The Anatomy of a Construction Dispute Stage 2- Increase the Heat
January 21, 2015 —
Christopher G. Hill – Construction Law MusingsLast week we discussed the groundwork and circumstances of a construction claim. This week’s post will discuss the next steps, hopefully short of full blown arbitration or litigation that you, as a construction company, can pursue presuming your claim has been properly preserved.
If your contract requires certain steps such as informal resolution attempts or other items, these are the first things that must be done while still preserving your rights to pursue all remedies available. Instituting such contractually required resolution steps can and should be the first “notch” on the dial of increased pressure on the Owner, General Contractor or possibly Subcontractor against whom you have a claim.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Colorado Court of Appeals Defines “Substantial Completion” for Subcontractors’ Work so as to Shorten the Period of Time in Which They Can Be Sued
October 20, 2016 —
David M. McLain – Colorado Construction Litigation BlogOver the past few years, there has been a battle raging on in district courts and arbitration hearing rooms throughout Colorado regarding when a subcontractor’s work is to be deemed “substantially complete,” for purposes of triggering Colorado’s six-year statute of repose. C.R.S. § 13-80-104 states, in pertinent part:
Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
* * *
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
C.R.S. § 13-80-104 (emphasis added).
As the battle raged on at the trial court level, subcontractors and design professionals argued that their work should be deemed “substantially complete” when they finished their discrete scope of work within a project. Developers and general contractors, seeking to maintain third-party claims against the subcontractors and design professionals, typically argued either that the subcontractors’ and design professionals’ work should be deemed “substantially complete” upon the issuance of the final certificate of occupancy on the project, or upon the issuance of the final certificate of occupancy for the last building within a project on which the subcontractor or design professional worked. Trial court judges and arbitrators have been split on this issue, with perhaps a slight majority favoring one or the other approaches advocated by developers and general contractors, that the subcontractors’ and design professionals’ work is “substantially complete” upon the issuance of the last certificate of occupancy in a project (the minority view) or upon the issuance of the last certificate of occupancy for the last building within a project on which the subcontractor of design professional worked (the majority view).
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Substantial Completion Explained: What Contractors & Owners Should Know
January 17, 2022 —
Travis Colburn - Ahlers Cressman & SleightA project’s Substantial Completion date is a critical construction milestone for contractors and owners. Depending on the contract, the date of Substantial Completion has project-specific contractual and statutory consequences.
Substantial Completion is an “event” – there is no universal definition of the term. It is generally understood to be (1) a point in time (2) when work performed by the contractor is sufficiently complete (3) where it can be used or occupied for the owner’s intended purpose. The date of Substantial Completion is generally established at the time of contract formation (either as a negotiated or a contract set date), and that date may be adjusted over the course of a project to account for excusable delays.
As a construction professional, your attorney should review and tailor any written agreement to your project-specific needs and risk tolerances prior to execution. Savvy construction professionals often start with standard form agreements promulgated by the American Institute of Architects (“AIA”), the Design-Build Institute of America (“DBIA”), or the Engineers Joint Contract Document Committee (“EJCDC”) as the basis for their construction contracts. The AIA, DBIA, and EJCDC standard forms each contains contract provisions relating to when and what happens once Substantial Completion has occurred, subject to any agreed-to, project-specific deviations.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
Renee Mortimer Recognized as "Defense Lawyer of the Year" by DTCI
December 13, 2022 —
Renee Mortimer - Lewis BrisboisHighland, Ind. (November 21, 2022) - Northwest Indiana Managing Partner Renee J. Mortimer was recently named "Defense Lawyer of the Year" by the Defense Trial Counsel of Indiana (DTCI). She was officially recognized at a Board & Officers dinner the evening before the DTCI's annual conference, which took place in Michigan City, Indianapolis from November 17 to 18.
The DTCI gives out three awards every year as part of its annual conference, including "Defense Lawyer of the Year," "Diplomat," and "Outstanding Young Lawyer." This year, two recipients received the "Diplomat" recognition
"I am honored to receive this recognition from my peers and look forward to continuing my work with the DTCI," said Ms. Mortimer.
