Challenging a Termination for Default
September 23, 2024 —
David Adelstein - Florida Construction Legal UpdatesNo contractor wants to be terminated for default. It is the harshest contractual recourse. It is a recourse that has implications, particularly in the public sector. However, a party needs to be in a position to support the basis of the termination for default, and the terminated party, in most instances, should not be in a position to imply accept the basis of the default. This applies regardless of the project.
In the federal context: “When a contractor challenges a default termination, the government bears the burden of establishing the validity of the termination.” Sergent’s Mechanical Systems, Inc. v. U.S., 2024 WL 4048175, *7 (Fed.Cl. 2024) (internal quotation and citation omitted). Once the government establishes the default, “the contractor bears the burden of establishing that the default was excused by fault of the government.” Id. at *8 (internal quotation and citation omitted).
Relevant considerations as to whether the contractor is in default include the contractor’s failure to meet contract specifications or the required schedule. Sergent’s Mechanical Systems, supra, at *8. “[T]here is ‘a requirement that the contractor give reasonable assurances of performance in response to a validly issued cure notice.” Id. (internal quotation and citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Seattle’s Audacious Aquarium Throws Builders Swerves, Curves, Twists and Turns
January 08, 2024 —
Nadine M. Post - Engineering News-RecordPatrick Nation describes the reinforcing steel for the main tank of the 50,000-sq-ft Seattle Aquarium Ocean Pavilion as a “monster” job for CMC Rebar. In his mind, it was like bending 496 tons of bars “on a golf ball.” In reality, the operation was more like weaving a giant steel basket. Ironworkers had to painstakingly hand-thread the reinforcing steel for the doubly curved and slanted concrete walls of the 350,000-gallon saltwater exhibit—one bar at a time—to create the dense latticework for the 41-ft-tall basket.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Video: Contractors’ Update on New Regulations Governing Commercial Use of Drones
September 01, 2016 —
David R. Cook Jr. – AHHC Construction Law BlogAt a presentation before the AGC of Georgia, AHHC attorneys Mark Hanrahan, David Cook, and Chadd Reynolds covered “Contractors’ Update on New Regulations Governing Commercial Use of Drones.” View the presentation here: https://vimeo.com/177566370
On June 23, 2016, the Department of Transportation and Federal Aviation Administration issued new regulations regarding non-hobby and non-recreational civil operation of small unmanned aircraft systems. These regulations are intended to limit interference with federal airspace while advancing research and safety in commercial industries. They also addressed practical implications and how to comply by the August 29, 2016 deadline.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Where Breach of Contract and Tortious Interference Collide
January 11, 2022 —
Christopher G. Hill - Construction Law MusingsClaims for breach of contract are numerous in the construction law world. Without these claims we construction attorneys would have a hard time keeping the doors open. A 2021 case examined a different sort of claim that could arise (though, “spoiler alert” did not in this case) during the course of a construction project. That type of claim is one for tortious interference with business expectancy.
In Clark Nexsen, Inc. et. al v. Rebkee, the U. S. District Court for the Eastern District of Virginia gave a great explanation of the law of this type of claim in analyzing the following basic facts:
In 2018, Clark Nexsen, Inc. (“Clark”) and MEB General Contractors, Inc. (“MEB”) responded to Henrico County’s (“Henrico”) Request for Proposals (“RFP”) for the design and construction of a sport and convocation center (the “Project”). Henrico initially shortlisted Clark and MEB as a “design-build” team for the Project, but later restarted the search, issuing a second RFP. Clark and MEB submitted a second “design-build” proposal, but Henrico selected Rebkee Co. (“Rebkee”) for certain development aspects of the Project. MEB also submitted proposals to Rebkee, and Rebkee selected MEB as the design-builder for the Project. MEB, at Rebkee’s request, solicited proposals from three design firms and ultimately selected Clark as its design partner. From December 2019 to May 2020, Clark and MEB served as the design-build team to assist Rebkee in developing the Project. In connection therewith, Clark developed proprietary designs, technical drawings, and, with MEB, several cost estimates. In February 2020, MEB submitted a $294,334.50 Pay Application to Rebkee for engineering, design, and Project development work. Rebkee never paid MEB. Henrico paid MEB $50,000.00 as partial payment for MEB’s and Clark’s work. MEB then learned that Rebkee was using Clark’s drawings to solicit design and construction proposals from other companies. On July 23, 2020, Rebkee told MEB that Henrico directed it to cancel the design-build arrangement with MEB and Clark and pursue a different planning method. MEB and Clark sued and Rebkee for, among other claims, tortious interference with a business expectancy. Rebkee moved to dismiss the tortious interference claim.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Pennsylvania Supreme Court Adopts New Rule in Breach-of-the-Consent-to-Settle-Clause Cases
August 19, 2015 —
Sean Mahoney – White and Williams LLPIn Babcock & Wilcox Company, et al. v. America Nuclear Insurers, et al., the Pennsylvania Supreme Court recently held that where a liability insurer has agreed to provide a defense to its insured in an underlying tort action subject to a reservation of rights but refuses to consent to a settlement in that action, the insured may nevertheless accept the settlement over the insurer’s objection where the settlement is “fair, reasonable, and non-collusive” from the perspective of a reasonably prudent person in the insured’s position in light of the totality of the circumstances and is covered. Babcock & Wilcox Company v. America Nuclear Insurers, No. 2 WAP 2014, 2015 WL 4430352 (Pa. Jul. 21, 2015). This decision fills an important gap in Pennsylvania precedent addressing the rules applicable when an insurer refuses to consent to an insured’s settlement of a lawsuit.
