Dispute between City and Construction Company Over Unsightly Arches
April 01, 2014 —
Beverley BevenFlorez-CDJ STAFFThe city of Swartz Creek, Michigan alleged that Slagter Construction’s work on “Texas-style arches along a new bridge” was “terrible” and doesn’t “match up to what the company promised when it took the job to build the $20,000 walkways that include the arches,” reported M Live.
However, Slagter Construction “maintains its repairs were adequate and claims in a letter to the state that the issue shouldn't resolved by local officials who have ‘no formal training or education on these matters.’”
According to M Live, “[t]he two sides are set to meet on May 5 with MDOT officials on May 5 in Bay City for arbitration.”
Read the court decisionRead the full story...Reprinted courtesy of
No Duty to Defend Construction Defect Claims under Kentucky Law
March 25, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court determined that the insurer was not obligated to defend construction defect claims under Kentucky law. Westfield Ins. Co. v. Kentuckiana Commercial Concrete, LLC, 2023 U.S. Dist. LEXIS 222674 (W.D. Ky. Dec. 14, 2023).
HRB, the owner of an apartment complex, filed an arbitration demand against the general contractor, Doster Commercial Construction, for allegedly doing faulty concrete work in the construction of the apartments. Doster added its concrete subcontrator Kentuckiana Commercial Concrete - and 16 other subcontractors - to the arbitration. Kentuckiana tendered the claim to its insurer, Westfield. Wesfield defended. Doster claimed it was an additional insured under the Westfield policy and also sought coverage. Westfield refused the defend Doster. Westfield argued there was no "occurrence."
Westfield then sued both Doster and Kentuckiana in federal court, seeking a declaration that it had no duty to defend either. Westfield moved for a judgment on the pleadings.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Illinois Court of Appeals Addresses Waiver and Estoppel in Context of Suit Limitation Provision in Property Policy
February 05, 2024 —
James M. Eastham - Traub LiebermanIn Naperville Hotel Partners, LLC v. Liberty Mut. Fire Ins. Co., 2023 IL App (3d) 220440-U the Illinois Third District Court of Appeals addressed whether failure to include reference to a limitations provision in reservation of rights correspondence to an insured can be deemed a waiver of the provision or otherwise estop the insurer from relying on the provision.
The claim involved water damage sustained at the Insured’s motel as a result of numerous rain events that occurred between 2015 and 2020. Liberty Mutual issued an insurance policy that covered several buildings including the subject hotel. The policy required that any legal action based on the coverage had to be brought "within two (2) years after the date on which the physical damage occurred, extended by the number of days between the date you submitted the statement of loss to us and the date we deny the claim in whole or in part."
Plaintiffs filed their claim with Liberty Mutual in May 2019. In June of 2019 Liberty Mutual sent a reservation of rights letter to the Insured which requested more information and listed the "immediate written notice of loss" provision as a potential basis for excluding coverage but did not list the two-year time-limitation on legal action. Liberty Mutual also did not mention the provision in subsequent communications with the Insured.
Read the court decisionRead the full story...Reprinted courtesy of
James M. Eastham, Traub LiebermanMr. Eastham may be contacted at
jeastham@tlsslaw.com
How Finns Cut Construction Lead Times in Half
December 17, 2024 —
Aarni Heiskanen - AEC BusinessRakennustieto organized a Q&A on December 5, 2024, titled “Halving Construction Lead Times—Responsible or Irresponsible?” The discussion focused on speeding up residential construction and renovations.
The experts answering questions were representatives from two Finnish contractors (COfLOW and Fira), a client organization (HOAS), a building materials retailer (STARK), and a research institute.
Can you halve construction lead time without sacrificing quality?
Jaana Matilainen of Rakennustieto asked the panelists whether halving construction time is a realistic goal today, whether they can provide any examples, and if the speed-up has increased or decreased quality.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
No Coverage for Home Damaged by Falling Boulders
March 08, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe policy's earth movement exclusion barred coverage for the home damaged by large boulders rolling down from the hillside above. Sullivan v. Nationwide Affinity Ins. Co. of Am., 2021 U.S. App. LEZXIS 628 (10th Cir Jan. 11, 2021).
