The “Right to Repair” Construction Defects in the Rocky Mountain and Plains Region
October 16, 2018 —
Jean Meyer & Sheri Roswell - Colorado Construction Litigation BlogIn excess of 30 states have enacted tort reform legislation requiring property owners to notify construction professionals of the presence of alleged construction defects prior to the commencement of a lawsuit. These statutes also often permit construction professionals to make an offer of repair within a statutorily defined period of time after receipt of a notice of claim letter. Undoubtedly, the notice-of-claim process has played a meaningful part in bringing construction professionals and claimants to timely resolutions of construction defect concerns in isolated instances.
However, while these statutes are commonly referred to as “right of repair” legislation, their practical effect is often reduced to little more than procedural empty gestures serving as a prelude to litigation. This article will briefly survey the “right to repair” statutes in Colorado, Montana, North Dakota and South Dakota. In Nebraska, New Mexico, Utah and Wyoming there is no right to repair or notice-of claim statue.
Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell LLC and
Sheri Roswell, Higgins, Hopkins, McLain & Roswell LLC
Mr. Bracken, may be contacted at meyer@hhmrlaw.com
Ms. Russo may be contacted at roswell@hhmrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Coverage Doomed for Failing Obtain Insurer's Consent for Settlement
January 22, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Fourth Circuit affirmed the district court's determination that there was no duty to indemnify after the insured settled without consent of the insurer. Perini/Tompkins Joint Venture v. ACE American Ins. Co., 2013 U.S. App. LEXIS 24865 (4th Cir. Dec. 16, 2013).
The insured, a joint venture, was hired as manager for the construction of a $900 million hotel and convention center. OCIP and excess policies were obtained through ACE. The project was also insured by a Builders Risk Policy through Factory Mutual Insurance Company.
During construction, a rod eroded, causing the atrium to collapse. Substantial property damage occurred and the completion of the project was delayed for several months.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Appeals Court Finds Manuscript Additional Insured Endorsements Ambiguous Regarding Completed Operations Coverage for Additional Insured
September 07, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Pulte Home Corp. v. American Safety Indemnity Co. (No. D070478; filed 8/30/17), a California appeals court found that manuscript additional insured endorsements on construction subcontractors’ policies were ambiguous regarding additional insured coverage for the developer, and that substantial evidence supported a finding that the insurer’s refusal to defend the developer was in bad faith. The court also approved awarding punitive damages on a one-to-one basis with the general damages. But the appeals court remanded the case for a further determination on the amount of Brandt fees, based on the developer’s change from a contingency to an hourly agreement.
The Pulte case arose from the development of two residential housing projects beginning in 2003 and sold in 2005-2006. Subcontractors were required to name Pulte as additional insured on their policies, some of them issued by American Safety. In 2013, homeowners sued Pulte based in part on the work of subcontractors insured by American Safety, which then denied coverage to Pulte because the construction had taken place years earlier.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Harmon Towers Duty to Defend Question Must Wait, Says Court
March 01, 2012 —
CDJ STAFFThe Harmon Towers project in Las Vegas was eventually halted short of the planned forty-seven stories after “it was determined that there was substantial defective construction, including defective installation of reinforcing steel throughout the Harmon.” The American Home Insurance Company and Lexington Insurance Company put forth a claim that they had no duty to defend Perini Construction, the builder of the defective Harmon Towers. Further, American Home seeks to recover the monies American reimbursed Perini. The United States District Court of Nevada ruled in the case of American Home Assurance Co. v. Perini Building on February 3, 2012.
The two insurance companies covered Perini and its subcontractors, Century Steel, Pacific Coast Steel, and Ceco Concrete Construction. Century Steel was the initial subcontractor for the reinforcing steel; they were later acquired by Pacific Coast Steel. In this current case, Perini Construction is the sole defendant.
Perini sought a dismissal of these claims, arguing that without the subcontractors joined to the case, “the Court cannot afford complete relief among existing parties.” The court rejected this claim, noting that the court can determine the duties of the insurance companies to Perini, which the court described as “separate and distinct from those of the subcontractors.” The subcontractors “have not claimed an interest in the subject matter of the action.” The court concluded that it could determine whether Perini was entitled or not to coverage without affecting the subcontractors. The court rejected Perini’s claim.
