Harmon Towers Duty to Defend Question Must Wait, Says Court
March 01, 2012 —
CDJ STAFFThe Harmon Towers project in Las Vegas was eventually halted short of the planned forty-seven stories after “it was determined that there was substantial defective construction, including defective installation of reinforcing steel throughout the Harmon.” The American Home Insurance Company and Lexington Insurance Company put forth a claim that they had no duty to defend Perini Construction, the builder of the defective Harmon Towers. Further, American Home seeks to recover the monies American reimbursed Perini. The United States District Court of Nevada ruled in the case of American Home Assurance Co. v. Perini Building on February 3, 2012.
The two insurance companies covered Perini and its subcontractors, Century Steel, Pacific Coast Steel, and Ceco Concrete Construction. Century Steel was the initial subcontractor for the reinforcing steel; they were later acquired by Pacific Coast Steel. In this current case, Perini Construction is the sole defendant.
Perini sought a dismissal of these claims, arguing that without the subcontractors joined to the case, “the Court cannot afford complete relief among existing parties.” The court rejected this claim, noting that the court can determine the duties of the insurance companies to Perini, which the court described as “separate and distinct from those of the subcontractors.” The subcontractors “have not claimed an interest in the subject matter of the action.” The court concluded that it could determine whether Perini was entitled or not to coverage without affecting the subcontractors. The court rejected Perini’s claim.
Perini also asked the court to abstain from the case, arguing that it was better heard in a state court. The court noted that several considerations cover whether a case is heard in state or federal courts. The court noted that if the case weighed heavily on state law, the state courts would be the obvious location. Further, if there were a parallel action in the state courts, “there is a presumption that the whole suit should be heard in state courts.” This is, however, no parallel state suit, although the court noted that Perini has “threatened” to do so.
However, the issue of who is to blame for the problems at Harmon Towers has not been resolved. The court concluded that until the “underlying action” was concluded, it was premature to consider the issues raised in this case while the earlier lawsuit was still in progress. The court denied Perini’s motion to dismiss the case. Given that the outcome of the earlier construction defect case may lead to further litigation in state court, the District Court granted Perini’s motion to abstain, but staying their judgment until the construction defect case is resolved.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Court Upholds Plan to Eliminate Vehicles from Balboa Park Complex
June 10, 2015 —
Kristen Lee Price and Lawrence S. Zucker II – Haight Brown & Bonesteel LLPIn Save Our Heritage Organisation v. City of San Diego, et al. (No. D063992, filed 5/28/15), the California Court of Appeal for the Fourth Appellate District upheld a controversial plan to eliminate vehicles from various plazas in historic Balboa Park. In reaching its decision, the Court of Appeal considered a question of first impression involving the interpretation of San Diego Municipal Code section 126.0504.
Balboa Park, designated a National Historic Landmark in 1940, is a large urban park in the center of San Diego. The City of San Diego (“City”) recently approved a proposed plan (“Project”) to eliminate vehicles from the plazas within the Balboa Park complex and to return the plazas to purely pedestrian zones. Subsequently, a community group named Save Our Heritage Organisation (“SOHO”) filed a petition for a writ of mandate alleging, among other things, the City erroneously approved the Project. SOHO contended Municipal Code section 126.0504 mandated two key findings be made before the Project could be approved: (1) that the intended purpose of the property would not be adversely affected; and (2) without the proposed project, the property would not be put to a “reasonable beneficial use.” SOHO argued that although the City made the requisite findings, those findings lacked substantial evidentiary support. The trial court agreed with SOHO and directed the City to rescind the site development permit.
The City argued on appeal that Municipal Code section 126.0504 vested it with “discretion to make a qualitative determination of whether an existing use of the property, even if deemed beneficial, is also a reasonable use of that property under all of the facts and circumstances applicable to the particular property in question.” The Court of Appeal agreed and reversed.
Reprinted courtesy of
Kristen Lee Price, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Ms. Price may be contacted at kprice@hbblaw.com; Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Chicago Developer and Trade Group Sue City Over Affordable Housing Requirements
September 03, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Chicago Tribune reported that Hoyne Development and Home Builders Association of Greater Chicago are suing the city of Chicago, claiming that the “Affordable Requirements Ordinance is unconstitutional because it involves the taking of private party without ‘just compensation,’ violating the Fifth Amendment.”
Shannon Breymaier, spokeswoman for Chicago Mayor Rahm Emanuel, however, disputes the claims, and told the Chicago Tribune in an email that the city planned to “defend the ordinance vigorously.”
Read the court decisionRead the full story...Reprinted courtesy of
Florida Court of Appeals Rejects Insurer’s Attempt to Intervene in Underlying Lawsuit to Submit Special Interrogatories
October 09, 2018 —
Jeremy Macklin - TLSS Insurance Law BlogOn August 10, 2018, the Florida Court of Appeals for the Second District upheld a trial court’s dismissal of an insurance company’s intervention in a tort lawsuit brought against its insured for the purposes of submitting special interrogatories and verdict forms.
In Houston Specialty Ins. Co. v. Vaughn, 2018 Fla. App. LEXIS 11197, 2018 WL 3795785 (Fla. 2d DCA Aug. 10, 2018), the insured, All Florida Weatherproofing and Construction, Inc. (“All Florida”) provided pressure washing, roof coating, and other roof-related services. Houston Specialty issued a general liability policy to All Florida. In 2012, a worker fell off a roof while applying protective coating on behalf of All Florida. The worker and his family sued All Florida in connection with the worker’s injuries.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremy Macklin, Traub Lieberman Straus & Shrewsberry LLPMr. Macklin may be contacted at
jmacklin@tlsslaw.com
A Court-Side Seat: May Brings Federal Appellate Courts Rulings and Executive Orders
June 29, 2020 —
Anthony B. Cavender - Gravel2GavelHere are a few interesting new rulings from the federal appellate courts.
