Georgia Local Government Drainage Liability: Nuisance and Trespass
November 29, 2021 —
David R. Cook Jr. - Autry, Hall & Cook, LLPA long-running dispute between a landowner and a municipality has escalated to the Georgia Court of Appeals and in the federal court for the Northern District of Georgia.[1] The municipality maintained a stormwater system that discharged on property uphill from the landowner’s property. The uphill property was used as an illegal dump, and debris washed downhill from the dump to the landowner’s property. The debris clogged the landowner’s surface water drainage system, which caused flooding of the property and a building.
State Case
The landowner sued for trespass, nuisance, takings, and inverse condemnation. While the other claims were barred by the four-year statute of limitations, the court addressed the plaintiff-landowner’s claim for continuing nuisance.
Municipalities may be liable when they negligently construct or maintain a sewer or drainage system that causes repeated flooding of property, such that it results in a continuing, abatable nuisance.[2] For a municipality to be liable for maintenance of a nuisance:
the municipality must be chargeable with performing a continuous or regularly repetitious act, or creating a continuous or regularly repetitious condition, which causes the hurt, inconvenience or injury; the municipality must have knowledge or be chargeable with notice of the dangerous condition; and, if the municipality did not perform an act creating the dangerous condition, . . . the failure of the municipality to rectify the dangerous condition must be in violation of a duty to act.[3]
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
New Becker & Poliakoff Attorney to Expand Morristown Construction Litigation Practice
September 10, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to New Jersey On-Line, Matthew Meyers has joined the Becker & Poliakoff firm at its Morristown office. Meyers “specializes in commercial litigation, with an emphasis on complex construction defects and real estate disputes.”
“This is an exciting move for me,” Meyers stated, as quoted by New Jersey On-Line. “I was attracted to Becker by the firm’s depth of construction litigation talent and the additional resources available for these claims. My new firm will not only enhance my practice but will elevate the level of services I provide to clients, which has always been my top priority.“
Read the court decisionRead the full story...Reprinted courtesy of
Three Reasons Late Payments Persist in the Construction Industry
December 22, 2019 —
Patrick Hogan - Construction ExecutiveConstruction professionals are all too familiar with the payment issues that plague the construction industry. Contractors, subcontractors and material suppliers often have to deal with payment delays and even nonpayment—affecting cash flow and their ability to meet expenses.
According to an Atradius study, a quarter of all B2B invoices issued in North America are overdue. The construction industry accounted for one-third of those past-due invoices, and many contractors and construction business owners do not have a positive outlook on the industry's payment issues. The same survey found 55% of U.S. firms think there will be no change in the industry’s payment practices over the coming months—one-third even expects an increase in late payments.
These findings show that managing cash flow is a significant challenge in the construction industry. Having a negative cash flow will push the company toward financial trouble, which may ultimately lead to its demise. Understanding the reasons why payment issues persist in construction will help contractors protect their business, prevent these issues from happening or at least minimize their effect on the current operations.
Reprinted courtesy of
Patrick Hogan, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Philadelphia Revises Realty Transfer Tax Treatment of Acquired Real Estate Companies
January 05, 2017 —
Nancy Frantz, Kevin Koscil & James Vandermark – White and Williams LLPOn December 8, 2016, the Philadelphia City Council voted unanimously to amend the ordinance governing realty transfer taxes in an effort to increase tax revenue. The current combined realty transfer tax rate in Philadelphia is 4.0% and will increase to 4.1% after December 31, 2016.[1] The amendment significantly impacts how taxes are imposed upon transfers of ownership in so-called “real estate companies” and effectively eliminates deals commonly referred to as 89-11 transactions. The amendment mainly focuses on transfers of real estate companies, rather than direct transfers of real estate, but it also affects certain direct transfers of real estate in exchange for noncash consideration.
