Nevada Legislature Burns Insurers' Rights to Offer Eroding Limits
August 28, 2023 —
William S. Bennett - Saxe Doernberger & Vita, P.C.Nevada’s legislature recently passed a groundbreaking law imposing two prohibitions on insurers. First, the law prohibits insurers from issuing or renewing any liability insurance policy with an “eroding limits” provision. While the first section of the law will have the most immediate effects, the statute goes further, generally prohibiting insurers from limiting the availability of coverage for the costs of defense, legal costs and fees, and other claim expenses. This second section leaves a great deal to interpretation, with the potential to massively expand policyholder rights, and may throw the traditional structure of liability insurance policies into question.
Nevada Statute §679a provides as follows:
Notwithstanding any other provision of law, an insurer, including, without limitation, an insurer listed in NRS 679A.160, shall not issue or renew a policy of liability insurance that contains a provision that:
- Reduces the limit of liability stated in the policy by the costs of defense, legal costs and fees and other expenses for claims; or
- Otherwise limits the availability of coverage for the costs of defense, legal costs and fees and other expenses for claims.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
WBennett@sdvlaw.com
Insurer Must Defend Additional Insured Though Its Insured is a Non-Party
November 18, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe plaintiff insurer's motion for partial summary judgment seeking an order that defendant insurer was obligated to defend a non-party as an additional insured was granted. Am Empire Surplus Lines Ins. Co. v. Burlington Ins. Co., 2019 N. Y. Misc. LEXIS 4145 (N. Y. Sup. Ct. July 25, 2019).
Quality Building Construction, LLC was the contractor hired to work on exterior facade of a building owned by Central Park West Corporation. The underlying complaint alleged that Quality caused plastic spacers and pedestals used for the penthouse terrace to fall down the roof drain riser. A clog and rainwater backup resulted in water damage to apartment 8A. The resulting damage was allegedly due to the clogged roof drain riser.
Quality subcontracted the work to Mega State, Inc. The subcontract required Mega to indemnify and hold Quality harmless against claims in connection with Mega's work, as well as name Quality as an additional insured on a primary, non-contributory bases under Mega's CGL policy. Burlington issued a policy to Mega naming Quality as an additional insured. American Empire issued a CGL policy to Quality.
Quality was sued in the underlying action, but Mega was not. American Empire tendered a demand for coverage to Mega and Burlington, relying on the agreement between Quality and Mega. Burlington responded that Mega was not liable for the alleged damages. American Empire sued Burlington. Subsequently, Burlington accepted the tender to defend Quality in the underlying action, and reserved rights as to whether Burlington's policy was primary and on the question of indemnification. American Empire agreed to withdraw its suit if Burlington would modify its reservation of rights. Burlington refused.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Real Estate & Construction News Roundup (06/06/23) – Housing Woes, EV Plants and the Debate over Public Financing
July 10, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, we look at the increasing difficulty of purchasing a home, potential international fallout from a new trade deal a renewed commitment by one American automaker to electric vehicles, and more!
It’s becoming
increasingly more difficult for house hunters to find homes, specifically in certain major cities. (Khristopher J. Brooks, CBS)
Due to years of overuse and a decades-long drought, Arizona has
halted new housing construction of parts of metro Phoenix. (AP via NBC)
After several claims by the FTC over privacy concerns regarding its voice assistant Alexa and doorbell camera Ring, Amazon has
agreed to pay over $30 million in fines. (Ayana Archie, NPR)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
The California Legislature Passes SB 496 Limiting Design Professional Defense and Indemnity Obligations
November 21, 2017 —
Mark Himmelstein & Jenny Guzman – Newmeyer & Dillion LLPOriginally published by CDJ on June 15, 2017
Since 2008 when the California legislature limited subcontractor indemnity obligations, the design professional community has been shouting “what about us?” Well, the legislature finally responded and a new law that limits design professional’s defense and indemnity obligations to their percentage of fault goes into effect on January 1, 2018.
