Texas Supreme Court Holds Anadarko’s $100M Deepwater Horizon Defense Costs Are Not Subject To Joint Venture Liability Limits
February 27, 2019 —
Sergio F. Oehninger & Michael S. Levine - Hunton Andrews KurthReversing a Texas Court of Appeals decision that allowed Anadarko’s Lloyd’s of London excess insurers to escape coverage for more than $100 million in defense costs incurred in connection with claims from the Deepwater Horizon well blowout, the Supreme Court of Texas held that the insurers’ obligations to pay defense costs under an “energy package” liability policy are not capped by a joint venture coverage limit for “liability” insured. Anadarko Petroleum Corp. et al. v. Houston Casualty Co. et al., No. 16-1013 (Tex. Jan. 25, 2019).
While the Lloyd’s of London insurers had agreed to pay Anadarko $37.5 million for damages, they declined to cover $100 million-plus in defense fees, arguing that both Anadarko’s liability and defense expenses are subject to the $37.5 million joint venture limit for “liability” insured. Anadarko asserted that only amounts paid as damages to third parties are subject to that limit. Defense costs, however, are not amounts paid as damages to a third party and, thus, are not a “liability.” Those amounts, therefore, are not subject to the joint venture limit and are instead subject to the policy’s $150 million coverage limit.
Reprinted courtesy of
Sergio F. Oehninger, Hunton Andrews Kurth and
Michael S. Levine, Hunton Andrews Kurth
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
OSHA COVID-19 Vaccination and Testing ETS Unveiled
November 19, 2021 —
Donna Reichle - Construction ExecutiveAssociated Builders and Contractors today released the following statement on the Occupational Safety and Health Administration’s issuance of its COVID-19 vaccination and testing Emergency Temporary Standard, which applies to employers with 100 or more employees as required by President Biden’s Path Out of the Pandemic COVID-19 Action Plan.
“The OSHA ETS is likely to increase compliance costs and cause regulatory burdens that will exacerbate several headwinds facing the construction industry—which is currently facing a workforce shortage of 430,000, escalating materials prices and supply chain bottlenecks—and the American economy,” says Ben Brubeck, ABC vice president of regulatory, labor and state affairs. “We are currently reviewing the 490-page rule and related documents from the Biden-Harris administration in order to thoroughly evaluate its impact on our membership and the construction industry.”
Reprinted courtesy of
Donna Reichle, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Reichle may be contacted at
reichle@abc.org
SDNY Vacates Arbitration Award for Party-Arbitrator’s Nondisclosures
April 13, 2017 —
Justin K. Fortescue & Ciaran B. Way - White and Williams LLPThe US District Court for the Southern District of New York recently vacated an arbitration award finding that a party-appointed arbitrator’s undisclosed relationship with the party appointing him was significant enough to demonstrate evident partiality. Certain Underwriting Members at Lloyd’s of London, et. al. v. Ins. Companies of America, Inc., Nos. 16-cv-232 and 16-cv-374 (S.D.N.Y. March 31, 2017).
In the arbitration, the panel was asked to determine whether the reinsurance contracts, covering workers’ compensation policies, only applied when multiple claimants were injured as the result of the same loss occurrence. After a three-day hearing, the arbitration panel issued an award in favor of the ceding company, Insurance Companies of America (ICA). After the award was issued, Lloyd’s discovered that ICA’s arbitrator had significant undisclosed relationships with principals at ICA and moved to vacate the award in federal court.
Reprinted courtesy of
Justin K. Fortescue, White and Williams LLP and
Ciaran B. Way, White and Williams LLP
Mr. Fortescue may be contacted at fortescuej@whiteandwilliams.com
Ms. Way may be contacted at wayc@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
PSA: Pay If Paid Ban Goes into Effect on January 1, 2023
December 05, 2022 —
Christopher G. Hill - Construction Law MusingsI have
written a couple of times here at Musings regarding the new pay-if-paid legislation passed by the General Assembly last session. While the statute has some inconsistencies and a working group has made
some recommendations, the legislation as passed will go into effect on January 1, 2023, without any changes (at least until next session). As always, such action by our legislature here in Virginia will create work for construction attorneys assisting their clients to amend contracts to meet the new rules.
Essentially (and with minor inconsistencies between public and private contracts), the bill requires that any construction contract entered into after January 1, 2023 have the following provisions:
- On public projects: A payment clause that obligates a contractor on a construction contract to be liable for the entire amount owed to any subcontractor with which it contracts. Such contractor shall not be liable for amounts otherwise reducible due to the subcontractor’s noncompliance with the terms of the contract. However, in the event that the contractor withholds all or a part of the amount promised to the subcontractor under the contract, the contractor shall notify the subcontractor, in writing, of his intention to withhold all or a part of the subcontractor’s payment with the reason for nonpayment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Blog Completes Fifteenth Year
December 13, 2022 —
Tred R. Eyerly - Insurance Law HawaiiInsurance Law Hawaii completes its fifteenth year of existence this month. We began posting in December 2007, 1656 posts ago.
