California Case Is a Reminder That Not All Insurance Policies Are Alike Regarding COVID-19 Losses
April 05, 2021 —
Neal I. Sklar & Joshua A. Morehouse - Peckar & Abramson, P.C.A recent case from the Central District of California reminds us that not all insurance policies are alike. Depending on the particular policy, losses from the COVID-19 outbreak could qualify as property damage and therefore could be recoverable under an all-risk insurance policy.
COVID-19 has in many cases imposed significant costs on contractors, and in a host of ways. Contractors’ attempts to recover these costs from owners or insurers have at times been frustrated by contractual or policy language written after a lengthy time, during which the risk of a pandemic on the scale of COVID-19 was not as much of a concern as it is now. This has led contractors to explore new, often creative legal theories in their attempts to recover costs flowing from COVID-19.
A recent Complaint filed in the Central District of California focuses on all-risk property insurance policies and the potential for contractors who have purchased such policies to classify contamination from COVID-19 as an insurable property loss.
In AECOM v. Zurich Insurance Company, Case No. 2:21-cv-00237-JAK-MRW (C.D. Cal), a contractor purchased “all-risk” property insurance from Zurich. This policy covered “economic losses from all risks not expressly excluded.” According to the Complaint, the presence of COVID-19 on its properties “physically alter[ed] air, airspace, and surfaces preventing… (the contractor) from using its properties for their intended purpose and function.”
Reprinted courtesy of
Neal I. Sklar, Peckar & Abramson, P.C. and
Joshua A. Morehouse, Peckar & Abramson, P.C.
Mr. Sklar may be contacted at nsklar@pecklaw.com
Mr. Morehouse may be contacted at jmorehouse@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Spreading Cracks On FIU Bridge Failed to Alarm Project Team
May 20, 2019 —
Scott Judy & Richard Korman - Engineering News-RecordOn the morning of last year’s Florida International University pedestrian bridge collapse, when the engineer of record assured project team members that there were no safety risks related to cracks propagating across a part of the unusual single-truss structure, other project team members voiced mild concern, but no alarm. In hindsight, considering that the bridge had no inherent structural redundancy as it sat, incomplete, straddling a busy highway—and would suffer a sudden, catastrophic and deadly collapse just hours later—the team’s lack of urgency remains puzzling, say engineering experts contacted by ENR for comment.
Reprinted courtesy of
Scott Judy, ENR and
Richard Korman, ENR
Mr. Judy may be contacted at mailto:judys@enr.com
Mr. Korman may be contacted at kormanr@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
Reminder: Quantum Meruit and Breach of Construction Contract Don’t Mix
July 30, 2015 —
Christopher G. Hill – Construction Law MusingsConstruction contracts (preferably written ones) are near and dear to my heart here at Construction Law Musings. In a world where the contract is king, having a written construction agreement is a key component of any properly run construction project. However, even with the best construction contract there are claims (Murphy was an optimist after all).
When making these claims, we construction lawyers tend to plead both the breach of contract and quantum meruit (or in non lawyer speak- unjust enrichment) when drafting a complaint in a construction dispute. A recent case out of the Western District of Virginia federal district court reminds us all that these two counts must be plead alternatively because they simply cannot exist in a lawsuit from beginning to end.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
New NEPA Rule Restores Added Infrastructure Project Scrutiny
May 10, 2022 —
Pam McFarland - Engineering News-RecordThe White House Council on Environmental Quality has finalized a regulation that restores basic project environmental review practices that were in place prior to changes made during the Trump administration. The rule is the first of two that will have the Biden administration’s stamp on how such reviews are done under the National Environmental Policy Act (NEPA) for major federal construction projects.
