Construction Costs Must Be Reasonable
May 17, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to proving a construction cost, particularly a cost in dispute, the cost must be REASONABLE. Costs subject to claims must be reasonably incurred and the party incurring the costs must show the costs are reasonable.
An example of the burden falling on the contractor to prove the reasonableness of costs is found in government contracting.
“[T]here is no presumption that a [government] contractor is entitled to reimbursement ‘simply because it incurred…costs.’” Kellogg Brown & Root Services, Inc. v. Secretary of Army, 973 F.3d 1366, 1371 (Fed. Cir. 2020) (citation omitted). Stated differently, a federal contractor is not entitled to a presumption of reasonableness just because it incurs costs. Id.
In government contracting, the Federal Acquisition Regulations (known as “FAR”) puts the burden of reasonableness on the contractor that incurred the costs. Id.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Congratulations 2016 DE, MA, NJ, NY and PA Super Lawyers and Rising Stars
October 27, 2016 —
White and Williams LLPThirty-two White and Williams lawyers have been named by Super Lawyers as a Delaware, Massachusetts, New Jersey, New York or Pennsylvania "Super Lawyer" while fourteen received "Rising Star" designations. Each lawyer who received the distinction competed in a rigorous selection process which took into consideration peer recognition and professional achievement. The lawyers named to this year's Super Lawyer list represent a multitude of practices throughout the firm.
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Court Slams the Privette Door on Independent Contractor’s Bodily Injury Claim
May 06, 2019 —
Brett G. Moore, Michael C. Parme, Lindsey N. Ursua & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPIn Johnson v. The Raytheon Company, Inc., Case No. B281411 (2019) WL 1090217, plaintiff Laurence Johnson (Johnson) was a maintenance engineer employed by an independent contractor that provided control room staff to defendant Raytheon Company, Inc. (“Raytheon”). Johnson was monitoring the computers in the control room when he received low water level alarms pertaining to the water cooling towers. Johnson went to the cooling tower wall in order to look over the wall and verify the water level. Johnson saw the upper half of an extension ladder leaning against the cooling tower’s wall. The ladder had a warning sign which said, “CAUTION” and “THIS LADDER SECTION IS NOT DESIGNED FOR SEPARATE USE.” Despite these warnings, Johnson used the ladder. As he was climbing the ladder it slid out causing him to fall and suffer injuries.
Johnson sued Raytheon, the hirer of the independent contractor, arguing the ladder, among other things, was unsafe and lead to Johnson’s injuries. Johnson believed that Raytheon’s course of conduct of leaving a platform ladder (as opposed to the extension ladder) at the wall constituted an implied agreement to always have one present, on which the independent contractor’s employees relied. Johnson further argued that Raytheon was negligent in providing a dangerous extension ladder, as opposed to a platform ladder, at the wall on the night of the accident.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Brett G. Moore,
Michael C. Parme,
Lindsey N. Ursua and
Lawrence S. Zucker II
Mr. Moore may be contacted at bmoore@hbblaw.com
Mr. Parme may be contacted at mparme@hbblaw.com
Ms. Lindsey may be contacted at lursua@hbblaw.com
Mr. Lawrence may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
HOA Has No Claim to Extend Statute of Limitations in Construction Defect Case
October 28, 2011 —
CDJ STAFFThe California Court of Appeals ruled on September 20, 2011 in the case of Arundel Homeowners Association v. Arundel Green Partners, a construction defect case involving a condominium conversion in San Francisco. Eight years after the Notice of Completion was filed, the homeowners association filed a lawsuit alleging a number of construction defects, including “defective cabinets, waterproofing membranes, wall-cladding, plumbing, electrical wiring, roofing (including slope, drainage and flashings), fire-rated ceilings, and chimney flues.” Three years of settlement negotiations followed.
Negotiations ended in the eleventh year with the homeowners association filing a lawsuit. Arundel Green argued that the suit should be thrown out as California’s ten-year statute of limitations had passed. The court granted judgment to Arundel Green.
The homeowners then filed for a new trial and to amend its complaint, arguing that the statute of limitations should not apply due to the doctrine of equitable estoppel as Arundel Green’s actions had lead them to believe the issues could be solved without a lawsuit. “The HOA claimed that it was not until after the statute of limitations ran that the HOA realized Arundel Green would not keep its promises; and after this realization, the HOA promptly brought its lawsuit.” The trial court denied the homeowners association’s motions, which the homeowners association appealed.
In reviewing the case, the Appeals Court compared Arundel to an earlier California Supreme Court case, Lantzy. (The homeowners also cited Lantzy as the basis of their appeal.) In Lantzy, the California Supreme Court set up a four-part test as to whether estoppel could be applied. The court applied these tests and found, as was the case in Lantzy, that there were no grounds for estoppel.