We strive to keep readers abreast of new developments in insurance-related cases from Hawaii and across the country. Coverage issues in the past year have again been dominated by COVID-19, business interruption, construction defect, and cyber claims. This trend will likely continue over the next year and we will do our best to track developments.
Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak Hastert
Mr. Eyerly may be contacted at te@hawaiilawyer.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Texas Federal Court Finds Total Pollution Exclusion Does Not Foreclose a Duty to Defend Waterway Degradation Lawsuit
October 24, 2022 —
Jeremy S. Macklin - Traub Lieberman Insurance Law BlogEvanston Ins Co. v. Tex. Concrete and Sand Gravel, Inc., No. 4:20-cv-00103 (S.D. Tex. Aug. 30, 2022) is a coverage dispute over Evanston Insurance Co.’s (“Evanston”) duty to defend and indemnify Texas Concrete Sand and Gravel, Inc. (“Texas Concrete”) and Apcon Services, LLC (“Apcon”) (collectively, the “Insureds”) for their contributions to the degradation of the waterways and retention lakes built to control flooding in the Houston area. On August 3, 2022, Magistrate Judge Yvonne Y. Ho recommended that Evanston’s motion for summary judgment be denied. On August 30, 2022, District Court Judge Alfred H. Bennett adopted Judge Ho’s Memorandum and Recommendations.
In 2017, Hurricane Harvey caused significant flooding of the Houston area, which resulted in large-scale property damage. The underlying lawsuits alleged that, since 1954, Lake Houston’s waterways sustained a steady decline in capacity because of the release of materials into the waterway system. The Insureds allegedly contributed to the decline by allowing “materials and substances” (such as processed water, silt, sand, sediment, dirt, rock, and aggregate) to run off their privately controlled properties and into the Houston waterways. The reduced capacity, allegedly caused in part by the Insureds, exacerbated the flooding after Hurricane Harvey hit, increasing the damage from the hurricane.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremy S. Macklin, Traub LiebermanMr. Macklin may be contacted at
jmacklin@tlsslaw.com
Hawaii Court Looks at Changes to Construction Defect Coverage after Changes in Law
November 06, 2013 —
CDJ STAFFA construction defect case lead at the U.S. District Court for Hawaii involved the insurer’s changed views on what was covered based on court decisions that came after the policy was written. John R. Casciano and Jessica L. Urban of Steptoe & Johnson LLP discuss the case on their firm’s website. They note that in Illinois National Insurance Company v. Nordic PCL Construction, Inc., Nordic built a retail building which soon afterwards had water leaks and property damage, due to alleged defects in the roof construction.
Nordic had purchased comprehensive general liability and umbrella polices, with coverage that included property damage. Mr. Casciano and Ms. Urban note that “at the time of contracting, the Ninth Circuit had predicted that, ‘if the Hawaii Supreme Court examined the matter, it would rule that, for purposes of insurance coverage, construction defects were “not occurrences.”’” After the policy was written, the Hawaii Intermediate Court of Appeals did rule that “construction defect claims do not constitute an ‘occurrence’ under a CGL policy.” On the basis of this, Illinois National determined that they had no duty to defend or indemnify their client.
Nordic made a claim of bad faith, but the court determined that “an insurer that denies coverage based on an open question of law does not act in bad faith, an insurer that actually relies on governing law, even if the insurer only belatedly learns of the law, cannot be said to thereby act in bad faith.”
However, the court denied a summary judgment of Nordic’s claim of negligent misrepresentation, determining that there was “a question of fact as to whether the Policies covered [or were represented as covering] only damage to third parties caused by subcontractors’ defective work.” Finally, the court found that “a reasonable jury could infer that, at the time the Polices were issued, the insurers meant to cover claims arising out of the defective work” of Nordic’s subcontractors.
They conclude that the Nordic decision “recognizes the varying consequences for coverage claims when post-contracting changes to the law may not coincide with the expectations of at least one of the parties at the time of contracting.”
Read the court decisionRead the full story...Reprinted courtesy of
School District Gets Expensive Lesson on Prompt Payment Law. But Did the Court Get it Right?
February 26, 2015 —
Garret Murai – California Construction Law BlogMy kids don’t like riding in my car.
I urge them to look outside the window (I don’t have DVD), suggest that they roll down their windows to get some fresh air (rather than have me turn on the A/C) and persist on listening to that archaic device called the radio (I don’t “stream”).
Plus, I make them play “Dad Games.” Like Synonyms.
In Synonyms, I say a word, and the next person has to come up with a synonym for that word until someone can’t think of another synonym. Sometimes, I take a walk on the wild side, and play “Antonyms.”
Things can get heated, though. Like when someone says a word and there is a disagreement over whether that word is a synonym or not.
The next case, FTR International, Inc. v. Rio School District, California Court of Appeal for the Second District, Case No. B238618 (January 27, 2015), also involved a disagreement over synonyms . . . except that the loser had to cough up nearly $10 million.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com