THE NEW LAW – SB 496
SB 496 amends California Civil Code section 2782.8 and states that indemnity agreements must be limited to the negligence, recklessness or willful misconduct of the indemnitee (i.e. no more Type I indemnity with design professionals). The amendment also provides that “in no event shall the cost to defend charged to the design professional exceed the design professional’s proportionate percentage of fault”, with a limited opportunity for reallocation in the event another defendant is judgment proof.
However, the duty to defend still remains and still arises at the time of the tender of the defense (both issues that were unsuccessfully targeted by the design professional lobbyists).
Reprinted courtesy of
Mark Himmelstein, Newmeyer & Dillion LLP and
Jenny Guzman, Newmeyer & Dillion LLP
Mr. Price may be contacted at mark.himmelstein@ndlf.com
Ms. Zucker may be contacted at jenny.guzman@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Was Jury Right in Negligent Construction Case?
September 30, 2011 —
CDJ STAFFYes, said the South Carolina Court of Appeals in Pope v. Heritage Communities, Inc. Heritage Communities developed Riverwalk, a community in South Carolina. During the earlier trial, HCI “conceded that construction defects existed at Riverwalk, and repairs needed to be made.” The trial court found that the construction was negligent, awarding the property owners association $4.25 million in actual damages and $250,000 in punitive damages, with the class of owners awarded $250,000 in actual damages and $750,000 in punitive damages. HCI appealed on nine issues. All were rejected by the appeals court.
The court rejected HCI’s claim that the judge’s instruction to the jury suggested to the jury that “the court had already determined that Appellants were willful, wanton, and reckless.” But here, the appeals court found “no reversible error.”
The general contractor for Riverwalk was BuildStar. Off-site management and sale were managed by Heritage Riverwalk, Inc., which also owned title to the property. Both these companies were owned by Heritage Communities, Inc. During the trial, an HCI employee testified that “the three corporations shared the same officers, directors, office, and telephone number.” The trial court found that the three entities were amalgamated. This was upheld by the appeals court.
Nor did the appeals agree with the HCI that the trial court had improperly certified a class. The owners were seen as properly constituting a class. Further, the court held that the property owners’ losses were properly included by the trial court. HCI objected at trial to the inclusion of evidence of subsequent remedial measures, however, as they did not object that it was inadmissible, the issue could not be addressed at appeal.
HCI argued on appeal that the trial court should not have allowed evidence of defects at other HCI developments. The appeals court noted that “the construction defects at the other HCI developments were substantially similar to those experienced by Riverwalk.”
The court additionally found that the negligence claims, the estimated damages (since full damage could not be determined until all defective wood was removed), and the award of punitive damages were all properly applied.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Negligent Misrepresentation in Sale of Building Altered without Permits
September 30, 2011 —
CDJ STAFFThe Supreme Court of New Hampshire has ruled in the case Wyle v. Lees. The Leeses owned a two-unit apartment building in North Conway, New Hampshire. They hired a contractor to add a third, larger apartment, including a two-car garage. The Leeses and their contractor submitted a building permit application. They were informed that site plan review was required. After receiving approval on the site plan, construction started. At no point did they obtain a building permit and the construction was never inspected. The Leeses subsequently added more space to the unit, reducing parking spaces below the minimum required. Again, they did not obtain a building permit.
In 2007, three years after all these changes were complete, the Leeses sold their building to Mr. Wyle. To the question “are you aware of any modifications or repairs made without the necessary permits?” they answered “no.” About six weeks after closing, Wyle “received a letter from the town code enforcement officer regarding the legality of the removal of a garage door from the new unit.” A subsequent inspection revealed “numerous building and life safety code violations.”
Mr. Wyle brought a claim against the Leeses for negligent misrepresentation. The defendants filed a motion “seeking to preclude economic loss damages.” At a two-day bench trial, Mr. Wyle won. The Leeses appealed.
