Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses
April 25, 2012 —
Douglas Reiser, Builders Council BlogEver had that lingering problem with a contracting partner that went away for awhile and then came back to bite you ? years later? In Washington, construction contract claims can be raised for up to six years after substantial completion. Six years!? Why would I want to wait that long to find out if I have a problem? You don’t have to.
Over the past few years, I have discussed the notion of “contractual claim periods” on The Builders Counsel. For today’s Save a Legal Fee column, I cannot think of a better topic. These provisions are specifically intended to save you from unnecessary legal fees that might arise if a problem goes unnoticed for too long.
Contractual claim periods are simply a way to reduce the amount of time that a contracting party has to raise a claim against its contracting partner. For example, a subcontractor might require that a general contractor raise any claim that it might have ? for defective or incomplete work, injury, damages, etc ? within a particular amount of time or forever lose the ability to raise the claim in a legal proceeding.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractual Assumption of Liability Does Not Bar Coverage
August 27, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Michigan Court of Appeals rejected the insurer's argument that coverage was barred for the insured's contractual assumption of liability of another. Travelers Prop. Cas. Co. of Am v. Peaker Serv., Inc., 2014 WL 3605680 (Mich. Ct. App. July 22, 2014).
The contractor was hired to install an "electronic over-speed system" at the University of Michigan. The hope was that the new system would prevent the steam turbines at the central power plant from turning too quickly. The parties' contract provided,
“Section 15.18. Supplier Damage to University Property. Without regard to any other section of the Agreement, Supplier shall be responsible for the costs to return to ‘as was’ condition from any damage caused to the building, grounds, or other equipment and furnishings caused in whole or part by Supplier Personnel while performing activities arising under this Agreement.”
The contractor improperly calibrated the system, causing one of the university's turbines to operate at twice the safe operational speed, causing significant damage to the generator equipment. The university sued the contractor for more than $3 million in damages. Travelers defended, but filed a declaratory judgment action, contending that coverage did not exist because the "contractual liability" exclusion applied. Section 15.18 of the contract purportedly constituted an "assumption" of the insured's own liability, and was therefore not covered under the CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Don’t Let Construction Problems Become Construction Disputes (guest post)
October 01, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaTo start our week off right, today we have another important article from guest blogger Christopher G. Hill, LEED AP. Chris is a Virginia Supreme Court certified mediator, construction lawyer and owner of the Richmond, VA firm, The Law Office of Christopher G. Hill, PC. He authors the Construction Law Musings blog where he discusses legal and policy issues relevant to construction professionals. His practice concentrates on mechanic’s liens, contract review and consulting, occupational safety issues (VOSH and OSHA), and risk management for construction professionals. [His blog was also one of the first construction law blogs I found and followed, even if he is a Duke alum!] Take it away, Chris!
First and foremost, thanks to Melissa for inviting me back to post here at her great blog. She continues to invite me back despite my being a Blue Devil (and I try not to hold her Tar Heel status against her).
So much of discussion relating to construction law and construction lawyers centers on the litigation of disputes. This discussion comes in many forms from avoidance of such litigation through the early intervention of good counsel prior to getting into a project to what sort of resolution mechanism to use. Another branch of this discussion is essentially the right way to pursue your claim (or as some may read it start the dispute ball rolling). Sometimes a payment bond claim is the best method while others a straight up contractual suit is the best way to go.
Of course, all of this discussion presumes that there will be disputes. While I agree to some degree that in the Murphy’s Law riddled world of commercial construction, problems will arise. These problems need not rise to the level of a dispute that requires outside (read court or arbitrator) intervention. A few tips that are easy to write, but admittedly hard to practice at times can hopefully keep problems from blossoming into disputes. I’ve listed three big ones here:
1.Use “in house counsel.” Yes, I know that most of you engineers, architects, commercial general contractors and subcontractors out there aren’t big enough to either want or need a full time attorney on the payroll. What I mean by this is that when problems occur (or preferably before doing so), give your friendly local construction lawyer a call. As I learned from my dad, an ounce of prevention and all that. That 10 minute phone call may help avoid many hours of time and bills from your attorney later down the road.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Supreme Court of Oregon Affirms Decision in Abraham v. T. Henry Construction, et al.
April 20, 2011 —
Beverley BevenFlorez CDJ STAFFAfter reviewing the decision in Abraham v. T. Henry Construction, et al., the Oregon Supreme Court affirmed that a tort claim for property damage arising from construction defects may exist even when the homeowner and the builder are in a contractual relationship.
When the case was initially filed, the plaintiffs alleged breach of contract and negligence. The defendants moved for summary judgment arguing that one, the claim was barred by the six-year statute of limitations and two, no special relationship (such as one between a doctor and patient) existed. The court agreed with the defendants. However, the Court of Appeals while affirming the trial court’s decision on breach of contract reversed the decision on negligence. The Court of Appeals stated that an administrative or statute rule could establish a standard of care independent from the contract.
The Oregon Supreme Court gave an example of cases where a tort claim could exist when a contract is present: “If an individual and a contractor enter into a contract to build a house, which provides that the contractor will install only copper pipe, but the contractor installs PVC pipe instead (assuming both kinds of pipe comply with the building code and the use of either would be consistent with the standard of care expected of contractors), that failure would be a breach of contract only. […] If the failure to install the copper pipe caused a reduction in the value of the house, the plaintiff would be able to recover that amount in an action for breach of contract. […] On the other hand, if the contractor installed the PVC pipe in a defective manner and those pipes therefore leaked, causing property damage to the house, the homeowner would have claims in both contract and tort. […] In those circumstances, the obligation to install copper instead of PVC pipe is purely contractual; the manner of installing the pipe, however, implicates both contract and tort because of the foreseeable risk of property damage that can result from improperly installed pipes.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Three Recent Cases Strike Down Liquidated Damages Clauses In Settlement Agreements…A Trend Or An Aberration?