In Arundel, the court noted that “there are simply no allegations that Arundel Green made any affirmative statement or promise that would lull the HOA into a reasonable belief that its claims would be resolved without filing a lawsuit.” The court also cited Lesko v. Superior Court which included a recommendation that the plaintiffs “send a stipulation?Ķextending time.” This did not happen and the court upheld the dismissal.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Killer Subcontract Provisions
January 20, 2020 —
Patrick McNamara - Porter Law GroupWe are frequently requested by subcontractor clients to review the subcontract that has been prepared by the prime contractor, before our client signs it. While no two agreements are identical, there are a number of problematic contract provisions that appear in many agreements. Here is a list of ten such provisions (and their variations) that are potential “deal breakers”:
- PAY IF/WHEN PAID (e.g. “Contractor shall have the right to exhaust all legal remedies, including appeals, prior to having an obligation to pay Subcontractor.”) “Pay-if-paid” provisions (“Receipt of payment from Owner shall be a condition precedent to Contractor’s duty to pay Subcontractor”) are illegal in California. However, the only legal limit on “Pay-When-Paid” provisions is that payment must be made “within a reasonable time.” The example above, as written, essentially affords the prime contractor a period of several years following completion of the project before that contractor has an independent duty to pay its subcontractors – not a “reasonable” amount of time, to those waiting to be paid. A compromise is to provide a time limit, such as 6 months or one year following substantial completion of the project.
- CROSS-PROJECT SET-OFF (e.g. “In the event of disputes or default by Subcontractor, Contractor shall have the right to withhold sums due Subcontractor on this Project and on any other project on which Subcontractor is performing work for Contractor.”) Such provisions are problematic and likely unenforceable, as they potentially bar subcontractors’ lien rights. Such provisions should be deleted.
- CONTRACTOR/SUBCONTRACTOR RESPONSIBILITY FOR DESIGN QUALITY (e.g. “Subcontractor warrants that the Work shall comply with all applicable laws, codes, statutes, standards, and ordinances.”) Unless a subcontractor’s scope of work expressly includes design work, this provision should either be deleted or modified, with the addition of the following phrase: “Subcontractor shall not be responsible for conformance of the design of its work to applicable laws, codes, statutes, standards, and ordinances.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
California Subcontractor Gets a Kick in the Rear (or Perhaps the Front) for Prematurely Recorded Mechanics Lien
October 21, 2019 —
Garret Murai - California Construction Law BlogCalifornia provides three statutorily recognized construction payment remedies: (1) mechanics liens; (2) stop payment notices; and (3) payment bond claims. Each is intended to provide payment protections for those who furnish labor, materials and services on a construction project. However, each is also different in important ways.
One of those differences has to do with timing. Specifically, when the statutory payment remedy may be used by a claimant. Stop payment notices can be served at any time during a project even before a claimant has completed its work. However, mechanics liens may only be recorded and payment bond claims may only be made after a claimant has completed or ceased performing its work.
In Precision Framing Systems, Inc. v. Luzuriaga, Case No. E069158 (August 29, 2019), the 4th District Court of Appeal examined whether a subcontractor had prematurely recorded a mechanics lien and, thereby, was prevented from filing a lawsuit to foreclose on its mechanics lien.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
PSA: Pay If Paid Ban Goes into Effect on January 1, 2023
December 05, 2022 —
Christopher G. Hill - Construction Law MusingsI have
written a couple of times here at Musings regarding the new pay-if-paid legislation passed by the General Assembly last session. While the statute has some inconsistencies and a working group has made
some recommendations, the legislation as passed will go into effect on January 1, 2023, without any changes (at least until next session). As always, such action by our legislature here in Virginia will create work for construction attorneys assisting their clients to amend contracts to meet the new rules.
Essentially (and with minor inconsistencies between public and private contracts), the bill requires that any construction contract entered into after January 1, 2023 have the following provisions:
- On public projects: A payment clause that obligates a contractor on a construction contract to be liable for the entire amount owed to any subcontractor with which it contracts. Such contractor shall not be liable for amounts otherwise reducible due to the subcontractor’s noncompliance with the terms of the contract. However, in the event that the contractor withholds all or a part of the amount promised to the subcontractor under the contract, the contractor shall notify the subcontractor, in writing, of his intention to withhold all or a part of the subcontractor’s payment with the reason for nonpayment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
A Brief Discussion – Liquidating Agreements
June 27, 2022 —
Gerard J. Onorata - Peckar & Abramson, P.C.During a construction project, it is not uncommon for disputes to arise between a general contractor and a subcontractor. Frequently, these disputes involve claims for extra work and delay damages that can be attributed to the owner of the project due to deficient design or unforeseen conditions. When these occasions arise, the parties can often resolve these claims without the need for litigation or arbitration by entering into a “liquidating agreement.”
What is a Liquidating Agreement?
Because there is no direct contractual relationship between a subcontractor and an owner, there does not exist a legal basis for a subcontractor to assert a breach of contract claim against a project owner. In legal parlance, this is known as “lack of contractual privity.” A liquidating agreement bridges this contractual gap and allows a subcontractor to pass its claim against the owner through the general contractor. Essentially, with a liquidating agreement, the general contractor acts as a conduit for passing through the subcontractor’s claim.
Read the court decisionRead the full story...Reprinted courtesy of
Gerard J. Onorata, Peckar & Abramson, P.C.Mr. Onorata may be contacted at