Read the court decisionRead the full story...Reprinted courtesy of
Renee Mortimer, Lewis BrisboisMs. Mortimer may be contacted at
Renee.Mortimer@lewisbrisbois.com
Home Prices on the Rise
September 03, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to CoreLogic, in July, housing prices rose 6.9% compared to last year, reported Housing Wire. Furthermore, prices increased by 1.7% compared to June 2015.
“Home sales continued their brisk rebound in July and home prices reflected that, up 6.9% from a year ago,” Frank Nothaft, chief economist for CoreLogic, told Housing Wire. “Over the same period, the National Association of Realtors reported existing sales up 10% and the Census Bureau reported new home sales up 26% in July.”
Read the court decisionRead the full story...Reprinted courtesy of
Fifth Circuit Finds Duty to Defend Construction Defect Case
March 14, 2022 —
Tred R. Eyerly - Insurance Law HawaiiReversing the judgment of the district court, the Fifth Circuit found the insurer owed a defense in a construction defect case. Siplast, Inc. v. Emplrs Mut. Cas. Co., 2022 U.S. App. LEXIS 795 (5th Cir. Jan. 11, 2022).
The Archdiocese of New York sued various parties for a roofing project at a high school in the Bronx. Siplast, the roofing manufacturer, was included as a defendant. The underlying lawsuit arose from the Archdiocese purchase of a roof membrane system from Siplast. Siplast guaranteed that the roof membrane system would remain "in a watertight condition for a period of 20 years . . . or Siplast will repair the Roof Membrane System at its own expense."
After installation of the roof, school officials noticed water damage in the ceiling tiles throughout the school after a rain storm. Siplast attempted to repair the damage, but was unsuccessful. Siplast later informed the Archdiocese that the guarantee would not be honored regarding any permanent improvements of the roof. The Archdiocese filed suit against Siplast and the installing contractor. The cause of action against Siplast was for breach of the guarantee.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Brenda Radmacher to Speak at Construction Super Conference 2024
November 05, 2024 —
Brenda Radmacher - The Construction SeytBrenda Radmacher, partner in Seyfarth’s Construction group, will present and moderate panels at the 38thAnnual Construction Super Conference 2024 on December 9-11. The conference is recognized as the preeminent construction conference developed for mid to senior-level professionals working in legal and commercial construction markets.
Panel – Looking Around Corners: Emerging Trends and Proactive Solutions
Brenda will co-present a panel on innovative ways to engage experts in construction disputes, focusing on early expert involvement to aid in risk management, issue analysis, mitigation, and documentation for potential litigation.
Panel – Top 10 Issues to Address in Your ADR Process for a Better Solution in Construction Disputes
Read the court decisionRead the full story...Reprinted courtesy of
Brenda Radmacher, SeyfarthMs. Radmacher may be contacted at
bradmacher@seyfarth.com
New Research Shows Engineering Firms' Impact on Economy, Continued Optimism on Business Climate
October 28, 2024 —
The ACEC Research InstituteWASHINGTON – The ACEC Research Institute – the leading source of original research for the business of engineering – released the results of two important studies on the current and future state of the engineering industry, and its role in the overall U.S. economy.
The reports, the
2024 Economic Assessment of the Engineering & Design Services Industry and the
Engineering Business Sentiment Report for 2024 Q4, both point to continued optimism for the industry and its firms, though somewhat softened compared to previous quarters.
"This research shows the outsized impact the engineering industry has on the American economy," said ACEC Research Institute Chair Mike Carragher. "As the engineering industry's contributions grow year over year, the Institute's research helps firm executives position their businesses for a successful future."
All told, the industry added $656 billion to the U.S. GDP in 2023, supported well over five million jobs directly or indirectly, and contributed $92 billion to federal tax coffers, with an additional $44 billion in state and local taxes.
Overall, the report found that the engineering and design services industry has continued to build on its year-over-year post-COVID gains, growing 5.5% in 2023 to $436 billion, with much of that growth driven by infrastructure projects. Non-residential and non-building construction, flush with government funding through the IIJA and Inflation Reduction Act, remained on an upward trajectory.