Hurricane Claim Cannot Survive Anti-Concurrent Causation Clause
May 15, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe court upheld the insurer's denial of coverage for hurricane damage caused by storm surge. Heritage Motorcoach Resort & Marina Condominium Association, Inc v. Axis Ins. Co., 2023 U.S. Dist. LEXIS 58931 (S.D. Ala. April 4, 2023).
Heritage operated a resort with a marina, dock and clubhouse. Hurricane Sally caused damage to the property. Heritage submitted a claim to its insurer, Axis. Axis investigated the claim. One investigator reported that the marina structures sustained damage caused by storm tide forces, wave action and debris impact. He opined that the marina structures did not sustain wind damage. When deposed, he testified that there was a combination of vessels and wave action causing damage to the marina. A second investigator found that the storm drove boats and other debris into the marina area causing much of the damage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Moving Finish Line: Statutes of Limitation and Repose Are Not Always What They Seem
June 01, 2020 —
Kenneth E. Rubinstein & Nathan Fennessy - Construction ExecutiveHaving an end date for risk is important to construction professionals who need to know when they can close their books and destroy files relating to old projects. While professionals typically look to the statute of limitations and repose, these deadlines can sometimes be harder to determine than one might think.
State Laws Prohibiting Alteration of Statutes of Limitation
Many contractors seek to control the extent of their risk by negotiating the length of their liability period. In some instances, contractors may seek to shorten the statute of limitations to protect against stale claims. While in other instances, owners periodically negotiate for longer periods to ensure that they will not be time barred from pursuing valid claims. While the majority of states enforce such contractual provision, a number of states hold such clauses unenforceable. In these instances, the state’s original statute of limitations will apply regardless of what the contract says.
Reprinted courtesy of
Kenneth E. Rubinstein & Nathan Fennessy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Rubenstein may be contacted at krubinstein@preti.com
Mr. Fennessy may be contacted at nfennessy@Preti.com
Read the court decisionRead the full story...Reprinted courtesy of
The Role of Code Officials in the Design-Build Process
November 16, 2023 —
Grace Calengor - Construction ExecutiveBuilding codes are an integral part of the design-build process, but what role do building code professionals play throughout that process? Kevin McOsker, vice president of technology services for the government relations department at the International Code Council, breaks it down, from basic design to groundbreaking ideas to incorporating new technology and retrofitting older builds.
McOsker, whose experience includes serving as building official for the city of Las Vegas, is no stranger to striking architecture and the safety protocols that go along with it. He believes that safety protocol starts before the contractors begin building and that contractors should be involved throughout the entire journey.
Reprinted courtesy of
Grace Calengor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Stadium Intended for the 2010 World Cup Still Not Ready
June 18, 2014 —
Beverley BevenFlorez-CDJ STAFFFour years after the HM Pitje Stadium in Pretoria, South Africa was expected to open, the stadium, which was meant to be used during the 2010 World Cup, remains closed. IOL News reported that upgrades began in 2006, “[b]ut since then there have been delays and problems with construction which may see the stands having to be rebuilt.” One of the defects that prevented the stadium from being used for the World Cup was that the slope of the main pavilion was too steep.
City of Tshwane spokesman Selby Bokaba told IOL News: “Upgrading of the stadium will take approximately two calendar years, with the completion date reliant on the approval and budget availability.”
Read the court decisionRead the full story...Reprinted courtesy of
Windstorm Exclusion Found Ambiguous
September 10, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe Second Circuit reversed the District Court's issuance of summary judgment to the insurer because a windstorm exclusion was deemed ambiguous. 7001 East 71st Street, LLC v. Continental Cas. Co., 2018 U.S. App. LEXIS 17334 (2nd Cir. June 26, 2018).
A windstorm during Hurricane Sandy caused the roof of 7001 East 71st Street LLC (7001) to tear, allowing rainwater to seep in and damage 7001's "Covered Equipment" as defined by the policy. Continental denied coverage based upon the windstorm exclusion and the district court granted summary judgment to Continental.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Harrisburg Sought Support Before Ruinous Incinerator Retrofit
September 20, 2017 —
Jonathan Barnes & Richard Korman - Engineering News-RecordWhen former Harrisburg, Pa., Mayor Stephen Reed (D) and his aides set out to retrofit the city’s aging incinerator in late 2000, the project spun out of control over the coming years, enlarging the debt the city owed on the facility to $300 million and sinking Harrisburg into financial ruin.
Reprinted courtesy of
Jonathan Barnes, ENR and
Richard Korman, ENR
ENR staff may be contacted at ENR.com@bnpmedia.com
Read the court decisionRead the full story...Reprinted courtesy of
2021 Executive Insights: Leaders in Construction Law
August 16, 2021 —
Donald Berry - Construction ExecutiveGregory Cokinos, President and CEO, Cokinos | Young
First, experience in the construction industry is of primary importance and vital to successfully negotiating construction contracts and handling construction claims and disputes. Even a mildly complex construction dispute is more than most non-construction lawyers can properly handle. Issues concerning scheduling, productivity, change management and risk shifting (among many others) are complex and unique to construction and can be further complicated by the procedural and substantive law that differs from jurisdiction to jurisdiction.
Second, it is essential that your law firm has a culture of representing construction professionals. Understanding construction nomenclature and how construction projects are staffed, organized and documented saves time and money in an already expensive and time-consuming process.
You cannot overstate the advantage of shared resources within an established construction firm when evaluating and handling construction matters. A law firm that dedicates a significant portion of its practice to the construction industry is uniquely positioned to realize this advantage. Finally, as I tell our young lawyers, “success” only comes before “work” in the dictionary. Hard work is the key to successfully negotiating a contract or executing a litigation plan in this complex industry. So, look for a firm that is not afraid of working long days and weekends to achieve success.
Reprinted courtesy of
Donald Berry, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
CGL Coverage for Liquidated Damages and the Contractual Liability Exclusion
October 09, 2023 —
Stu Richeson - The Dispute ResolverLiquidated delay damages are common in construction contracts and are generally imposed when a contractor fails to achieve substantial completion within the time required by the contract. While contracts like the AIA A201-2017 have provisions for extending the time to achieve substantial completion when delays are caused by circumstances beyond the contractor’s control, delays can result from factors other than improper management or planning and the like, for which the owner is not required to give the contractor additional time. Courts are split on whether there is ever coverage under a CGL policy for contractually agreed upon liquidated delay damages.
Liquidated delay damages are often excluded under the contractual liability exclusion of most CGL policies. The contractual liability exclusion excludes coverage for “liability for which the Insured is obligated to pay damages by reason of the assumption of liability in a contract or agreement.” Courts often find the contractual liability exclusion in a CGL policy precludes coverage for liquidated delay damages, because such damages are contractual in nature and are triggered by the failure to bring the contract to substantial completion by a fixed deadline, regardless of the cause of the delay. However, some courts will look to the cause of the delay and find that there is coverage under a CGL policy for liquidated delay damages that are the result of property damage caused by an accident or occurrence.
In Clark Const. Grp., Inc. v. Eagle Amalgamated Serv., Inc., 01-2478-DV, 2005 WL 2092998, at *1 (W.D. Tenn. Aug. 24, 2005) a general contractor entered a contract for the renovation of the convention center in Memphis. Part of the project included the demolition of a structure attached to the convention center. The demolition work was improperly performed by a subcontractor and resulted in damage to the convention center.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com