Cumulative Impact Claims and Definition by Certain Boards
June 21, 2024 —
David Adelstein - Florida Construction Legal UpdatesWhat is a cumulative impact claim? This is commonly referred to as the unforeseeable ripple effect of changes, i.e., the death by a thousand cuts. Cumulative impact claims refer to a disruption on productivity based on the cumulative impact of changes and their impact on unchanged work. Cumulative impact claims are difficult claims to prove, particularly based on the causation standpoint (and argument they could be released based on change order language). If pursuing or considering a cumulative impact claim, you will need to work with a consultant(s) and lawyer that understand the dynamic of these claims to best maximize your arguments and recovery from a causation and damages standpoint. Cumulative impact damages are real. They occur. But they are not damages you can just throw out there or use loosely and expect to develop traction on compensation.
Below is how cumulative impact claims are defined by certain Boards of Contract Appeals. The definitions are important.
In Appeal of Centex Bateson Construction, Co., Inc., 9901 BCA P 30153, VABCA 4613 (VABCA 1998), the Board explained:
Direct impact, as the immediate and direct effect of a change on unchanged work, is considered foreseeable.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Defects Uncertain Role in Coverage in Pennsylvania
February 04, 2013 —
CDJ STAFFDouglas E. Cameron, Jay M. Levin, and Traci S. Rea look at the implications of a pair of Pennsylvania court decisions from 2012. The judge in both cases, Judge Wettick of the Allegheny County Court of Common Pleas held that comprehensive general liability policies do not cover any claims that arise from faulty workmanship.
The three conclude that "these holdings may preclude coverage for any tort claims asserted against your company if the allegations involve construction defects, even if you are sued for property damage or personal injury by a third party to your construction contract." They note that both decisions have been appealed to the Pennsylvania Superior Court.
Read the court decisionRead the full story...Reprinted courtesy of
Design-Build Contracting: Is the Shine Off the Apple?
March 09, 2020 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCThe design-build delivery method offers many benefits to owners. Among the cited benefits are that projects are generally completed faster, at a lower cost, by allowing innovative approaches through early and continual contractor involvement in the design process. The design contractor serves as a single point of contact responsible for both the design and construction of the project.
The Washington State Department of Transportation (“WSDOT”) utilized the design-build procurement method on the largest project ($2 billion) of its type in the state of Washington: the Highway 99 Tunnel, which was finished almost three years late after the tunnel-boring machine (“Bertha”) broke down six years ago. The sorted tale of the SR-99 Tunnel Project was the source of many of this firm’s blog articles.[1] The State of Washington staunchly maintained that the design-build contract protected its taxpayers from covering the repair costs to the tunnel-boring machine when it broke down in 2013. Bertha did not resume tunneling for almost two years, putting on hold removal of the Alaska Way viaduct and rebuilding of the Seattle Waterfront without an elevated highway.
In December 2013, the contractor for the project, Seattle Tunnel Partners (“STP”), contended that a 110-foot long 8” steel pipe which Bertha hit caused the breakdown. That pipe had been installed for groundwater testing by WSDOT in 2002 during its preliminary engineering for the viaduct replacement project. The project’s Dispute Review Board (“DRB”) composed of three tunneling experts found that the pipe constituted a “differing site condition” for which the State was responsible to disclose to contractors. The Board, whose views were non-binding, did not opine about how much damage the undisclosed pipe cost.[2] In other words, the mere fact that a differing site condition occurred did not establish that there was a causal connection between the damages which STP was seeking (in excess of $600 million) and the differing site condition (the 8” steel pipe which WSDOT lawyers at trial derisively referred to as “nothing more than a toothpick for Bertha’s massive cutter head”). STP maintained that Bertha had made steady progress except for three days immediately after hitting the pipe. It didn’t help the contractors’ case that during the discovery phase of the two-month trial, WSDOT lawyers uncovered documents showing that the contractor’s tunnel workers encountered and logged the pipe before digging began.[3]
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
Florida Continues Enacting Tort Reforms, This Time Shortening the Statute of Repose
May 01, 2023 —
William L. Doerler - The Subrogation StrategistOn April 13, 2023, Florida’s governor, Ron DeSantis, signed into law
SB 360 which, among other things, shortens the statute of repose period for improvements to real property. The law also revises the date on which the statute of limitations period runs for these types of damage claims. Florida’s revision of this law provides further evidence of the state’s tort reform efforts.
