CDJ STAFFWriting in Claims Journal, Bryan Rendzio notes that the decline in construction has not been matched by a decline in construction defect lawsuits over condominiums. He reviews the ways in which lawyers representing developers can help protect their clients. He identifies four important considerations in defending developers from claims of construction defects.
He advocates a careful review of the contract. “Under a breach of contract claim, the insured’s duties to the party who brought the claim against the insured flow from the contract. Commonly, construction contracts limit the scope of recoverable damages, such as by waiving consequential damages.’
The next step, according to Rendzio is to check of a settlement agreement is already in place, noting that these are “a familiar occurrence in the construction industry, regardless of any lawsuits having been filed.”
He considers the statute of repose “the single-most decisive weapon an insured possesses in its arsenal during a condo defect lawsuit.” He notes that no lawsuits can be brought for construction defects after the end specified by the statute of repose, and if a lawsuit is brought beforehand, no additional parties can be named once the statute has taken effect.
Finally, he warns adjusters to be suspicious when a condo association requests contractual indemnification. He notes that the pitfall in this is that developers and the subsequent condominium association often have similar names, given the theoretical example of a condo project built by “Fake Lakes LLC” and later run by the “Fake Lakes Condominium Association.” Writing in regards to Florida law, he notes that condominium associations do not have successor interest in contracts developers made with contractors.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Wildfire Insurance Coverage Series, Part 7: How to Successfully Prepare, Submit and Negotiate the Claim
August 22, 2022 —
Scott P. DeVries & Yosef Itkin - Hunton Insurance Recovery BlogPrior posts in this series have discussed insurance coverage issues that pertain directly to wildfire claims, but we have not yet addressed how one proceeds following a loss. In this post in the Blog’s Wildfire Insurance Coverage Series, we discuss the preparation, submission and negotiation of the insurance claim.
Preparing a Claim
As different policies provide different timelines, where possible, it is advisable to submit the claim as soon as reasonably possible. Insurers commonly cite late submission as a basis for denial with jurisdictions varying on the import of “late” submission.
Insurers have a right to reasonable documentation of a claim before paying. Often, they will decline to consider a claim on its merits until such documentation is provided. The policy will specify whether to submit a hard copy or file online, but either way it is advisable to maintain a copy online or in a remote geographic location.
Reprinted courtesy of
Scott P. DeVries, Hunton Andrews Kurth and
Yosef Itkin, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Mr. Itkin may be contacted at yitkin@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
A Trivial Case
November 07, 2022 —
Garret Murai - California Construction Law BlogConstruction defect cases leading to physical injury are rarely trivial, at least in the eyes of the injured party, but alas sometimes they are as the next case,
Nunez v. City of Redondo Beach, 81 Cal.App.5th 749 (2022), demonstrates.
The Nunez Case
Monica Nunez, Vice President of Finance and Accounting at a restaurant chain and a part-time fitness instructor at a gym, tripped and fell on a public sidewalk in Redondo Beach. Ms. Nunez, who was in her forties, tripped following a group run when her back foot hit a sidewalk slab that was elevated at its highest point approximately 11/16 inches. Ms. Nunez landed on her left knee and right arm and in the process fractured her kneecap and elbow.
Ms. Nunez sued the City of Redondo Beach for her injuries alleging causes of action for dangerous conditions on public property under Government Code section 835, nuisance under Government Code section 815.2, and failure to perform a mandatory duty under Government Code section 815.6.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Cultivating a Company Culture Committed to Safety, Mentorship and Education
March 19, 2024 —
David Frazier - Construction ExecutiveThe construction industry is aging. Valuing the significance of promoting a culture that enhances safety, mentorship and educational opportunities is essential to recruiting and retaining top talent to keep the industry thriving.
According to the U.S. Department of Labor, one in five worker deaths in the U.S. occurs in the construction industry. Additionally, construction workers are statistically at a higher risk for mental-health issues than virtually every other profession. According to a study conducted by CIRP, 83% of construction workers have struggled with mental-health disorders.
Today’s leaders must be dedicated to listening to employees' voices to shape the construction industry, as future leaders will be formed by a culture committed to employees' mental and physical health, safety, professional growth and overall workplace culture.
Reprinted courtesy of
David Frazier, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Submitting Claims on Government Projects Can Be Tricky
March 19, 2015 —
Craig Martin – Construction Contractor AdvisorThe Federal Circuit Court of Appeals opinion in K-Con Building Systems, Inc. v. United States illustrates the difficulties a contractor may face when pursuing a claim before a Contracting Officer. After nearly 10 years of litigation, the court found that the contractor’s claim to the Contracting Officer did not contain enough detail to allow the claim to proceed. That’s a lot of time and resources wasted on a claim that was dead from the start.
