Recent Third Circuit OSHA Decision Sounds Alarm for Employers and Their Officers
October 14, 2019 —
John Baker - White and Williams LLPThe Third Circuit Court of Appeals recently issued an opinion that should serve as a warning not only to employers, but to their corporate officers. The case against Altor, Inc., a New Jersey-based construction company, began in 2012 when the Occupational Safety and Health Administration (OSHA) directed Altor and its sole director and officer to pay a $412,000 penalty (Payment Order) to OSHA for several violations, including the failure to comply with fall protection standards. The company refused to pay, arguing that it did not possess sufficient assets. The Secretary of Labor filed a Petition for Civil Contempt against Altor and its President, Vasilios Saites. The court acknowledged that the company and Mr. Saites could defend against a contempt finding by showing that he and the company were unable to comply with the Payment Order. Beyond merely stating that they could not pay, the court required that they must show that they made good faith efforts to comply with the Order.
After considering all of the evidence, the court ultimately relied on Altor’s bank records, which reflected that the company ended each month during a two-year period after the violations with a positive bank balance. Thus, the court determined that Altor could have made “at least relatively modest” payments and emphasized that the company never attempted to negotiate a reduced sum or a payment plan.
Read the court decisionRead the full story...Reprinted courtesy of
John Baker, White and Williams LLPMr. Baker may be contacted at
bakerj@whiteandwilliams.com
Construction Warranties and the Statute of Repose – Southern States Chemical, Inc v. Tampa Tank & Welding Inc.
January 20, 2020 —
David R. Cook - AHC Construction and Procurement BlogIn a recent holding by the Georgia Court of Appeals, the court held that Georgia’s eight-year statute of repose applied to bar the project owner’s warranty claims. The renovation work by the contractor on the owner’s chemical tank constituted an improvement of real property, and thus, the statute of repose bared any claims eight years after substantial completion thereof. In addition, the court rejected the project owner’s claim that it qualified as a third-party beneficiary of an extended warranty contained in a report given by a subcontractor to the contractor.
Factual Background
In 2000, Southern States Phosphate and Fertilizer Company (“Southern States”) hired Tampa Tank & Welding, Inc (“Tampa Tank”) to renovate a tank to hold sulfuric acid. The parties’ written contract contained an express one-year warranty for material and workmanship from the date of completion. Two years later, in January 2002, the tank renovation was completed. Tampa Tank contracted with Corrosion Control Inc. (“CCI”) to design, assist with, and test the cathodic corrosion system. CCI provided only consultation and did not provide any onsite installation. Upon completion of installation, CCI supplied a report to Tampa Tank that the system was properly installed and fully functioning. Additionally, a post–installation report from CCI to Tampa Tank calculated an estimated life expectancy of forty-three to forty-five years.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Quick Note: Notice of Contest of Claim Against Payment Bond
January 31, 2018 —
David Adelstein - Florida Construction Legal UpdatesOn private jobs where the general contractor has an unconditional payment bond, subcontractors, sub-subcontractors and suppliers need to serve a
notice of nonpayment to preserve payment bond rights.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
U.S. District Court for Hawaii Again Determines Construction Defect Claims Do Not Arise From An Occurrence
August 27, 2013 —
CDJ STAFFIn a decision authored by Judge Leslie E. Koybayashi, the U.S. District Court for the District of Hawaii followed its prior decisions that construction defect claims were not covered because such claims do not arise from an occurrence. Nautilus Ins. Co. v. 3 Builders, Inc., 2013 U.S. Dist. LEXIS 88480 (D. Haw. June 24, 2013).
3 Builders, the insured, was sued by the Apartment Owners of Mililani Pinnacle for the faulty installation of a new roof. Pinnacle claimed the completed roofs were not properly installed.complaint alleged breach of contract, breach of the duty of good faith and fair dealing, negligence, and other causes of action.
3 Builders tendered the defense to Nautilus, who accepted the tender and defended for three years. Nautilus, however, filed a complaint for a declaratory judgment on its coverage obligations. Nautilus sought summary judgment, contending there was no coverage because all of the claims arose from the contractual relationship to perform the roof work, and a breach of contract was not the type of fortuitous event covered by a CGL policy under Hawaii law.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Insurer's Summary Judgment Motion on Business Risk Exclusions Fails
November 15, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer unsuccessfully moved for summary judgment on the CGL policy's business risk exclusions. Scottsdale Ins. Co. v. TL Spreader, LLC, (W.D. La. Oct. 20, 2017).
