Panama Weighs Another Canal Expansion at Centennial Mark
August 20, 2014 —
Michael McDonald – BloombergA century after the U.S. steamship Ancon first sailed through the Panama Canal, a $5.3 billion expansion delayed by bickering contractors and angry workers is nearing completion. The problem is it might not be big enough.
With the expansion 16 months behind schedule, canal administrator Jorge Quijano said officials are studying whether to dig a fourth set of locks to handle a growing fleet of super-sized ships. Those include the 400-meter-long “Triple E” vessels capable of carrying more than 18,000 containers, four times more than current ships passing through the canal.
“We are always analyzing the market and as soon as we can economically justify it we will begin,” said Manuel Benitez, deputy administrator of the Panama Canal Authority, adding that he thinks the current expansion is sufficient for now. “If that changes and the demand exists we are ready to begin.”
Read the court decisionRead the full story...Reprinted courtesy of
Michael McDonald, BloombergMr. McDonald may be contacted at
mmcdonald87@bloomberg.net
Construction Contract Basics: Attorney Fee Provisions
November 13, 2023 —
Christopher G. Hill - Construction Law MusingsI have discussed the need for
attorney fee provisions in your construction contracts in prior posts here at Construction Law Musings, but thought it merited a restatement of the reasons for the inclusion of such fee provisions (and changing of such provisions when presented) here with the second of my
construction contract basics posts.
Why would you want such a provision? The answer is that without it, or a statute specifically allowing for such fees, a Virginia court will not award your attorney fees without such a provision. Virginia, and a lot of other states, follow the so-called “American Rule” when it comes to attorney fees and costs. In short, that rule states that the parties to litigation pay their own way unless they agree otherwise. While it may seem unfair to make a successful litigant pay for the privilege of being right, that is the rule in Virginia. Throw in the fact that Virginia courts
strictly construe construction contracts and voila we have a situation where without a provision in the contract stating that one party or both will be able to collect attorney fees should that contractor or subcontractor prevail, a construction professional that gets sued (whether rightly or wrongly) will be left with a hefty attorney fees bill and no way to recoup those fees through the courts or any other method.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Lease-Leaseback Battle Continues as First District Court of Appeals Sides with Contractor and School District
August 17, 2017 —
Garret Murai - California Construction Law BlogEarlier, we wrote about Davis v. Fresno United School District (2015) 237 Cal.App.4th 261, a Fifth District California Court of Appeals decision that sent shock waves through the school construction industry and raised questions regarding the use of California’s lease-leaseback method of project delivery (Education Code sections 17400 et seq.).
California’s lease-leaseback method of project delivery provides an alternative project delivery method for public school districts than the usual design-bid-build method of project delivery. Under the lease-leaseback method of project delivery, a school district leases its property to a developer, who in turn builds a school facility on the property and leases it back to the school district. One of the benefits of the lease-leaseback method of project delivery is that school districts do not need to come up with construction funds to build school facilities since they pay for the construction over time through their lease payments to the developer. Critics, however, argue that because lease-leaseback projects do not need to be competitively bid, they are ripe for cronyism between developers and school districts.
In Davis, a taxpayer successfully brought suit against the Fresno Unified School District challenging the propriety of a lease-leaseback project because the entirety of the District’s “lease payments” occurred while the project was being constructed and thus, successfully argued the taxpayer, there was no “true” lease of a facility since it was under construction.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
What Are The Most Commonly Claimed Issues In Construction Defect Litigation?
April 22, 2019 —
David M. McLain - Colorado Construction Litigation BlogAs a lawyer that has spent his career defending against construction defect claims, one of the most common questions I get when counseling clients regarding risk management is: “What are the most commonly claimed issues in construction defect litigation?” Until very recently, my answer to this question has been based on my own experience and knowledge on the subject, and only vaguely reliant on empirical data.
Recently, two engineers, Elizabeth Brogan and William McConnell, along with Caroline Clevenger, an associate professor at the University of Colorado, Denver, wrote a paper entitled “Emerging Patterns in Construction Defect Litigation: A Survey of Construction Cases.” The authors analyzed 41 multifamily construction defect cases litigated in 2015, 2016 and 2017, mostly in the Denver metro area.
