Defenses Raised Three-Years Too Late Estop Insurer’s Coverage Denial
February 21, 2022 —
Michael S. Levine & Yaniel Abreu - Hunton Insurance Recovery BlogLiability insurance typically affords broad defense coverage. But insurers sometimes reserve their right to challenge the insured’s right to a defense, or even outright terminate the defense. When this occurs after the insurer has been in exclusive control of the defense, some courts recognize that the consequences can be catastrophic for the insured defendant. Insurers, therefore, may be estopped from denying coverage where doing so will prejudice the insured. This is exactly what transpired in RLI Ins. Co. v. AST Engineering Corp., No. 20-214 (2d Cir. Jan. 12, 2022), where the Second Circuit affirmed the district court’s decision that an insurer’s attempt to withdraw the defense it had provided to its insured for three years would prejudice the insured.
In AST Engineering, RLI sought a declaration that it did not have to defend the insured, AST, in two underlying cases in which AST was sued as a third-party defendant. The underlying cases concerned a construction project in New York City for which AST provided engineering drawings on October 28, 2012.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Yaniel Abreu, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Abreu may be contacted at yabreu@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Fraud Claims and Breach Of Warranty Claims Against Manufacturer
March 04, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent case touches upon two issues that are noteworthy when considering fraud claims and breach of warranty claims against a manufacturer. Below contains a discussion on these claims.
Independent Tort Doctrine
“Florida’s independent tort doctrine provides that a party may not recover in tort for a contract dispute unless the tort is independent of any breach of contract.” MidAmerica C2L Inc. v. Siemens Energy, Inc., 2024 WL 414620, *6 (M.D.Fla. 2024). This means tort allegations and claims MUST be separate and distinct from performance under the contract. Id. (citation omitted).
In MidAmerica C2L, a plaintiff sued a manufacturer relating to sophisticated equipment for a coal gasification plant. The parties entered into different agreements for the equipment and a license where the plaintiff could use the manufacturer’s patented technology for its coal gasification plants. A dispute arose and the plaintiff sued the manufacturer under various legal theories. The manufacturer moved for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
CRH to Buy Building-Products Firm Laurence for $1.3 Billion
September 03, 2015 —
Phil Serafino & Andrew Marc Noel – BloombergCRH Plc agreed to buy Los Angeles-based C.R. Laurence Co. for $1.3 billion to expand in products used in window installation as U.S. construction markets stabilize.
C.R. Laurence, which is owned by the Friese family, makes hardware and products used in the installation of architectural glass and generated pretax profit of $51 million in 2014, Dublin-based CRH said in a statement Thursday.
CRH shares rose 4.9 percent to 25.79 euros as of 8:56 a.m. in Dublin, giving the company a market value of 21.2 billion euros ($24 billion).
The purchase is timed with a recovery in U.S. construction markets, driven by demand for industrial buildings. CRH reported a "promising backlog" of business at its Americas Materials division in May. Combining the companies will generate $40 million a year in savings from 2017, it said.
Reprinted courtesy of
Phil Serafino, Bloomberg and
Andrew Marc Noel, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Remember to Timely Foreclose Lien Against Lien Transfer Bond
July 09, 2019 —
David Adelstein - Florida Construction Legal UpdatesWhen a construction lien is transferred to a lien transfer bond pursuant to Florida Statute s. 713.24, instead of foreclosing the lien against the real property, you are foreclosing the lien against the lien transfer bond. This is not a bad deal and, oftentimes, is probably ideal. Remember, however, just because a construction lien was transferred to a lien transfer bond (pre-lawsuit) does not mean you get more time to file your lien foreclosure lawsuit. A lawsuit must still be filed within one year (short of that period being specifically shortened under operation of the law).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Why Biden’s Infrastructure Plan Is a Green Jobs Plan
April 26, 2021 —
Gernot Wagner - Bloomberg“Once you put capital money to work, jobs are created.”
These are not the words of President Joe Biden, announcing his administration’s infrastructure plan in Pittsburgh on Wednesday. Nor were they the words of Transportation Secretary Pete Buttigieg, standing on a train platform to announce expanded service, or of any of the administration’s economists charged with touting the virtues of the $2.25 trillion spending plan.
It was Michael Morris, then-CEO of Ohio utility American Electric Power, who uttered them on an investor call a decade ago. AEP was fighting an Environmental Protection Agency proposal to reduce mercury and other pollutants from power plants, citing the expense of creating jobs to install new scrubbers on smokestacks or build cleaner plants. Morris, taking his fiduciary responsibility to the utility’s investors seriously, argued these new roles would come at a cost to AEP and were, thus, bad. What he did not question, and correctly so, was whether more investments would indeed create more jobs.
