First Lumber, Now Drywall as Canada-U.S. Trade Tensions Escalate
November 30, 2016 —
Katia Dmitrieva – BloombergA new trade dispute has broken out between Canada and the U.S. that threatens to raise prices in Canada’s already overheated housing markets.
The Canada Border Services Agency imposed a provisional tariff as high as 277 percent on U.S. drywall imports in September after ruling that manufacturers were dumping the product, or selling it below the price in their home market, undercutting local suppliers.
The tariff has raised the price of drywall, or gypsum board as it’s also called, by as much as 30 percent and is causing “chaos” and delays as contractors scramble for alternative sources. Some builders say the tariff could add as much as C$13,000 ($9,671) to the cost of a new home, which would amount to a C$2.6 billion increase to the roughly 200,000 homes built in Canada each year.
Read the court decisionRead the full story...Reprinted courtesy of
Katie Dmitrieva, BloombergMs. Dmitrieva may be followed on Twitter @katiadmi
Application Of Two Construction Contract Provisions: No-Damages-For-Delay And Liquidated Damages
February 14, 2022 —
David Adelstein - Florida Construction Legal UpdatesA recent Florida opinion between a prime contractor and a Florida public body touches upon two important issues: (1) the application of a no-damage-for-delay provision; and (2) the application of a liquidated damages provision. Both provisions find there way into many construction contracts. Unfortunately, the opinion is sparse on facts. Nevertheless, the application of these provisions is worthy of consideration.
In this opinion, Sarasota County v. Southern Underground Industries, Inc., 2022 WL 162977 (Fla. 2d DCA 2022), a county hired a contractor to install sanitary and water piping underneath a waterway. During construction, a nearby homeowner complained that vibration from the drilling caused damage to his home. As a result, the county stopped the contractor’s work to address a potential safety issue, as it was contractually entitled to do. The contractor hired a structural engineer to inspect the house and the engineer issued a report determining that any alleged damage was cosmetic and that there was sufficient monitoring of the vibrations to prevent future damage. The contractor also had an insurance policy to cover any homeowner claim for damage. However, upon receipt of the engineer’s report, the county did not lift its stop work order. Rather, the stop work order remained in place for an additional 71 days.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
While Construction Permits Slowly Rise, Construction Starts and Completions in California Are Stagnant
December 05, 2022 —
John Kazanovicz & Jason Feld - Kahana FeldThere is an interesting phenomenon happening in the California construction market since the Summer of 2022. There is a steady but slow rise in the construction building permits being issued throughout California. According to the U.S. Census and the U.S. Department of Housing and Urban Development’s joint announcement (https://www.census.gov/construction/nrc/pdf/newresconst.pdf) of new residential construction statistics for September 2022, privately‐owned housing units authorized by building permits in September were at a seasonally adjusted annual rate of 1,564,000. This is 1.4 percent above the revised August rate of 1,542,000. While this is slightly lower than a year ago (3.2 percent below the September 2021 rate of 1,615,000), the trend for obtaining new home permits was reportedly ahead of the projected rates given the market conditions and inflation throughout the country. Interestingly, single‐family authorizations in September were at a rate of 872,000 which was also 3.1 percent below the revised August 2022 figure of 900,000. Authorizations of units in buildings with five units or more were at a rate of 644,000 in September. Overall, while slowly recovering from the record lows during the height of the pandemic, the economic forecast for new home construction in California is positive, but cautious.
The flip side of this coin is the construction starts in California, which continue to remain stagnant despite additional building permits being issued. Privately‐owned housing starts in September were at a seasonally adjusted annual rate of 1,439,000. This is 8.1 percent (±14.9 percent) below the revised August estimate of 1,566,000 and is 7.7 percent (±11.5 percent) below the September 2021 rate of 1,559,000. Single‐family housing starts in September were at a rate of 892,000; this is 4.7 percent (±10.7 percent) below the revised August figure of 936,000. The September rate for units in buildings with five units or more was 530,000.
Reprinted courtesy of
John Kazanovicz, Kahana Feld and
Jason Feld, Kahana Feld
Mr. Kazanovicz may be contacted at jkazanovicz@kahanafeld.com
Mr. Feld may be contacted at jfeld@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Must Pay for Matching Siding of Insured's Buildings
December 02, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Seventh Circuit found that the insurer was obligated to pay for siding of a building that was not damaged by hail so that it matched the replaced damaged portions of the siding. Windridge of Naperville Condominium Association v. Philadelphia Indem. Ins. Co., 2019 U.S. App. 23607 (7th Cir. Aug. 7, 2019).
A hail and wind storm damaged buildings owned by Windridge. The storm physically damaged the aluminum siding on the buildings' sought and west sides. Philadelphia Indemnity, Windridge's insurer, contended that it was only required to replace the siding on those sides. Windridge argued that replacement siding that matched the undamaged north and east elevations was no longer available, so Philadelphia had to replace the siding on all four sides of the buildings to that all of the siding matched.
Windridge sued and moved for summary judgment. The district court ruled that matching was required. The only sensible result was to treat the damage as having occurred to the building's siding as a whole.
