Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
The Show Must Go On: Navigating Arbitration in the Wake of the COVID-19 Outbreak
July 20, 2020 —
Justin K. Fortescue, Zachery B. Roth & Marianne Bradley - White and Williams LLPThe recent COVID-19 outbreak has altered life for all of us, in ways both big and small. Unprecedented restrictions relating to the pandemic have forced individuals across the globe to change the ways in which they live and work. Perhaps not surprisingly, these restrictions have also changed the way we resolve disputes. Just as virtual conferencing has become the “new normal” for family gatherings and social events, it has also become the “new normal” for everything from mediation, to oral argument, to full-blown hearings.
To be sure, there are a number of advantages to conducting adversarial proceedings virtually. First and foremost, it results in substantial cost savings for the parties involved. In-person proceedings typically require significant travel expenses, including airline tickets, hotel reservations, and food and beverage stipends. The use of a virtual forum essentially eliminates these expenses, cutting costs dramatically for attorneys, clients, judges, and arbitrators alike.
Virtual conferencing also affords the opportunity for increased participation from party representatives living across the country, or even across the world. While demanding work schedules often make it impossible for multiple party representatives to attend a deposition, or even a hearing, in person, virtual proceedings require much less of a time commitment. Because these virtual proceedings require participants to spend less time away from other work-related obligations, party representatives are able to attend proceedings that they may otherwise have had to miss.
Reprinted courtesy of White and Williams LLP attorneys
Justin K. Fortescue,
Zachery B. Roth and
Marianne Bradley
Mr. Fortescue may be contacted at fortescuej@whiteandwilliams.com
Mr. Roth may be contacted at rothz@whiteandwilliams.com
Ms. Bradley may be contacted at bradleym@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
2019 Promotions - New Partners at Haight
January 15, 2019 —
Haight Brown & Bonesteel LLPHaight proudly announces the promotion of Renata Hoddinott, Sarah Marsey and Annette Mijianovic to Partner in January 2019.
Renata and Sarah joined Haight’s San Francisco office in 2016. Renata relocated from a litigation firm in the Los Angeles area. She focuses her practice on professional liability, general liability, risk management & insurance law and transportation law.
Before coming to Haight, Sarah was with a respected trial firm in Anchorage, Alaska. She handles a variety of complex matters in appellate law, food safety, construction law and general liability.
Annette has been with Haight’s Los Angeles office for almost 12 years. Annette joined the firm as a summer clerk in 2007 and has continued to build her practice handling cases related to commercial litigation, products liability and transportation law.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Renata L. Hoddinott,
Sarah A. Marsey and
Annette F. Mijanovic
Ms. Hoddinott may be contacted at rhoddinott@hbblaw.com
Ms. Marsey may be contacted at smarsey@hbblaw.com
Ms. Mijanovic may be contacted at amijanovic@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Merger to Create Massive Los Angeles Construction Firm
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFAECOM Technology Corp., a Los Angeles engineering and construction firm, has agreed to pay $4 billion to acquire URS Corp., their San Francisco competitor. According to the Sacramento Bee, “The combined company will employ about 95,000 people in 150 countries.”
AECOM is currently building the World Trade Center in New York, and previous projects include the Los Angeles Police Department headquarters, and renovations to the Port of Los Angeles and the Bradley international terminal at the Los Angeles International Airport, the Sacramento Bee reported. Furthermore, “URS has worked on the Garden Grove (22) Freeway reconstruction, the UCLA Ronald Reagan Medical Center, the Port of Long Beach, the Gold Line Eastside Extension in Los Angeles and the Disneyland resort expansion.”
Read the court decisionRead the full story...Reprinted courtesy of
The Problem With Building a New City From Scratch
May 10, 2022 —
Nolan Gray - BloombergFrom California to Miami and points in between, housing costs in the U.S. are skyrocketing, bringing bidding wars in hot markets and fears of a fresh surge in homelessness as renters scramble for an affordable place to live.
The deepening housing crunch — and the intractable resistance that residents often put up when the prospect of new housing emerges nearby — has led some observers to ask: Why don’t we just make new cities?