Reprinted courtesy of
Pam McFarland, Engineering News-Record
Ms. McFarland may be contacted at mcfarlandp@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Risk Management and Contracting after Hurricane Irma: Suggestions to Avoid a Second Disaster
September 14, 2017 —
Stephen H. Reisman, Gary M. Stein & Adam P. Handfinger – Peckar & Abramson, P.C.Peckar & Abramson attorneys have assisted contractors in the immediate aftermath of several Hurricanes, including Andrew in 1992, Wilma in 2005, Ike in 2008, and Sandy in 2012. Based on this experience, we offer some post-storm strategies for contracting and risk management in three situations:
- Ongoing projects in the area directly impacted by the storm;
- Projects remote from the storm-impacted areas, but which may be affected by material or labor shortages; and
- Requests for assistance in recovery/clean-up/rebuild eff orts, which would be new projects.
Projects Directly Impacted By Hurricane Irma:
1. Immediately review each Owner contract to determine what notices are required for delays and/or extra costs arising from the storm. Contract notice requirements and time limits vary, whether for force majeure or other similar time and compensation rights. There is no effective one-size-fits-all solution. While the initial notice letters will likely look very similar, you should make sure that each is sent as required by the contract. Check each contract’s requirements for particulars regarding content, the form of delivery, and parties and individuals designated to receive the letters as well as carbon copy recipients like the architect. Follow-up notices and time periods differ from contract to contract and should be tracked so that if, for example, a follow-up notice is required in a week per the contract terms, it is tracked to ensure compliance.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Stephen H. Reisman,
Gary M. Stein and
Adam P. Handfinger
Mr. Reisman may be contacted at sreisman@pecklaw.com
Mr. Stein may be contacted at gstein@pecklaw.com
Mr. Handfinger may be contacted at ahandfinger@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Foreman in Fatal NYC Trench Collapse Gets Jail Sentence
December 21, 2016 —
Mary B. Powers – Engineering News-RecordWilmer Cueva, a construction foreman for Queens, N.Y.-based excavation subcontractor Sky Materials, was sentenced on Dec. 15 to up to three years in prison for causing the death of 22-year-old worker Carlos Moncayo, and endangering other workers at a lower Manhattan retail project site. Manhattan District Attorney Cyrus Vance said the workers were in an unprotected 13-ft trench that collapsed in 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Mary B. Powers, Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
Account for the Imposition of Material Tariffs in your Construction Contract
March 28, 2018 —
David Adelstein – Florida Construction Legal UpdatesAfter Hurricane Irma, I wrote an article that contractors should revisit the
force majeure provisions in their construction contracts. Not later. But Now.
The force majeure provision is an important provision in a construction contract to account for certain uncertainties that you have NO control over.
Recently, another reason has given rise to contractors needing to revisit their force majeure provisions, as well as any provisions dealing with material escalations. Not later. But now. The
imposition of raw steel and aluminum tariffs (tax on imported goods) and the back-and-forth regarding a potential trade war leads to the kind of uncertainty that should be assessed as a risk.
A risk in both time and cost from material escalations.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
You Cannot Arbitrate Claims Not Covered By The Arbitration Agreement
March 16, 2020 —
David Adelstein - Florida Construction Legal UpdatesRegardless of the type of contract you are dealing with, “[a]rbitration provisions are contractual in nature, and therefore, construction of such provisions and the contracts in which they appear is a matter of contract interpretation.” Wiener v. Taylor Morrison Services, Inc., 44 Fla. L. Weekly D3012f (Fla. 1st DCA 2019). This means if you want to preserve your right to arbitrate claims you want to make sure your contract unambiguously expresses this right. Taking this one step further, if you want to make sure an arbitrator, and not the court, determines whether the claim is arbitrable if a dispute arises, you want to make sure that right is expressly contained in the arbitration provision.
For example, in Wiener, a homeowner sued a home-builder for violation of the building code – a fairly common claim in a construction defect action. The homeowner’s claim dealt with a violation of building code as to exterior stucco deficiencies. The home-builder moved to compel the lawsuit to arbitration based on a structural warranty it provided to the homeowner that contained an arbitration provision. The structural warranty, however, was limited and did not apply to non-load-bearing elements which, per the warranty, were not deemed to have the potential for a major structural defect (e.g., a structural defect to load-bearing elements that would cause the home to be unsafe or inhabitable). The trial court compelled the dispute to arbitration pursuant to the arbitration provision in the structural warranty.
Read the court decisionRead the full story...Reprinted courtesy of