Pennsylvania Court Extends Construction Defect Protections to Subsequent Buyers
December 20, 2012 —
CDJ STAFFThe Pennsylvania courts have long held that there is an implied warranty of habitability for the initial purchaser of a home. Now, as some defects may not immediately show up, the court has extended that implied warranty to second and subsequent purchasers. As Marc D. Brookman, David I. Haas, and Christopher Bender of Duane Morris note, “this judicially created doctrine shifts the risk of a latent defect in the construction of a new home from the purchaser to the builder-vendor.”
The Pennsylvania Supreme Court concluded that a contractual relationship is not needed for an implied warranty of habitability. The court’s concern was inequalities would result when a home was sold while other homes were protected by being within the statute of repose.
Read the court decisionRead the full story...Reprinted courtesy of
Delays Caused When Government (Owner) Pushes Contractor’s Work Into Rainy / Adverse Weather Season
January 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesThere are a number of horizontal construction projects where a contractor’s sequence of work and schedule is predicated on avoiding the rainy season (or certain force majeure events). The reason is that the rainy season will result in delays due to the inability to work (and work efficiently) during the adverse weather (including flooding caused by the weather). If the work is pushed into the rainy season, is such delay compensable if the government (or owner) delayed the project that pushed work out into the rainy season? It very well can be.
For example, in Meridian Engineering Co. v. U.S., 2019 WL 4594233 (Fed. Cl. 2019), a contractor was hired by the Army Corps of Engineers to construct a flood control project for a channel in Arizona. Due to delays, including those caused by the government, the project was pushed into the monsoon season, which caused additional delays largely due to flooding caused by the heavy rain. One issue was whether such delays were compensable to the contractor – the government raised the argument that the contractor assumed the risk of potential flooding from the rainy season. The Court found this argument unconvincing:
[The contractor’s] initial construction schedule planned for a completion of the channel invert work, a necessary step in protecting the site from flooding, to be completed by late June 2008…[M]any issues arose in the project’s early stages that led to cumulative substantial delay, including those caused by the government’s failure….The government cannot now claim that [the contractor] assumed the risk of flooding from monsoon season when the government was largely responsible for [the contractor’s] inability to complete the project prior to the beginning of the monsoon season. Simply put, the government cannot escape liability for flood damages when the government is responsible for causing the contractor to be working during the flood-prone season.
Meridian Engineering, 2019 WL at *7 (internal citations omitted)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
South Carolina Legislature Redefining Occurrences to Include Construction Defects in CGL Policies
April 01, 2011 —
Beverley BevenFlorez CDJ STAFFThe question of what circumstances must be in place for construction defects to be covered in a general commercial liability (CGL) policies is being raised by the courts and the legislature in South Carolina. The Insurance Journal reports that the American Insurance Association as well as the Property and Casualty Insurers Association of America are speaking out on the issue.
The problem seems to be centered on what defines an “occurrence.” CGL policies were not meant to cover faulty workmanship, according to the filing by the South Carolina Supreme Court. In January of this year, the South Carolina Supreme Court reversed the ruling in Crossmann Communities v Harleysville Mutual declaring that “Respondents cannot show the damage here was the result of an occurrence. Rather, the damage was a direct result and the natural and expected consequence of faulty workmanship; faulty workmanship did not cause an occurrence resulting in damage.” They focused their attention on the word “accident,” stating that there is a fortuity element that is not diminished.
The South Carolina legislature reacted by producing a bill that would add new language directly negating the ruling by the Supreme Court. The South Carolina bill S-431 would change the definition of an occurrence in regards to construction defects as follows: “For a liability insurance policy issued to a construction professional, an ‘occurrence’ means, at a minimum: (1) an accident; or (2) continuous or repeated exposure to substantially the same general harmful condition or substance. No additional requirement of a fortuitous event is needed to constitute an ‘occurrence.’”
S-431 is currently residing in the House Committee on Labor, Commerce and Industry.
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Small to Midsize Builders Making Profit on Overlooked Lots
March 26, 2014 —
Beverley BevenFlorez-CDJ STAFFTeresa Burney and John Caulfield writing in Big Builder discussed how many small to mid-size firms are making profits off of lots overlooked by the big building firms. They stated that “builders are scouring the country for land to meet the new housing demand, and they are having trouble finding good lots in the right place at the right price. This is particularly true for small to mid-size builders.”
While the number of finished lots may be up, Burney and Caulfield declared that “the numbers are deceptive because roughly 25 percent of them are in what Metrostudy, BUILDER’s research company, describes as ‘D’ and ‘F’ locations—places so undesirable that nobody wants to live there.”
Strategies that builders have tried with success, according to Big Builder, include looking for older communities that local builders have forgotten, or choosing a lot that needs more work than most builders would want to deal with. “We are kind of a savior for developers with troublesome leftover lots,” William H. Hoover, president of Texas-based Inland Homes, told Big Builder. “You have got some ugly lots, let us come and finish out your community.”
