Narrow Promissory Estoppel Exception to Create Insurance Coverage
August 07, 2022 —
David Adelstein - Florida Construction Legal UpdatesThere is an affirmative claim known as promissory estoppel. (Whereas equitable estoppel is used an affirmative defense, promissory estoppel is used as an affirmative claim.)
To prove promissory estoppel, a plaintiff must plead and prove the following three elements: “(1) a representation as to a material fact that is contrary to a later-asserted position; (2) a reasonable reliance on that representation; and (3) a change in position detrimental to the party claiming estoppel caused by the representation and reliance thereon.” Romo v. Amedex Ins. Co., 930 So.2d 643, 650 (Fla. 3d DCA 2006) (citation and quotation omitted). Stated differently: “A party will be estopped from denying liability under the principle of promissory estoppel when the party makes ‘[a] promise which the promisor should reasonably expect to induce action or forbearance of a definite and substantial character on the part of the promisee and which does induce such action or forbearance…[and] injustice can be avoided only by enforcement of the promise.’” Criterion Leasing Group v. Gulf Coast Plastering & Drywall, 582 So.2d 799, 800 (Fla. 1st DCA 1991).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Fixing That Mistake
October 25, 2021 —
Patrick Barthet - Construction ExecutiveSomeone once said, more people could learn from their mistakes if they weren’t so busy denying that they made them in the first place.
In the construction industry, mistakes are not uncommon. Addressing them, however, can be complicated. What should a contractor do when the project owner says some aspect of the project is not satisfactorily completed or isn’t performing as it should? Should the contractor wait, hoping it may get resolved without having to do anything? Or should the contractor take on the repair or replacement as soon as practically possible?
Doing nothing may be easy but can expose the contractor to significant subsequent liability. Dealing with the issue, on the other hand, could result in the destruction of what might later be required evidence in any litigation which develops. Considered “spoliation,” such manipulation or elimination of evidence is a consequence to be avoided. Even though done with the best of intentions to fix a problem, the process can wind up exposing one to liability and damages.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
Colorado Court of Appeals Defines “Substantial Completion” for Subcontractors’ Work so as to Shorten the Period of Time in Which They Can Be Sued
October 20, 2016 —
David M. McLain – Colorado Construction Litigation BlogOver the past few years, there has been a battle raging on in district courts and arbitration hearing rooms throughout Colorado regarding when a subcontractor’s work is to be deemed “substantially complete,” for purposes of triggering Colorado’s six-year statute of repose. C.R.S. § 13-80-104 states, in pertinent part:
Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
* * *
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
C.R.S. § 13-80-104 (emphasis added).
As the battle raged on at the trial court level, subcontractors and design professionals argued that their work should be deemed “substantially complete” when they finished their discrete scope of work within a project. Developers and general contractors, seeking to maintain third-party claims against the subcontractors and design professionals, typically argued either that the subcontractors’ and design professionals’ work should be deemed “substantially complete” upon the issuance of the final certificate of occupancy on the project, or upon the issuance of the final certificate of occupancy for the last building within a project on which the subcontractor or design professional worked. Trial court judges and arbitrators have been split on this issue, with perhaps a slight majority favoring one or the other approaches advocated by developers and general contractors, that the subcontractors’ and design professionals’ work is “substantially complete” upon the issuance of the last certificate of occupancy in a project (the minority view) or upon the issuance of the last certificate of occupancy for the last building within a project on which the subcontractor of design professional worked (the majority view).
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Who is Responsible for Construction Defect Repairs?
August 24, 2017 —
Laura Parsons-CDJ STAFFAn appellate court has ruled that the sponsor and not the condo board is responsible for repairing construction defects at 50 Madison Avenue, a multi-story apartment building in New York City across from Madison Square Park, Habitat reported. Plaintiff’s Simon and Ludmilla Lorne have brought upon three lawsuits in a legal battle lasting a decade.
The first came in 2007, two years after the Lorne’s purchased their $3 million seventh-floor apartment. At that time, the sponsor offered to repair the concrete slab under the hardwood floors that had not been properly leveled. However, the Lorne’s and the condo board disagreed about who and how the repairs would be accomplished. The second lawsuit wherein the court ruled that repairing the construction defects was the responsibility of the sponsor occurred in 2009. However, the Lorne’s sued the board yet again in 2015, citing failure to maintain and repair the building. Since the 2015 suit was based on the same allegations as the 2007 suit, it was dismissed by the judge.