Perini also asked the court to abstain from the case, arguing that it was better heard in a state court. The court noted that several considerations cover whether a case is heard in state or federal courts. The court noted that if the case weighed heavily on state law, the state courts would be the obvious location. Further, if there were a parallel action in the state courts, “there is a presumption that the whole suit should be heard in state courts.” This is, however, no parallel state suit, although the court noted that Perini has “threatened” to do so.
However, the issue of who is to blame for the problems at Harmon Towers has not been resolved. The court concluded that until the “underlying action” was concluded, it was premature to consider the issues raised in this case while the earlier lawsuit was still in progress. The court denied Perini’s motion to dismiss the case. Given that the outcome of the earlier construction defect case may lead to further litigation in state court, the District Court granted Perini’s motion to abstain, but staying their judgment until the construction defect case is resolved.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Modernist Houses Galore! [visual candy for architects]
February 25, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaDo you like modern architecture? Is Frank Lloyd Wright someone you wish you could have met?
If so, then you’ll want to check out the new “Masters Gallery” of the North Carolina Modernist Houses (NCMH) group. With changes and additions announced this week, it’s Gallery is America’s largest open digital archive of Modernist houses, as well as the internationally known Modernist architects who designed them.
Currently, the Gallery showcases over 30 architects with extensive house histories and over 10,000 photos. The Gallery is extensive and searchable and includes, among many other notables, Frank Gehry and, of course, Frank Lloyd Wright.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback can be contacted at
mbrumback@rl-law.com
More Charges Anticipated in Las Vegas HOA Scam
February 28, 2013 —
CDJ STAFFWith almost forty people already charged in the conspiracy to take over Las Vegas homeowners associations in order to profit from construction defect claims, more charges are likely to come, according to an article in the Las Vegas Review Journal. The article also notes that the trial against Leon Benzer will involve millions of pages of documents. It is alleged that Benzer found straw purchasers for condominiums in order to control homeowner boards. Benzer’s firm, Silver Lining Construction, would then receive contracts to repair construction defects.
The Justice Department will be seeking restitution for the victims, which may total $25 million. Four individuals with connections to the conspiracy have died since investigations began. At least three of these deaths were suicides, and included Nancy Quon, who with Benzer are thought to be the main figures in the scam.
Read the court decisionRead the full story...Reprinted courtesy of
Disputes Over Arbitrator Qualifications: The Northern District of California Offers Some Guidance
August 10, 2021 —
Justin K. Fortescue - White and WilliamsThe selection of an arbitration panel can often lead to disputes between the parties regarding things like whether a particular candidate is qualified, whether a challenge to an arbitrator’s qualifications can be addressed pre-award and whether a party that names an unqualified arbitrator should lose the opportunity to name a replacement. In Public Risk Innovations v. Amtrust Financial Services, No. 21-cv-03573, 2021 U.S. Dist. LEXIS 129464 (N.D. Ca. July 12, 2021), the court provided answers on all three of these issues.
In Amtrust, the parties filed cross-motions to compel arbitration. Although both parties agreed the dispute was arbitrable, they disagreed about whether Public Risk Innovations, Solutions and Management’s (PRISM) arbitrator was qualified under the terms of the applicable contract. In seeking to have PRISM’s arbitrator disqualified, Amtrust argued that he: (1) was not a “current or former official of an insurance or reinsurance company”; and (2) was not “disinterested.” Amtrust also argued that because PRISM named an unqualified arbitrator (and presumably the time to appoint had passed), PRISM should be deemed to have failed to select an arbitrator as required by the contract and that Amtrust had the right to select a second arbitrator of its choice.
Read the court decisionRead the full story...Reprinted courtesy of
Justin K. Fortescue, White and WilliamsMr. Fortescue may be contacted at
fortescuej@whiteandwilliams.com
High Court Could Alter Point-Source Discharge Definition in Taking Clean-Water Case
March 18, 2019 —
Mary B. Powers - Engineering News-RecordThe U.S. Supreme Court's decision to review lower court rulings on whether a permit is required under the federal Clean Water Act when pollutants originate from a point source but are carried to navigable waters by a non-point source such as groundwater could set some new parameters for compliance, observers say.
Read the court decisionRead the full story...Reprinted courtesy of
Mary B. Powers, ENRENR may be contacted at
ENR.com@bnpmedia.com