Read the court decisionRead the full story...Reprinted courtesy of
To Require Arbitration or Not To Require Arbitration
December 31, 2014 —
Christopher G. Hill – Construction Law MusingsMany, if not most, construction contracts that I review during the course of my practice day include a mandatory arbitration clause. Most of these refer in a blanket manner to AAA Construction Industry Rules. The topic for this post is not whether such clauses are enforceable or whether they are one tool in the contracting tool box in a state where the contract is king. I picked the title of this post carefully because I wanted to discuss whether such clauses should be required as a routine part of all construction contracts and, if so, how those clauses can and should be written.
I have previously shared my thoughts on mandatory arbitration and its desirability in numerous spots here at Construction Law Musings (you can search arbitration or check out the ADR page for more). In short, my opinion is that arbitration was initially conceived with the purpose of streamlining the dispute resolution process and to correspondingly lower the costs associated with such dispute resolution. Arbitration, when used correctly, can, in certain very industry specific cases, help by using an arbitrator or panel of arbitrators that have some expertise in the particular area of the construction industry or the particular specialized issue that will turn the case one way or the other. All of these goals are good and I applaud them.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
When is an Indemnification Provision Unenforceable?
September 06, 2021 —
Christopher G. Hill - Construction Law MusingsVirginia Code Sec. 11-4.1 makes indemnification provisions in construction contracts that are so broad as to indemnify the indemnitee from its own negligence unenforceable. Of course, this begs the question as to what language of indemnification provisions make them unenforceable.
A case from the City of Chesapeake Virginia Circuit Court examined this question. In Wasa Props., LLC v. Chesapeake Bay Contrs., Inc., 103 Va. Cir 423 [unfortunately I can’t find a copy to which to link], Wasa Properties (“Wasa”) hired Chesapeake Bay Contractors (“CBC”) to perform utility work at Lake Thrasher in the Tidewater area of Virginia. Wasa then alleged that CBC breached the contract and caused over $400,000 in damages due to incorrectly installed water lines. Wasa used the following indemnification language as the basis for its suit:
To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the Owner and his agents and employees from and against all claims, damages, losses, and expenses, including but not limited to attorney’s fees arising out of or resulting from the performance of the Work.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Hybrid Contracts for The Sale of Goods and Services and the Predominant Factor Test
February 15, 2021 —
David Adelstein - Florida Construction Legal UpdatesFlorida’s Uniform Commercial Code (also known as the UCC) applies to transactions for goods. “Goods” is defined by Article II of the UCC as “all things (including specially manufactured goods) which are movable at the time of identification to the contract for sale other than the money in which the price is to be paid, investment securities (chapter 678) and things in action.” Fla. Stat. s. 672.105(1).
The UCC does NOT apply to transactions for services. Transactions for services are governed by common law.
Oftentimes, transactions or contracts include BOTH goods and services. In this scenario, referred to as a hybrid contract, does the UCC or common law apply? In this scenario, courts apply the predominant factor test to determine whether the UCC or common law governs the transaction:
Whether the UCC or the common law applies to a particular hybrid contract depends on “whether the[ ] predominant factor, the [ ] thrust, the[ ] purpose [of the contract], reasonably stated, is the rendition of service, with goods incidentally involved (e.g., contract with artist for painting) or is a transaction of sale, with labor incidentally involved (e.g., installation of a water heater in a bathroom).” In such instances, the determination whether the “predominant factor” in the contract is for goods or for services is a factual inquiry unless the court can determine that the contract is exclusively for goods or services as a matter of law.
Allied Shelving & Equipment, Inc. v. National Deli, LLC, 154 So.3d 482, 484 (Fla. 3d DCA 2015) (citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Survey Finds Tough Labor Market Top-of-mind for Busy Georgia Contractors
July 30, 2019 —
Scott Hazy - Construction ExecutiveIn February 2019, the results of the third Annual Georgia Construction Outlook Survey were released. The survey respondents includes general contractors (44%), specialty contractors (53%) and heavy contractors (3%) with gross revenue size that ranged from in excess of $1 billion to less than $5 million. Three-quarters of respondents reported revenues of less than $25 million. Here’s what they had to say about the state of construction in Georgia.
Financial Performance and 2019 Outlook
It was no surprise to see the majority of respondents reporting increased revenues and margins in 2018. Average gross margins from all respondents increased to 11.3%, up from 9.33% in the prior year. Overall, 72% of respondents saw their gross margins increase and/or remain the same. The largest decrease in margins was seen in the heavy contractor sector, with 33% of respondents reporting a decrease in margins. When it comes to backlog, Georgia is seeing a record number of months in the pipeline and 57% of respondents reported higher backlogs than in the previous year. The increase in backlog helps explain why 84% of respondents are expecting increase in revenues in 2019 over 2018. Interestingly, of those expecting increase in revenue, 40% are anticipating an increase of more than 10% from the prior year. So, the overall financial health of Georgia contractors looks to remain strong at least through 2019.
Reprinted courtesy of
Scott Hazy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Hazy may be contacted at
scott.hazy@btcpa.net