Payment Bond Claim Notice Requires More than Mailing
August 04, 2015 —
Christopher G. Hill – Construction Law MusingsIt’s been a while since I posted something new relating to Virginia’s “Little Miller Act” and its various notice requirements for a subcontractor to make a payment bond claim.
I have posted on the basics of a Virginia payment bond claim previously here at Musings. One of these basics is the 90 day notice requirement for suppliers or second tier subcontractors with no direct contractual relationship to the general contractor. A recent case from the Norfolk, Virginia Circuit Court examined when notice is “given” under the Little Miller Act.
In R T Atkinson Building Corp v Archer Western Construction, LLC the Court looked at the question of whether mailing of the notice of claim is enough to constitute notice being “given” in a manner that would satisfy the statutory requirements. In that case, the supplier mailed the notice within the 90 day window, but the defendant argued on summary judgment that it did not receive the notice until 2 days after the 90 day window had closed. In support of this contention, the defendant provided tracking information showing delivery by the USPS on the non-compliant date.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Updates to Residential Landlord Tenant Law
October 18, 2021 —
Lawrence S. Glosser - Ahlers, Cressman & SleightOver the past several months, there have been major updates to the residential landlord tenant laws in Washington State and Seattle. There are also some remaining moratoria or eviction restrictions in Washington and Seattle. The following is a general overview of the changes.
Eviction Moratoria:
Washington State
Governor Inslee’s state-wide eviction moratorium technically ended on June 30, 2021. However, in late June 2021, Governor Inslee announced a “bridge” proclamation between the eviction moratorium and the housing stability programs put in place by the Washington State Legislature. The bridge is effective July 1 through September 30. The goal of the bridge period was to protect tenants from evictions for non-payment of rent to allow local governments to set up distribution programs for funds. More than $650 million of federal relief dollars allocated to assist renters was predicted to be available beginning in July. This is in addition to the $500 million previously released by the Department of Commerce to local governments for rental assistance and will help more than 80,000 landlords and renters. However, insofar as many localities have not established distribution protocols, the bridge period was instituted to allow time for those programs to be set up in various parts of the state.
Read the court decisionRead the full story...Reprinted courtesy of
Lawrence S. Glosser, Ahlers, Cressman & SleightMr. Glosser may be contacted at
larry.glosser@acslawyers.com
SEC Climate Change Disclosure Letter Foreshadows Anticipated Regulatory Changes
November 08, 2021 —
Karen C. Bennett & Jane C. Luxton - Lewis BrisboisWashington, D.C. (October 13, 2021) - In late September 2021, the Division of Corporation Finance of the Securities and Exchange Commission (SEC) issued a Sample Letter providing guidance to companies on how their climate disclosures will be analyzed for compliance with material risk reporting obligations. The Sample Letter precedes the SEC’s issuance of mandatory climate-related disclosure rules anticipated by year-end and signals a greater focus on specific information used to support securities filings, a development that businesses should take seriously.
The Sample Letter builds on climate change guidance the SEC issued in 2010 and identifies nine categories of disclosures the SEC suggests may be material risks that must be disclosed. These include:
- Consistency between a company’s corporate social responsibility report and its SEC filings;
- Risks associated with climate-related legislation, regulation, or policy, and resulting compliance costs;
- Litigation risks related to climate change; and
- Risks linked to an array of operational and market factors, including capital expenditures, continuity of business operations, supply chain stability, changing demand, reputation, availability of credit and insurance, and other climate-change related potential impacts on the financial condition of the company.
Reprinted courtesy of
Karen C. Bennett, Lewis Brisbois and
Jane C. Luxton, Lewis Brisbois
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Challenging a Termination for Default
September 23, 2024 —
David Adelstein - Florida Construction Legal UpdatesNo contractor wants to be terminated for default. It is the harshest contractual recourse. It is a recourse that has implications, particularly in the public sector. However, a party needs to be in a position to support the basis of the termination for default, and the terminated party, in most instances, should not be in a position to imply accept the basis of the default. This applies regardless of the project.
In the federal context: “When a contractor challenges a default termination, the government bears the burden of establishing the validity of the termination.” Sergent’s Mechanical Systems, Inc. v. U.S., 2024 WL 4048175, *7 (Fed.Cl. 2024) (internal quotation and citation omitted). Once the government establishes the default, “the contractor bears the burden of establishing that the default was excused by fault of the government.” Id. at *8 (internal quotation and citation omitted).
Relevant considerations as to whether the contractor is in default include the contractor’s failure to meet contract specifications or the required schedule. Sergent’s Mechanical Systems, supra, at *8. “[T]here is ‘a requirement that the contractor give reasonable assurances of performance in response to a validly issued cure notice.” Id. (internal quotation and citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Acord Certificates of Liability Insurance: What They Don’t Tell You Can Hurt You
June 28, 2013 —
David McLainAs anyone involved in construction knows, one of the most heavily used forms for tracking insurance information during the subcontracting phase of a project is the Acord Certificate of Liability Insurance. General contractors often require subcontractors to provide these ubiquitous forms as evidence that the subcontractor maintains adequate insurance or insurance which complies with the requirements of the subcontract. Unfortunately, experience has shown that the Acord forms being used today are insufficient sources of the information needed by the developer and general contractor.