COURT ORDERS
Like a Good Neighbor …? —
State of Maryland v. EPA
On May 19, 2020, the D.C. Circuit decided a Clean Air Act case involving the use of the “Good Neighbor Provision” of the Act, which is triggered when one state has a complaint about emissions generated in a neighboring upwind state that settle in the downwind state. Here, Maryland and Delaware filed petitions with EPA seeking relief from the impact of emissions from coal-fired power plants that allegedly affect their states’ air quality. EPA largely denied relief, and the court largely upheld the agency’s use and interpretation of the Good Neighbor Provision. The opinion is valuable because of its clear exposition of this complicated policy.
A Volatile Underground Issue —
Wayne Land and Mineral Group v. the Delaware River Basin Commission
Also on May 19, 2020, the U.S. Court of Appeals for the Third Circuit issued a ruling involving the Delaware River Basin Commission. Established in 1961, the Commission oversees and protects the water resources in the Basin. Not long ago, the Executive Director of the Commission, citing a rule of the Commission, imposed very strict limitations on fracking operations in the Basin. This decision has been very controversial with the Third Circuit opining that the Commission’s authority to regulate fracking operations—thought to be a province of state authority—was not clear-cut. In this case, three Pennsylvania state senators filed motions to intervene in the case, but the lower court rejected their request. The Third Circuit has directed the lower court to take another look at their standing to participate in this litigation. This is a volatile issue in Pennsylvania.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Ready, Fire, Aim: The Importance of Targeting Your Delay Notices
November 08, 2021 —
Bradley Sands, Jones Walker LLP - ConsensusDocsProviding written notice of delay to subcontractors when a project is behind schedule is a regular part of good project documentation practices. A properly targeted delay notice is an important, project correspondence that is an appropriate response to a subcontractor’s specific delay or ongoing delays. However, when a project falls behind schedule and the project management team is in the fog of war, it could seem like a good idea to start firing off project delay notices to any and every subcontractor. While these delay notices may provide a short term burst of productivity, you could find that those same notices are aimed back at you in a future litigation.
This article identifies two potential unintended consequences of sending delay notices that a contractor should keep in its sights and then provides recommendations for properly calibrating future delay notices in light of these potential consequences.
Acceleration: You Might Get What You Ask For
A delay notice to a subcontractor could be interpreted as—or expressly state—direction to the subcontractor to accelerate its work. When a subcontractor is directed to accelerate its work, it may incur additional costs for premium, extended, or overtime labor, additional crews, increased supervision costs, increased overhead costs, and losses due to productivity impacts from the acceleration (e.g., stacking of trades and fatigue). A subcontractor may be entitled to recover these increased costs that are caused by a direction to accelerate.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley Sands, Jones Walker LLPMr. Sands may be contacted at
bsands@joneswalker.com
Managing Once-in-a-Generation Construction Problems – Part II
April 03, 2023 —
Jeffrey S. Wertman - Construction ExecutivePart I of this series discussed the benefits of construction participants using alternative project delivery methods and properly addressing change order issues, rising costs and payment structure issues to manage construction during these uncertain times. Part II below explores the possibility that higher prices and steady consumer demand could lead to an increase in unscrupulous contractor practices—and how owners can mitigate that risk, managing the challenges posed by the unforeseen labor shortage and turnover in the industry and evolving your construction team for short-term and long-term success.
Higher Prices and Steady Demand
With the demand for construction projects relatively stable, contractors remaining in high demand and a surge in prices for construction materials and components, owners are under great pressure to accept less favorable construction terms. This has presented unscrupulous contractors with perceived leverage over owners and new opportunities to engage in questionable business practices and fraud. Although some contractors may seek to stretch the boundaries of a construction contract, other contractors are more deliberate. Falsifying payment applications and invoices to inflate labor or materials costs, billing for work not yet performed or materials not yet delivered to the project site and manipulating change orders are examples of illicit and fraudulent practices by contractors.
Reprinted courtesy of
Jeffrey S. Wertman, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ten-Year Statute Of Repose To Sue For Latent Construction Defects
November 12, 2019 —
David Adelstein - Florida Construction Legal UpdatesIf you are dealing with latent construction defects, it is imperative that you consult with counsel to understand your rights. This not only includes claims for property damage stemming from latent construction defects, but also personal injury stemming from such defects. There is a ten-year statute of repose to sue for latent construction defects. See Fla.Stat. s. 95.11(3)(c). After the expiration of this statute of repose you are out of luck, meaning you can no longer sue.
Now, I probably will not be the first to tell you that the statute of repose is not written so clear that you know the precise date it ends (or the last date you can sue for a latent defect). For this reason, you really want to operate conservatively, meaning it is always better to sue early if you think you could be running on the end of the statute of repose period. It is always advisable to avoid any legitimate argument that you filed your construction defect lawsuit too late.
In Harrell v. The Ryland Group, 44 Fla. L. Weekly D2054b (Fla. 1st DCA 2019), a subsequent owner of a house sued the original homebuilder in negligence for a construction defect causing a personal injury. The subsequent owner claimed the homebuilder defectively installed an attic ladder (that provided access to the attic for the original construction) which collapsed as he was using it. The homebuilder filed a motion for summary judgment that the statute of repose expired so the owner’s claim was time-barred. The First District agreed.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at