In Babcock, the underlying plaintiffs sued Babcock & Wilcox Company and Atlantic Richfield Company (“the Insureds”) alleging that the Insured’s nuclear facilities caused bodily injury and property damage. The Insureds’ liability insurers agreed to defend the Insureds subject to a reservation of rights. The insurers later refused to consent to an offer to settle the underlying action for a total of $80 million because they believed the Insureds were likely to succeed on the merits. Nevertheless, in 2009, the Insureds accepted that offer and settled the underlying action for $80 million, notwithstanding the insurer’s refusal. The Insureds then sought reimbursement of the $80 million settlement from their insurers, who rejected that request on the ground that the Insureds had breached the consent-to-settlement/cooperation provisions of the implicated policies.
Read the court decisionRead the full story...Reprinted courtesy of
Sean Mahoney, White and Williams LLPMr. Mahoney may be contacted at
mahoneys@whiteandwilliams.com
Specific Performance of an Option Contract to Purchase Real Property is Barred Absent Agreement on All Material Terms
December 20, 2017 —
Richard H. Herold - Real Estate Litigation BlogOn November 14, 2017, the Court of Appeals (Division 1), in Offerman v. Granada, LLC, 2017 WL 5352664, reversed a trial court order directing specific performance of an alleged option to purchase real property, holding that the alleged option was too indefinite to be specifically performed because the parties did not agree to all of the material terms of the option.
Tenant-Purchaser Offerman executed a two-year lease with Landlord-Seller Granada, which granted Offerman “the option to purchase [the] property…for a sales price to be determined at that time by an independent appraiser acceptable to both Tenant and Landlord. (Terms and Conditions to be stipulated by both parties at such time).” (emphasis added). Offerman timely advised Granada he intended to exercise the option, asked Granada to name an appraiser, and, when Granada did not respond, Offerman tendered a $240,000 appraisal to exercise the option. Granada did not retain an appraiser but instead simply demanded $350,000 to close the sale. After a bench trial, the Court determined that Offerman was entitled to specific performance, and, as the parties had not agreed to certain terms, held a second evidentiary hearing to resolve the form of judgment, therein naming a title agency to handle the escrow, setting a closing date, allocating the transaction fees between the parties, and ordering Granada to pay for the property inspection.
Read the court decisionRead the full story...Reprinted courtesy of
Richard H. Herold, Snell & WilmerMr. Herold may be contacted at
rherold@swlaw.com
Oregon Duty to Defend Triggered by Potential Timing of Damage
June 28, 2013 —
CDJ STAFFThe Oregon Supreme Court has concluded that if it is possible that damage could have occurred prior to the completion of the project, then the policies in effect at that time are triggered. John Green of Farella Braun + Martel LLP writes that “we have long argued that, since the duty to defend exists if there is any ‘potential’ of covered liability, there is a potential that damage happened before that project was completed, or at any time after completion, triggering all policies in that time frame.” The Oregon court concluded that if property damage could have happened during construction, the insuerer had a duty to defend and “the insured had no burden to establish any additional facts to support that potential.”
Read the court decisionRead the full story...Reprinted courtesy of
Firm Pays $8.4M to Settle Hurricane Restoration Contract Case
December 13, 2022 —
James Leggate - Engineering News-RecordAn electricity distribution infrastructure contractor that worked for the U.S. Army Corps of Engineers on hurricane restoration in Puerto Rico has agreed to pay the government $8.4 million to resolve allegations that it improperly withheld pricing data. The company denies the charges, agreeing to the settlement in order to avoid lengthy litigation.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of