The new law went into effect upon signing and includes the following changes:
- Shortens the statute of repose period set forth in Fla. Stat. § 95.11(3)(c) for actions founded on the design, planning or construction of improvements to real estate from ten (10) to seven (7) years. The statute of repose period runs from the earliest (rather than the latest) of the date: a) the authority having jurisdiction issues a temporary certificate of occupancy; b) a certificate of occupancy; c) a certificate of completion; or d) of abandonment of construction if not completed. Of note, the revised repose period eliminates that date of actual possession by the owner as one of the accrual dates.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Build Me A Building As Fast As You Can
March 15, 2021 —
Jodi Stein & Jennifer Dickson - Sheppard Mullin Construction & Infrastructure Law BlogNot your average game of patty-cake! Earlier this week, New York’s First Department, Appellate Division issued its decision related to 200 Amsterdam,[1] overturning the lower court’s decision which would have required 200 Amsterdam to remove several floors of its building in order to comply with zoning. The lower court determined that the NYC Zoning Resolution did not permit a developer to utilize a portion of a tax lot to merge with a neighboring zoning lot.
Known as the “gerrymandered zoning lot,” the developer of 200 Amsterdam included portions of neighboring tax lots in its zoning lot in order to transfer air rights from those portions of tax lots to be utilized in 200 Amsterdam’s 55-story development. The inclusion of partial tax lots in a zoning lot is not expressly discussed in the NYC Zoning Resolution, but was permitted by a 1978 Department of Buildings memo. While challenges to 200 Amsterdam started in 2017, the developer moved forward with the construction of its development under lawfully issued building permits.
Reprinted courtesy of
Jodi Stein, Sheppard Mullin and
Jennifer Dickson, Sheppard Mullin
Ms. Stein may be contacted at jstein@sheppardmullin.com
Ms. Dickson may be contacted at jdickson@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of
Cultivating a Company Culture Committed to Safety, Mentorship and Education
March 19, 2024 —
David Frazier - Construction ExecutiveThe construction industry is aging. Valuing the significance of promoting a culture that enhances safety, mentorship and educational opportunities is essential to recruiting and retaining top talent to keep the industry thriving.
According to the U.S. Department of Labor, one in five worker deaths in the U.S. occurs in the construction industry. Additionally, construction workers are statistically at a higher risk for mental-health issues than virtually every other profession. According to a study conducted by CIRP, 83% of construction workers have struggled with mental-health disorders.
Today’s leaders must be dedicated to listening to employees' voices to shape the construction industry, as future leaders will be formed by a culture committed to employees' mental and physical health, safety, professional growth and overall workplace culture.
Reprinted courtesy of
David Frazier, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Remote Work Issues to Consider in Light of COVID-19
March 23, 2020 —
Philip K. Lem - Payne & FearsMany employers have elected to implement a remote work policy in light of the COVID-19 coronavirus outbreak. If you are one of them, you should consider the following as you transition your workforce to a remote working environment.
Preliminary Steps
The first step prior to implementation is ensuring that you have sufficient technological infrastructure and capabilites. You should assess what types of equipment (e.g., desktop computers, laptops, phones, printers, and office supplies) your employees will need to work remotely, and ensure that there is sufficient inventory and that employees can gain access to the equipment. You should also confirm that you have data security measures in place and brief employees on best practices for security and protection of data. You should refer employees to your organization’s technology policy regarding the safeguarding of data. If none exist, you should strongly consider creating and implementing one. One of the more important aspects of any policy is restrictions on where employees may work remotely. For example, some employers prohibit employees from working remotely on public wifi networks due to security concerns. Whether these or other policies are right for your organization depends on the nature of your work and data, security measures you have in place, and your risk tolerance.
Beyond technology issues, you should prepare a checklist of necessary work items and materials that employees will need to perform their jobs remotely. You should also clearly communicate to employees which items may be removed from the workplace and taken home and which should remain.
Read the court decisionRead the full story...Reprinted courtesy of
Philip K. Lem, Payne & FearsMr. Lem may be contacted at
pkl@paynefears.com
Massive Danish Hospital Project Avoids Fire Protection Failures with Imerso Construction AI
December 23, 2023 —
Aarni Heiskanen - AEC BusinessEnsuring regulatory compliance of firewall constructions is getting a high-tech boost. Over the past 16 months, the construction team responsible for the iconic new Nyt Hospital Nordsjælland near Copenhagen used Imerso construction AI technology to achieve remarkable results. By using Imerso, the team enhanced work productivity while preventing costs and delays worth €5.2 million during the construction of the superstructure.
Inspired by this success, the team led by Project Manager Anders Kaas has since been eager to explore the potential of the technology in other areas. The opportunity arose to address a topic that has traditionally posed significant challenges and expenses in numerous construction projects – ensuring regulatory compliance of fire barriers and firewall constructions.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at