Reprinted courtesy of White and Williams LLP
Nancy Frantz,
Kevin Koscil and
James Vandermark
Ms. Frantz may be contacted at frantzn@whiteandwilliams.com
Mr. Koscil may be contacted at koscilk@whiteandwilliams.com
Mr. Vandermark may be contacted at vandermarkj@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Data Is Critical for the Future of Construction
April 19, 2022 —
Raghi Iyengar - Construction ExecutiveAccording to a
recent study, real-time visibility and access to critical data and insights are vital for rapid construction decision-making. Notably, inaccurate and missing data cost the industry almost $2 trillion in 2020. Even more surprising, construction companies often don’t know if they’ve made or lost money until the job is complete or if they’re on schedule until they start falling behind. These findings portray an important reality for the industry: Construction needs to establish and optimize data strategies to ensure it has the visibility control, and transparency needed to improve efficiency and productivity on projects.
Luckily, while historically slow to change, the construction industry has begun to adopt technologies that help firms improve efficiency and productivity on projects. With this technology, contractors can establish and optimize data strategies to ensure they have visibility, control and transparency.
Embracing data is a game changer as the industry continues to expand. In fact, the report from Autodesk and FMI cited above found that the construction companies using data technologies and strategies saw
fewer project delays, less rework and fewer change orders.
Reprinted courtesy of
Raghi Iyengar, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
You Can Take This Job and Shove It!
June 10, 2015 —
Garret Murai – California Construction Law BlogThat’s it.
You’ve had it.
They can take their job and shove it!
But can you really tell an owner on a construction project to proverbially shove it where the sun don’t shine?
Well, far be it for me to tread on your First Amendment Rights or stick my nose into the subsequently brought public disturbance charges against you. But can you legally tell an owner to shove it, and that you’re no longer going to perform work on their [insert expletive] project? Well, indeed you can, in limited circumstances, and it’s called a “Stop Work Notice.”
Note: A stop work notice is different from a stop payment notice.
What is a stop work notice?
A stop work notice is a notice given by a direct contractor to a project owner that the contractor will stop work if an amount owed to the contract is not paid within 10 days after notice is given.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Traub Lieberman Attorneys Recognized as 2020 Super Lawyers and Rising Stars
November 16, 2020 —
Traub LiebermanTraub Lieberman is pleased to announce that Super Lawyers has named nineteen of our attorneys as 2020 Super Lawyers and Rising Stars.
Super Lawyers selects attorneys using a multiphase selection process in which nominations and evaluations are combined with independent research. Each candidate is evaluated on 12 indicators of peer recognition and professional achievement. Selections are made on an annual, state-by-state basis. The objective is to create a credible, comprehensive and diverse listing of outstanding attorneys that can be used as a resource for attorneys and consumers searching for legal counsel.
The Super Lawyers designation recognizes the top 5% of attorneys in the U.S. and the Rising Stars designation recognizes the top 2.5% of attorneys in the U.S. under the age of forty, as chosen by their peers and through independent research within their practice area.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Hunton Insurance Team Wins Summary Judgment on Firm’s Own Hurricane Harvey Business Income Loss
March 23, 2020 —
Michael S. Levine & Michelle M. Spatz - Hunton Insurance Recovery BlogA Texas judge has ruled that Hunton Andrews Kurth is entitled to coverage from Great Northern Insurance Co., a unit of Chubb, Ltd. (“Chubb”), for losses its predecessor firm suffered when Hurricane Harvey closed its Houston office and disrupted business in 2017.
The court agreed with Hunton’s position that the policy, written specifically for a law firm, covered its business income loss until the firm’s operations were restored to their pre-loss levels. The court rejected in its entirety Chubb’s argument that coverage lasted only until the physical damage that closed the building had been repaired. Rather, siding with Hunton, the court found that the policy language affords, in addition to ordinary business income coverage during the damage period, “extended period” coverage that commences after the damaged property is repaired and after the firm’s operations resume.
From August 27 to August 31, 2017, the firm was forced to close its Houston office due to flooding and damage caused by Hurricane Harvey. While employees were permitted to return to the office on August 31, income did not return to its pre-loss level until September 14, 2017. The firm submitted a claim to Chubb for the loss sustained from August 27 to September 14, but Chubb paid only for income loss suffered during the 3-day closure period, and refused to cover the loss suffered after the building reopened.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Michelle M. Spatz, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Spatz may be contacted at mspatz@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of