K-Con was awarded a $582,000 job to design and build a Coast Guard support building in Michigan. K-Con was unable to complete the project by the finish date and the Coast Guard assessed liquidated damages of $109,554. K-Con contested the assessment of liquidated damages by submitting a one paragraph letter asserting that it was not the sole cause of the alleged delays; that the government was at fault for the delay; and the liquidated damages were an impermissible penalty. The Contracting Officer ultimately denied K-Con’s claim and K-Con appealed to the Court of Claims.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Homeowners Not Compelled to Arbitration in Construction Defect Lawsuit
January 06, 2012 —
CDJ STAFFA California appeals court has ruled that developers cannot enforce CC&Rs in a case where a developer cited an arbitration clause it had inserted into the CC&R. The homeowners are alleging construction defect and wished to sue the developer who claimed a right to this under the CC&Rs.
The Marina del Rey Argonaut reports that particular appeal dealt only with whether the developer could compel arbitration. The underlying construction defect issues will subsequently have to be determined at trial.
The attorney for the homeowners’ association, Dan Clifford, noted that “arbitration has to be agreed to by both parties.” The covenant was drafted by the developer and in addition to requiring arbitration, it had a clause that it could not be amended without the consent of the developers. The court ruled that CC&Rs “can be enforced only by the homeowners association, the owner of a condominium or both.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
World Cup May Pull Out of Brazil because of Construction Delays
January 28, 2014 —
Beverley BevenFlorez-CDJ STAFFBack in October of last year, CNN reported that a judge suspended construction at one of the stadiums being built for this summer’s World Cup in Brazil. The judge stated that the dangers for construction workers included "being buried, run over, falling from heights and being hit by material, among other serious risks,” according to CNN.
Recently, the Los Angeles Times reported that FIFA is threatening to pull out of Brazil because of construction delays: “We cannot organize a match without a stadium,” Jerome Valcke, FIFA’s secretary general, as quoted in the Los Angeles Times. “This has reached a critical point.”
The deadline for completion of the 12 World Cup stadiums was January 1st, but various delays—including “fatal construction accidents at stadiums in Sao Paulo, Brasilia, and Manaus” as well as worker walk offs over pay—forced FIFA to “relax” the deadline.
Read the full story at CNN...
Read the full story at the Los Angeles Times... Read the court decisionRead the full story...Reprinted courtesy of
MTA’S New Debarment Powers Pose an Existential Risk
July 15, 2019 —
Steven M. Charney, Gregory H. Chertoff & Paul Monte - Peckar & Abramson, P.C.The normal project and contractual risks faced by contractors, consultants and suppliers to the Metropolitan Transportation Authority are considerable. A new law and regulations mandating that the MTA debar contractors, consultants and suppliers for unexcused schedule and cost overruns creates a new and unfair existential risk.
The new law, Public Authorities Law Section 1279-h, slipped into the New York State budget bill and passed without public comment, was enacted on April 12, 2019. Implementing regulations were issued on June 5, 2019, and mandate that the MTA debar contractors (defined to include consultants, vendors and suppliers) if they: (1) fail to achieve substantial completion of their contractual obligations within 10% of the adjusted contract time; or (2) present claims for additional compensation that are denied in an amount that exceeds the total adjusted contract amount by 10% or more.[1]
To say that your business and your livelihood are at risk is not an overstatement. The MTA umbrella includes the New York City Transit Authority, MTA Capital Construction, Bridges & Tunnels, Long Island Railroad and Metro North, among others. A debarment by one of these authorities will lead to a debarment by all of them, and then to a debarment by all New York State agencies and authorities,[2] and possibly debarment across state lines. Public and major private owners, as part of their RFP and procurement processes, routinely inquire regarding a bidding contractor’s debarment history.
The risk is to new contracts and, because the MTA has decided to give retroactive effect to the law and regulations, to contracts that are already ongoing (even though these risks could not have been considered, priced or agreed to by contractors or their sureties).
Reprinted courtesy of Peckar & Abramson, P.C. attorneys
Steven M. Charney,
Gregory H. Chertoff and
Paul Monte
Mr. Charney may be contacted at scharney@pecklaw.com
Mr. Chertoff may be contacted at gchertoff@pecklaw.com
Mr. Monte may be contacted at pmonte@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of