The authors classified the 55 most prevalent alleged defects into the following categories: structural issues; civil issues; building envelope issues; roof issues; deck, balcony and porch issues; fire protection issues; and miscellaneous issues. The authors then identified the 10 most commonly claimed construction defects, which occurred in over half of all of the cases analyzed.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Hawaii Federal District Court Denies Brokers' MSJ on Duties Owed In Construction Defect Case
October 19, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court for the District of Hawaii denied the brokers' motion for summary judgment seeking dismissal from claims that they inadequately advised the insured of the law regarding construction defects in Hawaii. Am Auto. Ins. Co. v. Haw. Nut & Bolt, Inc., 2017 U.S. Dist. LEXIS 148571.
Safeway sued Hawaii Nut & Bolt (HNB) and others for construction defects in a newly constructed store. The underlying complaint alleged products liability claims against HNB as the distributor of the "VersaFlex Coating System." HSB had represented that the coating system was adequate for its intended use. The underlying complaint alleged failure of the VersaFlex Coating System in waterproofing the roof deck of the store. After the store opened, water leaks from the roof deck appeared. Safeway alleged they were caused by the cracks and failures in the waterproof membrane in the roof deck.
HNB notified its insurers of the claims. The insurers defended HNB during the litigation subject to reservation of rights letters.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Harlem Developers Reach Deal with Attorney General
February 25, 2014 —
Beverley BevenFlorez-CDJ STAFFJoseph Scarpinito and Shiraz Sanjana, developers of the Mirada condominium in Harlem, New York can avoid a contempt charge from state Attorney General Eric Schneiderman, “if they make the required repairs and obtain a permanent certificate of occupancy at the property,” according to The Real Deal.
Scarpinito and Sanjana “agreed to deposit $200,000 into an escrow account and make repairs to stop flooding and other defects at the 161 East 110th Street condo, which are required to obtain a certificate of occupancy from the city Department of Buildings.”
Last December, the Attorney General “filed suit against the developers, alleging they submitted false filings to his office in claiming that Scarpinito’s 83-year-old mother was the actual developer of the 68-unit condo.” Furthermore, the condo board lawyers submitted a complaint to Schneiderman “detailing extensive defects in the building, including water leaks entering the building from the roof and façade.”
The developers have been ordered “to submit weekly reports to the AG’s office detailing progress on the repairs and obtaining the certificate of occupancy.”
Read the court decisionRead the full story...Reprinted courtesy of
More Clear, But Not Yet Crystal: Virginia Amends its Prompt Payment Law and Legislation Banning “Pay-If-Paid Clauses in Construction Contracts Effective July 1, 2023
November 16, 2023 —
Hanna Lee Blake - ConsensusDocsThe Virginia General Assembly has joined a minority of jurisdictions that ban pay-if-paid clauses in construction contracts on public and private projects. Senate Bill 550 went into effect applying to contracts executed after January 1, 2023, and most recently has been amended effective July 1, 2023. This update highlights the recent amendments to Virginia’s prohibition against pay-if-paid provisions, of which owners and contractors should be aware to ensure that their contracts comply with developing law in the Commonwealth.
Recap on Senate Bill 550
On April 27, 2022, the Virginia General Assembly passed Senate Bill 550, which amended Virginia Code §§ 2.2-4354 and 11-4.6, which govern both public and private sector contracts. In short, SB 550 (as the bill is commonly known) prohibited pay-if-paid clauses, and established fixed deadlines for the payment of invoices on private projects. Previously, Virginia’s Prompt Payment Act only applied to public projects.
Read the court decisionRead the full story...Reprinted courtesy of
Hanna Lee Blake, Watt TiederMs. Blake may be contacted at
hblake@watttieder.com
“It Just Didn’t Add Up!”
November 05, 2024 —
Daniel Lund III - LexologyOverturning arbitration awards in court is difficult. One of the few bases for a challenge to an award (under the Federal Arbitration Act, 9 U.S.C. 10(a)(4), as well as most state arbitration laws) is where the arbitrator is alleged to have “exceeded [his/her] powers” afforded the arbitrator by whatever rules and agreements are in place for the arbitration. Obviously, this places a burden on the arbitrator to “color within the lines” when serving as arbitrator and issuing rulings in the case.
“After extensive discovery and a 10-day hearing, the Tribunal rendered a 142-page” award, whereupon the parties both sought to have the arbitrators correct what the parties agreed was an error in the award – increasing the award by $47,710. One of the parties, however, went further, urging that the arbitrators “erroneously included damages for claims related to production revenue” that occurred before a certain date. According to the court, that party was urging that “the Tribunal erred by factoring into its award damages related to Claims 2 and 3, which the Tribunal never substantially addressed.”
Read the court decisionRead the full story...Reprinted courtesy of