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Finds that When it Comes to Intentional Interference Claims, Public Works Projects are Just Different, Special Even
November 21, 2017 —
Garret Murai - California Construction Law BlogOriginally published by CDJ on April 20, 2017
Earlier, we reported on a California Court of Appeals decision – Roy Allan Slurry Seal, Inc. v. American Asphalt South, Inc. – which held for the first time that a second-place bidder on a public works contract could sue a winning bidder who failed to pay its workers prevailing wages, under the business tort of intentional interference with prospective economic advantage.
Fast forward nearly two years, several amicus briefs, and “one doghouse”* later and the California Supreme Court has . . . reversed.
The Roy Allan Slurry Seal Case
To catch you up, or rather, refresh your recollection . . .
Between 2009 and 2012, American Asphalt South, Inc. was awarded 23 public works contracts totaling more than $14.6 million throughout Los Angeles, Orange, San Bernardino and San Diego counties. Two of the losing bidders on those projects – Roy Allan Slurry Seal, Inc. and Doug Martin Contracting, Inc. – sued American in each of these counties for intentional interference with prospective economic advantage as well as under the Unfair Practices Act (“UPA”) (Bus. & Prof. Code §§ 17000 et seq.) and the Unfair Competition Law (“UCL”) (Bus. & Prof. Code §17200).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
California Supreme Court Hands Victory to Private Property Owners Over Public Use
June 21, 2017 —
Sean M. Sherlock - Snell & Wilmer Real Estate Litigation BlogIn 1970 the California Supreme Court held that, under certain circumstances, private property owners impliedly dedicate their property to the public if they permit the public to use it. Gion v. City of Santa Cruz (1970) 2 Cal.3d 29. This holding was controversial, and the next year the California Legislature enacted Civil Code section 1009 limiting the public’s ability to permanently use private property through an implied dedication.
In the 40-plus years since then, the lower courts have wrestled with the issue of whether the statute limiting implied dedication applies only to recreational uses by the public, or also to nonrecreational uses. On June 15, 2017, the California Supreme Court issued its unanimous opinion in Scher v. Burke (June 15, 2017, S230104) ___ Cal.4th ___, holding that the limitations on implied dedication apply to nonrecreational as well as recreational uses. The case is significant because it demonstrates that the Supreme Court will apply the plain language of the state’s statutes to uphold private property rights.
Read the court decisionRead the full story...Reprinted courtesy of
Sean M. Sherlock, Snell & WilmerMr. Sherlock may be contacted at
ssherlock@swlaw.com
New WA Law Caps Retainage on Private Projects at 5%
May 29, 2023 —
Brett M. Hill & Ryanne S. Mathisen - Ahlers Cressman & Sleight PLLCThis month, Governor Jay Inslee signed into law a new statute that caps retainage on private construction projects to five percent (5%), provides a mechanism for subcontractors to get paid their retainage prior to project completion, and allows for contractors and subcontractors to post a retainage bond and get paid their retainage early. For those interested in reading the full text of this new law, the statute can be found
here.
The new statute goes into effect on July 23, 2023. Under the statute, when a contractor or subcontractor considers their work under a contract subject to retainage complete, they may notify the party they contracted to perform the work for. Within 15 days of receiving the notice of completion of work, the party receiving the notice must respond with either (1) notice of acceptance of work or (2) notice of uncompleted items to the contractor or subcontractor.
If the party receiving notice does not provide notice of uncompleted items within 15 days or fails to respond to the notice of completion entirely, the unpaid retainage will begin to accrue interest at a rate of one percent (1%) per month, 30 days after the initial 15-day period. However, this interest will not accrue against a contractor who has not been paid the retainage by an upper-tier contractor or owner until payment has been received, so long as that contractor has submitted its subcontractor’s notice of completion to the upper-tier contractor or owner within 30 days of receipt.
Reprinted courtesy of
Brett M. Hill, Ahlers Cressman & Sleight PLLC and
Ryanne S. Mathisen, Ahlers Cressman & Sleight PLLC
Mr. Hill may be contacted at brett.hill@acslawyers.com
Ms. Mathisen may be contacted at ryanne.mathisen@acslawyers.com
Read the court decisionRead the full story...Reprinted courtesy of
Structural Failure of Precast-Concrete Span Sets Back Sydney Metro Job
January 04, 2018 —
Chris Webb - Engineering News-RecordOriginally Published by CDJ on February 23, 2017
A key component of Australia’s biggest public transport infrastructure project—Sydney’s $6.3-billion Metro North West—is the subject of a critical and detailed technical report describing how an elevated viaduct span failed at a stitch joint between two precast segments during construction last September. Project officials say the affected span, which did not suffer a progressive collapse, has since been removed and its replacement fast-tracked to avoid further delays. Little additional detail was provided.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Webb, ENR