Historically, developers and GCs would require Acord forms to ensure that a subcontractor had a CGL insurance policy, with sufficient limits, and which named them as additional insureds. More recently, developers and GCs took the additional step of requiring a confirmation on the Acord forms that they were named as additional insureds for both ongoing and completed operations. This is important because coverage for ongoing operations only provides coverage during the construction process. Once the homes are put to their intended use, developers and GCs must be named as additional insureds for completed operations also in order to avail themselves of the benefits of the policy. Unfortunately, this is where the evolution of the use of the Acord forms ended, resulting in a failure to provide sufficient information to protect developers and GCs from the unknown.
My firm has had a rash of recent experience where our clients have not obtained the benefit of additional insured coverage for which they bargained because they relied on Acord forms which failed to provide sufficient information to allow them to protect themselves from insufficient insurance coverage on the part of the subcontractors with which they did business. For example, in one recent case a homeowners association alleged insufficient grading and drainage away from the homes within a development built by one of our clients. In reviewing the insurance information from the construction files, we found the Acord forms from the excavating company that performed all of the grading work around the homes. To our delight, the Acord form listed our client as an additional insured for both ongoing and completed operations.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLainDavid M. McLain can be contacted at
mclain@hhmrlaw.com
Colorado Court of Appeals Defines “Substantial Completion” for Subcontractors’ Work so as to Shorten the Period of Time in Which They Can Be Sued
October 20, 2016 —
David M. McLain – Colorado Construction Litigation BlogOver the past few years, there has been a battle raging on in district courts and arbitration hearing rooms throughout Colorado regarding when a subcontractor’s work is to be deemed “substantially complete,” for purposes of triggering Colorado’s six-year statute of repose. C.R.S. § 13-80-104 states, in pertinent part:
Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
* * *
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
C.R.S. § 13-80-104 (emphasis added).
As the battle raged on at the trial court level, subcontractors and design professionals argued that their work should be deemed “substantially complete” when they finished their discrete scope of work within a project. Developers and general contractors, seeking to maintain third-party claims against the subcontractors and design professionals, typically argued either that the subcontractors’ and design professionals’ work should be deemed “substantially complete” upon the issuance of the final certificate of occupancy on the project, or upon the issuance of the final certificate of occupancy for the last building within a project on which the subcontractor or design professional worked. Trial court judges and arbitrators have been split on this issue, with perhaps a slight majority favoring one or the other approaches advocated by developers and general contractors, that the subcontractors’ and design professionals’ work is “substantially complete” upon the issuance of the last certificate of occupancy in a project (the minority view) or upon the issuance of the last certificate of occupancy for the last building within a project on which the subcontractor of design professional worked (the majority view).
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Insurance Company’s Reservation of Rights Letter Negates its Interest in the Litigation
November 12, 2019 —
Frank Ingham - Colorado Construction LitigationThe Colorado Court of Appeals held that an insurance company, which issues a reservation of rights letter to its insured, loses its interest in the litigation, pursuant to C.R.C.P. 24(a)(2), when the insured settles the claims and assigns the bad faith action against the insurance company to the plaintiff. Bolt Factory Lofts Owners Association, Inc. v. Auto-Owners Insurance Company, 2019WL 3483901(Colo. App. 2019).
In a 2016 lawsuit in Denver District Court, 2016CV3360, the Bolt Factory Loft Owners Association, Inc. (“Association”) asserted construction defect claims against six contractors. Two of those contractors then asserted claims against other subcontractors, including Sierra Glass Co., Inc. (“Sierra Glass”). After multiple settlements, the only remaining claims were those the Association, as assignee of the two contractors, asserted against Sierra Glass.
Auto-Owners Insurance Company (“AOIC”) issued policies to Sierra Glass and defended it under a reservation of rights. The policy afforded AOIC the right to defend Sierra Glass, and it required Sierra Glass to cooperate in the defense of the legal action. The Association presented a settlement demand of $1.9 million to Sierra Glass, which AOIC refused to pay. To protect itself from an excess judgment that AOIC might not have paid, Sierra Glass entered into an agreement with the Association whereby Sierra Glass would refrain from offering a defense at trial and assign its bad faith claim against AOIC to the Association in exchange for the Association’s promise that it would not pursue recovery against Sierra Glass of any judgment entered against it at trial. Such agreements, known as Bashor or Nunn Agreements, are allowed in Colorado. Nunn v. Mid-Century Insurance Co., 244 P.3d 116 (Colo. 2010). Therefore, Sierra Glass was entitled to protect itself in the face of AOIC’s potential denial of coverage and refusal to settle. Bolt Factory Lofts, at ¶ 15.
Read the court decisionRead the full story...Reprinted courtesy of
Frank Ingham, Higgins, Hopkins, McLain & Roswell, LLCMr. Ingham may be contacted at
ingham@hhmrlaw.com
Building Down in November, Even While Home Sales Rise
January 17, 2013 —
CDJ STAFFThe Chicago Sun-Times reports that construction saw a small decline in November, the first since the spring. Happily, though this was the first dip in eight months, construction spending dropped only 0.3 percent, compared to October. The Sun-Times noted that the level of construction is well below what is considered healthy for the economy, while still being above the low of February 2011.
While fewer homes (and other buildings) were built, sales of new homes were up 4.4 percent in November. Home purchases were at their highest rate in more than two years.
Read the court decisionRead the full story...Reprinted courtesy of