Should I Pull the Pin? Contractor and Subcontractor Termination for Cause
January 26, 2017 —
Patrick McNamara - Porter Law GroupAny owner or general contractor who has a few projects under his or her belt has likely had this thought: “My contractor (or subcontractor) is not performing the way I expected; should I replace him?” The other side of the termination coin is: “This project is not going the way I expected; should I get out?”
While there may be an emotional high that immediately comes from terminating a contractor or subcontractor (or leaving a project, in mid-stream), there are many factors to be weighed, before making that decision.
Project Delay. Replacing a contractor or subcontractor that has already begun performance always results in delays to the project. Assessing the work in place, interviewing replacement contractors, and negotiating the terms of the new relationship can easily consume weeks, if not months of project time.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
El Paso Increases Surety Bond Requirement on Contractors
April 25, 2011 —
Beverley BevenFlorez CDJ STAFFThe city of El Paso has recently increased surety bonds required of contractors from $10,000 to $50,000, according to the El Paso Times. Proponents of the increase believe it was necessary to protect homeowners from fly-by-night builders, while opponents argue that the increase will have an adverse effect on an industry in that is already suffering due to the economic slowdown.
Arguments for and against the increase have been flooding the blogosphere with their views. Christian Dorobantescu on the Small Business Entrepreneur Blog claims that “only about 15% of the city’s 2,500 contractors had been able to secure a higher bond to remain eligible for work after the new requirements were announced.” However, insurance companies have a different take. “From a surety broker standpoint, most contractors will be able qualify for the bond; some will just have to pay higher premium rates to obtain it,” a recent post on the Surety1 blog argues.
While the increased bond may help homeowners deal with construction defect claims, it is not clear what effect it will have on builders in El Paso.
Read more from the El Paso Times…
Read more from the Small Business Entrepreneur Blog…
Read more from the Surety1 Blog…
Read the court decisionRead the full story...Reprinted courtesy of
Compliance with Contractual and Jurisdictional Pre-Suit Requirements is Essential to Maximizing Recovery
November 27, 2023 —
Michael S. Levine, Geoffrey B. Fehling & Charlotte Leszinske - Hunton Insurance Recovery BlogTimely notice is an important first step in a successful insurance recovery. But insurance policies are not always straightforward in identifying how, when, and to whom notice must be provided. Some states may also impose additional procedural hurdles, including requiring policyholders to contact their insurers before filing suit (the idea behind this requirement is that it may avoid litigation). Failing to comply with pre-suit requirements can hurt the policyholder’s recovery, as illustrated in a recent decision from the Northern District of Texas.
In NewcrestImage Holdings, LLC v. The Travelers Lloyds Insurance Company, No. 2:23-cv-039-BR (N.D. Tex. Oct. 17, 2023), the court considered whether NewcrestImage had forfeited its right to recover attorneys’ fees by failing to give Travelers pre-suit notice. NewcrestImage had filed suit against Travelers to obtain coverage for damage to its hotel property arising out of Winter Storm Uri. In its answer, Travelers asserted that NewcrestImage failed to provide the insurer with pre-suit notice as required under the Texas Insurance Code, and that if NewcrestImage successfully proved it was entitled to coverage, NewcrestImage’s failure to provide pre-suit notice precluded it from recovering attorneys’ fees. Travelers later moved to strike the claim for attorneys’ fees on that basis.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth,
Geoffrey B. Fehling, Hunton Andrews Kurth and
Charlotte Leszinske, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Ms. Leszinske may be contacted at cleszinske@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
NJ Transit’s Superstorm Sandy Coverage Victory Highlights Complexities of Underwriting Property Insurance Towers
February 24, 2020 —
Traub LiebermanIn New Jersey Transit Corp. v. Certain Underwriters at Lloyd’s, London, 2019 WL 6109144 (N.J. App. Div. Nov. 18, 2019), New Jersey Transit (“NJT”) defeated the claim of several of its insurers that a $100 million flood sublimit applied to its Superstorm Sandy damages and recovered the full $400 million limits of its property insurance tower. The decision is a big win for the beleaguered transit agency, and for insurance professionals working with complex insurance towers, the decision highlights critical underwriting issues that can dramatically affect the amount of risk transferred by the policyholder or assumed by the insurer.
In NJ Transit, NJT secured a multi-layered property insurance program providing $400 million in all-risk coverage. The first and second layers provided $50 million each, the third and fourth layers provided $175 million and $125 million, respectively, with several insurers issuing quota shares in each layer. The program contained a $100 million flood sublimit, and “flood” was defined to include a “surge” of water. The program did not contain a sublimit for damage caused by a “named windstorm,” which was defined to include “storm surge” associated with a named storm. After NJT made its Superstorm-Sandy claim, some of the third- and fourth-layer insurers advised NJT that the $100 million flood sublimit applied to bar coverage under their policies. NJT sued these excess insurers and won at the trial and appellate levels.
In holding that the $100 million flood sublimit did not apply, the court applied the rule of construction that the specific definition of “named windstorm,” which included the terms “storm surge” and “wind driven water,” controlled over the policies’ more general definition of “flood.” In ascertaining the parties’ intent, the court noted that the omission of the term “storm surge” in the definition of “flood” evidenced an intention that the flood sublimit would not apply to storm surges. Based on this finding, the court rejected several arguments made by the insurers that other policy provisions evidenced the parties’ intent to apply the flood sublimit to all flood-related losses, regardless of whether the loss was caused by a storm surge.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Craig Holden Named Top 100 Lawyer by Los Angeles Business Journal
June 27, 2022 —
Craig Holden - Lewis BrisboisLos Angeles, Calif. (May 17, 2022) - Los Angeles Partner Craig Holden has been named to the Los Angeles Business Journal’s (LABJ) “Top 100 Lawyers” list, which recognizes the most impactful attorneys in the Los Angeles region for their ongoing efforts as outstanding legal professionals. The attorneys on the list were honored on May 12 at LABJ’s inaugural Top 100 Lawyers Awards at the ASU California Center.