Plaintiffs' home sustained extensive damage when two or three large builders rolled down a steep hillside and struck the home. The insurer, Nationwide, hired an engineering firm that determined the boulders were not influenced by meteorological conditions such as torrential rain or high winds. The report noted that rockfall hazards existed primarily due to an undercut sandstone outcrop, and evidenced by numerous rocks from rockfall events that scattered Plaintiffs' property.
Based on the report, Nationwide denied coverage under the earth movement exclusion. The exclusion provided Nationwide did "not insure for loss caused directly or indirectly by . . . Earth Movement" and regardless of "whether or not the loss event results in widespread damage or affects a substantial area." The policy further defined "earth movement" to include "landslide . . . or any other earth movement including earth sinking, risking or shifting."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Real Estate & Construction News Roundup (05/10/23) – Wobbling Real Estate, Booming (and Busting) Construction, and Eye-Watering Insurance Premiums
May 22, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, the commercial real estate sector continues to wobble, construction booms and busts, flood insurance premiums reach eye-watering levels, and more.
- In its latest Financial Stability report, the Federal Reserve acknowledges that the shaky commercial real estate sector could potentially harm the U.S. financial system. (Courtenay Brown, Axios)
- New data from the California Department of Finance shows that even though the state’s population significantly decreased during the COVID-19 pandemic, home building soared, reaching levels not seen since 2008. (Terry Castleman, Los Angeles Times)
- Already weakened by rising interest rates, inflation and debt, Sweden’s real estate sector took another hit as SBB’s shares continued to slump. (Reuters)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
CalOSHA Updates its FAQ on its COVID-19 Emergency Temporary Regulations
March 22, 2021 —
Garret Murai - California Construction Law BlogAs we reported in early December, CalOSHA adopted emergency temporary regulations requiring, among other things, that employers implement a written COVID-19 prevention program, that notice be given by employers to employees in the event of potential COVID-19 exposure, and that employers continue to pay employees who have been exposed to COVID-19 even if the employee has no paid time off available. In conjunction with the emergency temporary regulations, CalOSHA posted a FAQ on the emergency regulations.
On February 26, 2021, CalOSHA updated its FAQ. Among other things, the updated FAQ updates the following sections of the FAQ:
- Scope of Coverage: Clarifies that the emergency regulations apply even to workplaces with only one employee but that it does not apply to employees working remotely.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Blackouts Require a New Look at Backup Power
April 06, 2020 —
John McBride - Construction ExecutiveRecent blackouts on both East and West coasts are causing commercial property owners to reassess their need for backup power. The likelihood of more-frequent blackouts means backup power must evolve from ensuring the safe exit of office workers to enabling core business functions to continue uninterrupted. That’s a major shift in preparedness that construction executives should consider in future planning.
In New York City on July 13, 2019, a Con Edison blackout left 72,000 customers in Manhattan and Queens without power primarily because of a flawed connection at an electrical substation. Eight days later, a second Con Edison blackout left more than 50,000 customers, mostly in Brooklyn, without power due to high usage during a heat wave. These events occurred even though, as Con Edison stated, the New York City grid is one of the most complex and technologically advanced in the world and contains multiple layers of redundancy.
In northern and central California in late October, 2019, intentional blackouts were implemented by Pacific Gas and Electric (PG&E) on a massive scale in response to out-of-control wildfires. “Never before in California history have more than 2 million people gone five days without electrical power because of the intentional safety policy of a utility,” reported the Los Angeles Times. It was the second massive blackout in California in two weeks, after PG&E had earlier shut off power to almost 2 million people in rolling blackouts.
The blackouts on both coasts are remarkable not only for their breadth but for the range of causes—from limiting wildfires sparked in part by faulty, above-ground, power lines to a flawed connection at a substation to overuse during a heat wave. The conditions creating those causes are not likely to subside, and Con Edison warned this summer of more service outages to come. In California, The Washington Post writes, “blackouts are redefining the prosperous state.”
Reprinted courtesy of
John McBride, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of