The appeals court found that “the defendants negligently misrepresented that the premises were licensed for immediate occupancy and that the defendants had obtained all necessary permits,” and thus upheld the lower court’s finding of negligent misrepresentation. The appeals court also rejected the Leeses’ argument that damages must be apportioned on all parties, including “the plaintiff himself, the plaintiff’s building inspector, and the defendant’s contractor,” finding a lack of “adequate evidence.”
The Leeses further argued that they were unaware that modifications and repairs were accomplished without the required permits. The appeals court noted that “the trial court found that both the conditional approval and final approval for the site plan stated that a building permit and a certificate of occupancy were required prior to any use.” The court concluded that the Leeses “knew or should have known of the falsity of their representation.”
The appeals affirmed the findings of the trial court.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Venue for Miller Act Payment Bond When Project is Outside of Us
December 02, 2019 —
David Adelstein - Florida Construction Legal UpdatesThe proper venue for a Miller Act payment bond claim is “in the United States District Court for any district in which the contract was to be performed and executed, regardless of the amount in controversy.” 40 U.S.C. s. 3133(b)(3)(B).
Well, there are a number of federal construction projects that take place outside of the United States. For these projects, where is the correct venue to sue a Miller Act payment bond if there is no US District Court where the project is located? A recent opinion out of the Southern District of Florida answers this question.
In U.S. ex. rel. Salt Energy, LLC v. Lexon Ins. Co., 2019 WL 3842290 (S.D.Fla. 2019), a prime contractor was hired by the government to design and construct a solar power system for the US Embassy’s parking garage in Burkina Faso. The prime contractor hired a subcontractor to perform a portion of its scope of work.
The subcontractor remained unpaid in excess of $500,000 and instituted a Miller Act payment bond claim against the payment bond surety in the Southern District of Florida, Miami division. The surety moved to transfer venue to the Eastern District of Virginia arguing that the Southern District of Florida was an improper venue. The court agreed and transferred venue. Why?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Court Requires Adherence to “Good Faith and Fair Dealing” in Construction Defect Coverage
September 30, 2011 —
CDJ STAFFThe California Court of Appeals has ruled in the case of Allied Framers, Inc. v. Golden Bear Insurance Company. Allied had been sued in a construction defect case and its primary insurer had become insolvent. Coverage for Allied’s defense was paid for by the California Insurance Guarantee Association through June 8, 2006. When warned that CIGA’s involvement was ending, Allied notified Golden Bear, which declined to provide coverage.
In the matters that followed, Golden Bear claimed that Allied had not exhausted its $1 million in primary insurance. Allied then showed that $1 million had already been paid out in the case. A few months thereafter, Golden Bear offered a $500,000 settlement on behalf of Allied which was rejected. Thereafter, Golden Bear hired new counsel to defend Allied. Golden Bear received, but allegedly did not pay, invoices Allied sent from their former counsel. Golden Bear finally settled the construction defect case for $2 million.
Allied’s original counsel sued Allied for payment. Golden Bear declined coverage. Allied then claimed that Golden Bear liable on several counts, arising from its failure to settle the construction defect action earlier than it did and its failure to pay Allied’s counsel. Golden Bear demurred, arguing that Allied had now exhausted is coverage with the $2 million settlement. The lower court sustained Golden Bear’s demurrer, dismissing Allied’s complaints.
The appeal court reviewed Allied’s seven complaints and sustained most of them. However, the court did reverse the trial court’s order in regard to Allied’s complaint that Golden Bear breached an implied covenant of good faith and fair dealing. The appeals court was not convinced that Golden Bear properly evaluated the settlement demand in the underlying construction defect case. The court found three other ways in which Golden Bear’s actions might show bad faith, in refusing to pay defense fees “after promising [Allied] such costs would be paid in full,” “failing to advise Allied about ‘actual or potential negative consequences of agreeing to the proposed settlement,’” and that their choice of counsel “failed to protect [Allied’s] interests in the negotiation.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of