In the publication’s special section, LABJ Publisher Josh Schimmels noted that the attorneys on the Top 100 Lawyers list “have demonstrated exceptional legal skill and achievements across the full spectrum of responsibility, exemplary leadership and contributions to the Los Angeles community at large.” He also observed, “Considering the fact that the Los Angeles region has long been known for its status as a hub for legal [through] leaders and record-setting attorneys, being a standout in that field is particularly impressive.”
Likewise, in discussing his inclusion on the list, Mr. Holden remarked, “I am honored to be included on this list with so many exceptional attorneys from the LA legal community.”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Holden, Lewis BrisboisMr. Holden may be contacted at
Craig.Holden@lewisbrisbois.com
Building 47 Bridges in Two Years
December 23, 2023 —
Dan Sopczak - Construction ExecutiveEvery construction project has its challenges, but some truly push the boundaries of what is achievable in the heavy civil industry. When the Indiana Department of Transportation sought to modernize its I-65/I-70 North Split Interchange in Indianapolis, Indiana, its request for proposals included building 47 new bridges and rehabilitating six additional bridges on an ambitious two-year timeline—905 days to substantial completion.
“Three design-build teams responded to the RFQ, and the same three teams responded to the RFP,” according to INDOT Strategic Communications Director Natalie Garrett. “Proposals were scored and evaluated using the best-value evaluation process defined by INDOT. The score was a combination of a technical proposal score and a price score.”
Reprinted courtesy of
Dan Sopczak, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Toll Brothers Surges on May Gain in Deposits for New Homes
June 01, 2020 —
Prashant Gopal - BloombergToll Brothers Inc. shares surged after the company posted profit that beat estimates and said deposits on new homes were up in recent weeks, a potential sign of optimism for the luxury housing market.
The homebuilder, which focuses on higher-end customers, has struggled during the pandemic. It reported orders for the second quarter that missed estimates and said the key metric had plunged starting March 16, when much of the economy shut down.
But investors shrugged off those results, focusing instead on a 13% year-over-year gain this month in deposits, which the company called a “leading indicator of current market demand.”
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, Bloomberg
Arizona Court of Appeals Decision in $8.475 Million Construction Defect Class Action Suit
May 09, 2011 —
CDJ STAFFIn the case of Leflet v. Fire (Ariz. App., 2011), which involved an $8.475 million settlement in a construction defect class action suit, the question put forth to the Appeals court was “whether an insured and an insurer can join in a Morris agreement that avoids the primary insurer’s obligation to pay policy limits and passes liability in excess of those limits on to other insurers.” The Appeals court provided several reasons for their decision to affirm the validity of the settlement agreement as to the Non-Participatory Insurers (NPIs) and to vacate and remand the attorney fee awards.
First, the Appeals court stated, “The settlement agreement is not a compliant Morris agreement and provides no basis for claims against the NPIs.” They conclude, “Appellants attempt to avoid the doctrinal underpinnings of Morris by arguing that ‘the cooperation clause did not prohibit Hancock from assigning its rights to anyone, including Appellants.’ This narrow reading of the cooperation clause ignores the fact that Hancock did not merely assign its rights — it assigned its rights after stipulating to an $8.475 million judgment that neither it nor its Direct Insurers could ever be liable to pay. Neither Morris nor any other case defines such conduct as actual ‘cooperation’—rather, Morris simply defines limited circumstances in which an insured is relieved of its duty to cooperate. Because Morris agreements are fraught with risk of abuse, a settlement that mimics Morris in form but does not find support in the legal and economic realities that gave rise to that decision is both unenforceable and offensive to the policy’s cooperation clause.”
The Appeals court further concluded that “even if the agreement had qualified under Morris, plaintiffs did not provide the required notice to the NPIs.” The court continued, “Because an insurer who defends under a reservation of rights is always aware of the possibility of a Morris agreement, the mere threat of Morris in the course of settlement negotiations does not constitute sufficient notice. Instead, the insurer must be made aware that it may waive its reservation of rights and provide an unqualified defense, or defend solely on coverage and reasonableness grounds against the judgment resulting from the Morris agreement. The NPIs were not given the protections of this choice before the agreement was entered, and therefore can face no liability for the resulting stipulated judgment.”
Next, the Appeals court declared that “the trial court abused its discretion in awarding attorney’s fees under A.R.S § 12-341.” The Appeals court reasoned, “In this case, the NPIs prevailed in their attack on the settlement. But the litigation did not test the merits of their coverage defenses or the reasonableness of the settlement amount. And Plaintiffs never sued the NPIs, either in their own right or as the assignees of Hancock. Rather, the NPIs intervened to test the conceptual validity of the settlement agreement (to which they were not parties) before such an action could commence. In these circumstances, though it might be appropriate to offset a fee award against some future recovery by the Plaintiff Leflet v. Fire (Ariz. App., 2011) class, the purposes of A.R.S. § 12-341.01 would not be served by an award of fees against them jointly and severally. We therefore conclude that the trial court abused its discretion in awarding fees against Plaintiffs ‘jointly and severally.’”
The Appeals court made the following conclusion: “we affirm the judgment of the trial court concerning the validity of the settlement agreement as to the NPIs. We vacate and remand the award of attorney’s fees. In our discretion, we decline to award the NPIs the attorney’s fees they have requested on appeal pursuant to A.R.S. § 12-341.01(A).”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of