The policy was a replacement-cost policy. Philadelphia promised to "pay for direct physical 'loss' to 'Covered Property' caused by or resulting from" the storm, with the amount of loss being "the cost to replace the lost or damaged property with other property . . . of comparable material and quality . . . and . . . used for the same purpose." The loss payment provision offered four different measures for loss, leaving Philadelphia free to choose the least expensive: (1) pay the value of the lost or damaged property; (2) pay the cost of repairing or replacing the lost or damaged property; (3) take all or any part of the property at an agreed or appraised value; or (4) repair, rebuild or replace the property with other property of like kind and quality.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
You’ve Been Suspended – Were You Ready?
April 20, 2020 —
Curtis W. Martin, Patrick J. Greene, Jr. & Levi W. Barrett - Peckar & Abramson“Effective tomorrow … the City is suspending all regular activity at construction sites in Boston.” This was just one of the surprises that greeted contractors last week. Contractors and owners with projects across the country are scrambling to comply with mandated governmental suspensions. Project participants should begin contingency planning for possible project shutdowns.
Reacting to Suspension
Your legal rights and remedies will be largely determined by your contract and the laws applicable to it. But some basic principles will be applicable depending on the source of the suspension.
Suspension by the Owner: An owner work suspension suggests review of the contract’s suspension of work clause. Federal contractors would look to the FAR Suspension of Work clause, FAR 52.242-14, but that is applicable if the suspension is by the Contracting Officer; the US would argue that a systemic suspension was a sovereign act and outside the FAR clause.
Contractors for private work and state or municipal work may have contractual suspension of work clauses. At least some suspension clauses provide relief for time and money.
Reprinted courtesy of Peckar & Abramson attorneys
Curtis W. Martin,
Patrick J. Greene and
Levi W. Barrett
Mr. Martin may be contacted at cmartin@pecklaw.com
Mr. Greene may be contacted at pgreene@pecklaw.com
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Statute of Limitations Upheld in Construction Defect Case
September 30, 2011 —
CDJ STAFFThe Missouri Court of Appeals has ruled in Ball v. Friese Construction Co., finding that Mr. Ball’s claims were barred by the statute of limitations.
Mr. Ball hired Friese Construction Company to build a single-family home. The sale was completed on March 29, 2001. That December, Mr. Ball complained of cracks in the basement floor. SCI Engineering, n engineering firm, hired by Friese, determined that the home’s footing had settled and recommended that Mr. Ball hire a structural engineer to determine if the footings were properly designed and sized. In September 2002, the structural engineer, Strain Engineering, determined that the cracks were due to slab movement, caused in part by water beneath the slab, recommending measures to move water away from the foundation. In 2005, Mr. Ball sent Friese correspondence “detailing issues he was having with the home, including problems with the basement slab, chimney structure, drywall tape, and doors.” All of these were attributed to the foundation problems. In 2006, Friese stated that the slab movement was due to Ball’s failure to maintain the storm water drains.
In 2009, Ball received a report from GeoTest “stating the house was resting on highly plastic clay soils.” He sued Friese in May, 2010. Friese was granted a summary judgment dismissing the suit, as the Missouri has a five-year statute of limitations. Ball appealed on the grounds that the extent of the damage could not be determined until after the third expert report. The appeals court rejected this claim, noting that a reasonable person would have concluded that after the conclusion of SCI and Strain Engineering that “injury and substantial damages may have occurred.”
The court concluded that as there were not “continuing wrongs causing new and distinct damages,” he should have filed his lawsuit after the first two expert reports, not waiting seven years for a third expert to opine.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Mitigating Mold Exposure in Manufacturing and Multifamily Buildings
July 31, 2024 —
Laura Champagne - Construction ExecutiveAs hurricanes season and summer storms approach, more apartment complexes, commercial and industrial properties, and public buildings are at risk of leaking and flooding. Water-saturated structures are prime breeding grounds for mold, but there are ways to prevent, detect and remove it before it becomes a serious and costly issue—for buildings and building residents alike. Being proactive limits an owner’s exposure to the liability of debilitating health effects and structural safety concerns.
Mold requires three things to grow: water, food and humidity. Water will stealthily penetrate small porous surfaces of any building material, such as drywall, plaster, wood, concrete or even fabrics. These materials serve as a food source to quickly produce more fungus. Common sources of undetected water flow include foundation problems, poorly installed windows, roof malfunctions, gutter clogs, storm damage, leaky pipes, improper drainage, HVAC issues, faulty appliances, bathroom vent issues and wet building materials. Mold loves humidity and thrives in dark, warm environments, such as attics, basements, lofts, building corners and bathrooms.
Reprinted courtesy of
Laura Champagne, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Prejudice to Insurer After Late Notice of Hurricane Damage Raises Issue of Fact
January 03, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied the insurer's motion for summary judgment on admittedly late notice because prejudice to the insured remained an issue of fact. Guzman v. Scottsdale Ins. Co., 2021 U.S. Dist. LEXIS 219625 (S.D. Fla. Nov. 15, 2021).
The insured first noticed water leaking into his kitchen from the roof during Hurricane Irma on September 10, 2017. Various attempts were made by the insured to fix the leak, but none were successful. After the hurricane, the roof continued to leak whenever it rained. Notice was finally given to Scottsdale, the insurer, on April 19, 2020.
Scottsdale retained structural engineer Nazario Ramirez, who inspected the property twice. He also had photographs of the rapids. Ramirez denied being prejudiced during his inspections. Based on the pictures aerial photography and weather research, he determined that the damage was caused by underlayment failing, which could have resulted from age and deterioration or poor construction. When Scottsdale's corporate representative was deposed, he testified that Ramirez was able to determine the cause of the damage to the roof.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at