Helena Chemical Company contracted with its customer Wild Farms to sell and apply certain herbicides and pesticides to Wild Farms' 123 acre rice filed. Helena subcontracted the TL Spreader, LLC (TLS) to apply the chemicals to Wild Farm's rice field. The TLS employee failed to properly neutralize a chemical being used in the spray.
TLS finished its work on May 6, 2014, completing all its work for Helena's contract with Wild Farms. Three days after completion of the spraying, the rice crop first began to exhibit physical damage in the form of abnormal stunting, lesions, yellowing and death.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
A Retrospective As-Built Schedule Analysis Can Be Used to Support Delay
May 23, 2022 —
David Adelstein - Florida Construction Legal UpdatesDelay claims are part of construction. There should be no surprise why. Time is money. A delay claim should be accompanied by expert opinions that bolster evidence that gets introduced. The party against whom the delay claim is made will also have an expert – a rebuttal expert. Not surprisingly, each of the experts will rely on a different critical path as to relates to the same project. The party claiming delay will rely on a critical path that shows the actions of the other party impacted their critical path and proximately caused the delay. This will be refuted by the opposing expert that will challenge the critical path and the actions claimed had no impact on the critical path (i.e., did not proximately cause the delay). Quintessential finger pointing!
This was the situation in CTA I, LLC v. Department of Veteran Affairs, CBCA 5826, 2022 WL 884710 (CBCA 2022), where the government terminated the contractor for convenience and the contractor claimed equitable adjustments for, among other things, delay. The contractor’s expert relied on an as-built critical path analysis by “retrospectively creating updates to insert between the contemporaneous updates.” Id., supra, n.3. The government’s expert did not do a retrospective as-built analysis and relied on only contemporaneous schedule updates. Id.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Mental Health and Wellbeing in Construction: Impacts to Jobsite Safety
August 16, 2021 —
NAHB - NWFA and Hardwood Floors MagazineThis article originally appeared in the National Wood Flooring Association's Hardwood Floors Magazine.
In the construction industry, workplace safety efforts have often focused on eliminating the most-common causes of on-the-job accidents, such as falls, being struck by or caught in-between objects, electrocutions, or being exposed to hazardous chemicals and substances. For more than two decades, the National Association of Home Builders (NAHB) has been at the forefront of enhancing physical safety and health in residential construction. NAHB takes proactive steps to keep members and affiliated state and local associations informed and educated about safety and health issues and trends affecting the building industry, including developing safety and health resources to help builders and contractors operate safe jobsites and lower workers’ compensation costs.
However, we recently have learned that construction workers are particularly susceptible to mental health issues and suicide – which is a silent killer in construction, and we know that the home building industry is not immune to the issues in the construction industry at large. We also know that industry associations have a role to play in promoting the importance of worker health and well-being to their member organizations. Helping to create sustainable workplaces and healthy, thriving professionals strengthens the industry and deepens the volunteer leadership bench. In addition to the benefits to the association, workplace well-being is good for employee health and retention, may reduce the cost of insurance, sick time, and employee turnover, and increase productivity. This can be accomplished by addressing mental well-being as part of overall safety – both physical and psychological.
How big is this problem of mental health and suicides in construction? According to the Centers for Disease Prevention and Control (CDC), the construction industry has one of the highest rates of death by suicide compared to other industries. In 2017, the suicide rate for construction workers was 53.3 per 100,000 workers, which is nearly five times greater than the rate for all fatal work-related injuries in construction (9.5 per 100,000 workers) from the physical hazards companies focus on eliminating.
Read the court decisionRead the full story...Reprinted courtesy of
NAHB
Governor Signs Permit Extension Bill Extending Permit Deadlines to One Year
October 23, 2018 —
Garret Murai - California Construction Law BlogIt’s like that feeling you got when your teacher said you have another week to complete your group project.
On September 21, 2018, Governor Brown signed AB 2913, which, for the first time, provides a uniform 12-month period across the state for work to commence before a building permit expires. Previously, the period was six months.
In addition to doubling the expiration period, the statute includes a “justifiable cause” provision permitting local building departments to extend the time for one or more additional periods of not more than 180 days per extension upon written demonstration of “justifiable cause for the extension.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com