawsuit or my administrative charge? For the past couple of months, most litigation cases have largely been put on pause in the courts and at administrative agencies. However, as we adjust to what is clearly a new normal in both our lives and the legal landscape as we know it, cases will begin to pick up speed again, albeit with new strategies and challenges to keep in mind.
As courts begin to reopen, judges are emphasizing in many jurisdictions that criminal cases will take priority in an effort to attend to constitutionally required timelines. Nevertheless, it will remain just as important as before the pause button was hit to keep cases moving forward. This ramp up period presents a unique opportunity for clients and attorneys to invest meaningful time into investigating and developing defenses to claims while the court system and related case pace remains slowed.
Read the court decisionRead the full story...Reprinted courtesy of
Amanda Mathieu, Lewis BrisboisMs. Mathieu may be contacted at
Amanda.Mathieu@lewisbrisbois.com
Kentucky Court Upholds Arbitration Award, Denies Appeal
June 15, 2011 —
CDJ STAFFThe Kentucky Court of Appeals has ruled in Lake Cumberland Community Action Agency v. CMW, Inc. affirming the arbitration award. CMW, Inc. was responsible for the construction of a facility to be used for pre-school students and the housing of Alzheimer patients and senior citizens. An agreement was made that any disputes would be heard by an arbitrator selected by the construction industry.
The plaintiff alleged that there were design and construction defects in the building trusses, violation of the Kentucky Building Code, and problems with the HVAC system. The arbitrator awarded $106,000 to the plaintiff which then sought to vacate the award. The circuit court upheld the arbitrator’s decision.
The Court of Appeals found that there was no basis for rejecting the arbitrator’s decision, noting “there is nothing to show that there was any fraud or bias on the part of the arbitrator.” The appeals court, with all three judges concurring, upheld the arbitration award.
Read the court’s decision
Read the court decisionRead the full story...Reprinted courtesy of