Read the court decisionRead the full story...Reprinted courtesy of
Gernot Wagner, Bloomberg
Breach Of Duty of Good Faith And Fair Dealing Packaged With Contract Disputes Act Claim
March 27, 2023 —
David Adelstein - Florida Construction Legal UpdatesAn interesting opinion on a motion to dismiss came out of the United States Court of Federal Claims dealing with the claim that the government breached its duty of good faith and fair dealing in administering the prime contract. The contractor’s argument was that the government breached its duty of good faith and fair dealing by denying the contractor’s claim under the Contract Disputes Act (CDA). This was a creative claim and argument that deserves consideration because it tied in the contracting officer’s denial of the CDA claim for additional money with a breach of the duty of good faith and fair dealing.
In this case, Aries Construction Corp. v. U.S., 2023 WL 2146598 (Fed. Cl. 2023), a prime contractor was hired for a water pipeline construction project. The contractor encountered unexpected difficult site conditions that required additional equipment and labor. The contractor informed the contracting officer and alleged it was instructed to proceed with the additional equipment and labor. The contractor submitted a claim under the CDA but the contracting officer denied the claim. The contractor pursued the claim in the United States Court of Federal Claims arguing the government breached the contract and, of interest, breached its duty of good faith and fair dealing.
The government moved to dismiss the breach of good faith and fair dealing claim arguing that besides failing to state a cause of action the Court of Federal Claims had no jurisdiction because the breach of the duty of good faith and fair dealing was not properly presented to the contracting officer under the CDA. The Court of Federal Claims denied the government’s motion.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Manhattan Home Prices Jump to a Record as Buyers Compete
April 02, 2014 —
Oshrat Carmiel – BloombergManhattan apartment sales surged in the busiest start to a year since 2007, setting price records as buyers vied for a limited supply of homes for sale and deals were completed at new high-end developments.
Sales of co-ops and condominiums in the first quarter jumped 35 percent from a year earlier to 3,307, according to a report today from appraiser Miller Samuel Inc. and brokerage Douglas Elliman Real Estate. The median price climbed 19 percent to $972,428, while the the average price per square foot rose 24 percent to $1,363, the highest in 25 years of record-keeping.
Price gains are accelerating in a market where the inventory of homes for sale plummeted to record lows three times in the past year as buyer demand increased. Of the deals completed in the first quarter, 38 percent were at or above the asking price, up from 17 percent a year earlier, according to Jonathan Miller, president of New York-based Miller Samuel.
Read the court decisionRead the full story...Reprinted courtesy of
Oshrat Carmiel, BloombergMs. Carmiel may be contacted at
ocarmiel1@bloomberg.net
Green Investigations Are Here: U.S. Department of Justice Turns Towards Environmental Enforcement Actions, Deprioritizes Compliance Assistance
January 10, 2022 —
Karen C. Bennett, R. Morgan Salisbury, Sean P. Shecter & Rose Quam-Wickham - Lewis BrisboisWashington, D.C. (January 4, 2022) - Two high-ranking Department of Justice (DOJ) officials announced that the Biden Administration is prioritizing environmental regulatory enforcement over compliance assistance. Todd Kim, Assistant Attorney General for the DOJ’s Environment and Natural Resources Division (ENRD), and Deborah Harris of the DOJ’s Environmental Crimes Section, indicated in mid-December 2021 that companies and individuals should expect more “vigorous enforcement,” with an emphasis on criminal enforcement. This new policy is in contrast to the Environmental Protection Agency’s (EPA) Office of Enforcement and Compliance Assurance (OECA)'s previous emphasis on compliance and pollution mitigation instead of enforcement actions under the prior administration.
DOJ’s new policy of promoting enforcement actions is consistent with the Biden Administration’s overall efforts to prioritize environmental justice. In April 2021, as explained in a previous Lewis Brisbois Client Alert, OECA released two memoranda directing enforcement teams to consider a variety of tools to resolve enforcement actions, including increased inspections, restitution, and reparation for victims of environmental crimes and overstepping state regulators where necessary.
Reprinted courtesy of
Karen C. Bennett, Lewis Brisbois,
R. Morgan Salisbury, Lewis Brisbois,
Sean P. Shecter, Lewis Brisbois and
Rose Quam-Wickham, Lewis Brisbois
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Mr. Salisbury may be contacted at Morgan.Salisbury@lewisbrisbois.com
Mr. Shecter may be contacted at Sean.Shecter@lewisbrisbois.com
Ms. Quam-Wickham may be contacted at Rose.QuamWickham@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of