November 01, 2021 —
Adam M. Tuckman - ConsensusDocsBeginning more than one century ago, owners and contractors generally have adopted the convention of including liquidated damages in their contracts to fix potential liability for delay (and other losses) at the inception of the project. The proliferation of liquidated damages clauses in modern contracts can be attributed to economic and legal factors. From the owner’s standpoint, it may be exceedingly difficult to prove the actual cost impact of a delayed completion of the project. A properly calculated liquidated damages rate would save the owner the significant expense of quantifying its delay damages. On the contractor’s side, a reasonable amount of liquidated damages may be preferable to uncapped or unknown liability, allowing the contractor to more accurately price its bid and efficiently allocate risk.
Coinciding with, or perhaps a leading cause of, the industry’s embrace of liquidated damages provisions, was the shift in courts throughout the country from disfavoring such clauses to accepting them (within limits) as an appropriate exercise of contract rights. While some variation exists among the states, courts have generally recognized that liquidated damages clauses are a viable alternative to proof of actual loss so long as (i) actual losses were difficult to quantify, and (ii) the stipulated sum bears a reasonable relationship to the anticipated loss at the time of contracting. See, e.g., Restatement (Second) of Contracts § 356. Conversely, a clause that penalizes the breaching party rather than serving as an estimate of probable loss is likely to be found unenforceable.
Read the court decisionRead the full story...Reprinted courtesy of
Adam M. Tuckman, Watt, Tieder, Hoffar, & Fitzgerald, LLPMr. Tuckman may be contacted at
atuckman@watttieder.com
Utah’s Highest Court Holds That Plaintiffs Must Properly Commence an Action to Rely on the Relation-Back Doctrine to Overcome the Statute of Repose
August 20, 2018 —
Shannon M. Warren - The Subrogation StrategistEarlier this summer, in Gables & Villas at River Oaks Homeowners Ass’n v. Castlewood Builders LLC, 2018 UT 28, the Supreme Court of Utah addressed the question of whether the plaintiff’s construction defects claims against the general contractor for a construction project were timely-filed, or barred by the statute of repose. In Utah, the statute of repose requires that an action be “commenced within six years of the date of completion.” The plaintiff alleged that its 2014 amended complaint naming the general contractor as a defendant was timely-commenced because, before the date on which Utah’s statute of repose ran, a defendant filed a motion to amend its third-party complaint to name the general contractor as a defendant, and the defendant subsequently assigned its claims to the plaintiff. The plaintiff argued that the filing of its 2014 amended complaint related back[1] to the date of its original complaint. The Supreme Court disagreed, holding that an action is “commenced” by filing a complaint and that a motion for leave to amend does not count as “commencing” an action.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon M. Warren, White and Williams LLPMs. Warren may be contacted at
warrens@whiteandwilliams.com
Filing Motion to Increase Lien Transfer Bond (Before Trial Court Loses Jurisdiction Over Final Judgment)
May 15, 2023 —
David Adelstein - Florida Construction Legal UpdatesIf a construction lien is recorded against real property, the lien can be transferred to a lien transfer bond. This transfers the security or collateral of the construction lien from the real property to the lien transfer bond. The lien transfer bond can be a bond posted by a surety company or it can be cash. This is governed by Florida Statute s. 713.24. The amount of the lien does not dictate the amount of the lien transfer bond. Rather, the lien transfer bond needs to be in the amount of the lien, plus interest on that amount for three years, plus $1,000 or 25% of the amount of the lien (whichever is greater so factor in the 25%) to cover attorney’s fees. Fla. Stat. 713.24(1).
If you are looking to transfer a construction lien to a lien transfer bond, make sure to consult with counsel.
Keep in mind there is a statutory mechanism for a lienor to increase the lien transfer bond to cover attorney’s fees and costs and notice the word “must” in the statute below. Pursuant to Florida Statute s. 713.24(3):
Any party having an interest in such security or the property from which the lien was transferred may at any time, and any number of times, file a complaint in chancery in the circuit court of the county where such security is deposited, or file a motion in a pending action to enforce a lien, for an order to require additional security, reduction of security, change or substitution of sureties, payment of discharge thereof, or any other matter affecting said security. If the court finds that the amount of the deposit or bond in excess of the amount claimed in the claim of lien is insufficient to pay the lienor’s attorney’s fees and court costs incurred in the action to enforce the lien, the court must increase the amount of the cash deposit or lien transfer bond. Nothing in this section shall be construed to vest exclusive jurisdiction in the circuit courts over transfer bond claims for nonpayment of an amount within the monetary jurisdiction of the county courts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
MGM Seeks to Demolish Harmon Towers
September 01, 2011 —
CDJ STAFFCiting public safety concerns and the cost of repair, MGM Resorts International is seeking to demolish the unfinished hotel tower. The company has a few hurdles to go through before they start laying the charges to implode the structure. Any plans would have to be approved by not only Clark County officials, but also the district court has an order blocking any activity during litigation between MGM and the general contractor on the project, Perini Building Company.
Architectural Record reports that MGM states it would take “approximately 18 months to conduct test and come up with an approved, permitted design to fix the Harmon.” MGM feels that repairs would then take another two to three years. Perini contends that they could “provide stamped drawings detailing all necessary repairs within three months.” They attribute MGM’s desire to demolish the building as “buyer’s remorse.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of