“When China needs new places for people to live, they just build a new city,” Nathan J. Robinson recently wrote in Current Affairs, contemplating all the undeveloped land in between California’s costly major urban areas. “They’ve built 600 of them since 1949.”
At first blush, it might seem obvious. But history is full of failed, unfinished or underperforming scratch-built city projects, in California and elsewhere, and more are in the pipeline.
To learn more about how we might best approach building new cities, CityLab talked to a person who’s had a hand in planning a few of them: Alain Bertaud, a fellow at the Marron Institute for Urban Management and a globetrotting former city planner at the World Bank. Our conversation has been edited for length and clarity.
Read the court decisionRead the full story...Reprinted courtesy of
Nolan Gray, Bloomberg
Colorado House Bill 17-1279 – A Misguided Attempt at Construction Defect Reform
March 29, 2017 —
David McClain - Colorado Construction LitigationOn March 17th, House Bill 17-1279, concerning the requirement that a unit owners’ association obtain approval through a vote of unit owners before filing a construction defect action, was introduced and assigned to the House State, Veterans, and Military Affairs Committee. The bill is currently scheduled for its first committee hearing on March 29th, at 1:30 in the afternoon. While, on its face, this appears to be a step in the right direction towards instituting “informed consent” before an HOA can file a construction defect action, the bill actually restricts the ability of developer to include more stringent requirements in the declaration of covenants, conditions, and restrictions for an association, thereby lowing the threshold of “consent” required to institute an action.
House Bill 17-1279 would amend C.R.S. § 38-33.3-303.5 to require an association’s executive board to mail or deliver written notice of the anticipated commencement of a construction defect action to each unit owner and to call a meeting of the unit owners to consider whether to bring such an action. Any construction professional against which a claim may attend the unit owners’ meeting and have an opportunity to address the unit owners and may include an offer to remedy any defect in accordance with C.R.S. § 13-20-803.5(3). The conclusion of the meeting would initiate a 120-day voting period, during which period the running of any applicable statutes of limitation or repose would be tolled. Pursuant to this bill, an executive board may only institute a construction defect action only if authorized by a simple majority of the unit owners, not including: 1) any unit owned by any construction professional, or affiliate of a construction professional, involved in the design, construction, or repair of any portion of the project; 2) any unit owned by a banking institution; 3) any unit owned in which no defects are alleged to exist, and/or 4) any unit owned by an individual deemed “nonresponsive.”
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Georgia Update: Automatic Renewals in Consumer Service Contracts
August 31, 2020 —
David R. Cook - AHC BlogGeorgia HB 1039 amends O.C.G.A. § 13-12-3 to provide additional protections for consumers who enter into service contracts containing lengthy automatic renewal provisions.
Pre-Existing Requirement: For service contracts with an initial term of twelve months or longer and an automatic renewal provision for more than one month, unless the consumer terminates the agreement, sellers must provide written or electronic notification of the automatic renewal provision to the consumer. The notification must be provided to the consumer between 30 and 60 days before the cancellation deadline under such renewal provision. The notice must also “clearly and conspicuously” disclose that unless the consumer cancels, the agreement will automatically renew and disclose how the consumer may obtain details about the automatic renewal provision and cancellation procedure. The process by which a consumer may obtain such information must include the seller’s contact information (e.g., specific phone number or address), reference to the contract, or any other method provided.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Navigating Complex Preliminary Notice Requirements
March 30, 2016 —
Christopher G. Hill – Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome back a good friend, Scott Wolfe. Scott is the founder of zlien, a cloud-based platform that gives construction industry participants control over their financial risk and payment processes. The zlien platform manages the mechanics lien compliance process for all parties in the contracting chain, automating and optimizing the exchange of preliminary notices, monitoring lien rights and exposure, and exchanging lien waivers. zlien empowers over 10,000 companies to optimize their credit and financial risk management, and works to promote a fair and transparent construction payment process, improve B2B relationships, facilitate faster payments, and reduce legal and financial risk.
Sending preliminary notice is the most important step in mechanics lien compliance. A majority of states require preliminary notice (sometimes called a pre-lien notice or notice to owner) from contractors, material suppliers, and other construction parties. Even if preliminary notice is not required, however, it is best practice to send this document on all projects for a variety of reasons.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com