Three Recent Cases Strike Down Liquidated Damages Clauses In Settlement Agreements…A Trend Or An Aberration?
November 01, 2021 —
Adam M. Tuckman - ConsensusDocsBeginning more than one century ago, owners and contractors generally have adopted the convention of including liquidated damages in their contracts to fix potential liability for delay (and other losses) at the inception of the project. The proliferation of liquidated damages clauses in modern contracts can be attributed to economic and legal factors. From the owner’s standpoint, it may be exceedingly difficult to prove the actual cost impact of a delayed completion of the project. A properly calculated liquidated damages rate would save the owner the significant expense of quantifying its delay damages. On the contractor’s side, a reasonable amount of liquidated damages may be preferable to uncapped or unknown liability, allowing the contractor to more accurately price its bid and efficiently allocate risk.
Coinciding with, or perhaps a leading cause of, the industry’s embrace of liquidated damages provisions, was the shift in courts throughout the country from disfavoring such clauses to accepting them (within limits) as an appropriate exercise of contract rights. While some variation exists among the states, courts have generally recognized that liquidated damages clauses are a viable alternative to proof of actual loss so long as (i) actual losses were difficult to quantify, and (ii) the stipulated sum bears a reasonable relationship to the anticipated loss at the time of contracting. See, e.g., Restatement (Second) of Contracts § 356. Conversely, a clause that penalizes the breaching party rather than serving as an estimate of probable loss is likely to be found unenforceable.
Read the court decisionRead the full story...Reprinted courtesy of
Adam M. Tuckman, Watt, Tieder, Hoffar, & Fitzgerald, LLPMr. Tuckman may be contacted at
atuckman@watttieder.com
Update to Washington State Covid-19 Guidance
November 23, 2020 —
Brett M. Hill - Ahlers Cressman & Sleight PLLCYesterday, November 15, 2020, Governor Inslee announced modifications to the current COVID-19 restrictions in response to the current rise in cases across Washington State.
There are no additional restrictions on construction at this time. However, during the Governor’s press conference yesterday, he did indicate that positive cases were increasing on construction sites, and that they would be tracking the statistics over the next 2 – 3 weeks – to see if additional restrictions would be necessary for construction sites in the future. Additionally, the construction industry group is meeting with the Governor’s office today, November 16, 2020, and we will keep you informed of any changes as a result of that meeting.
Unless otherwise specifically noted, the modifications take effect at 12:01 a.m., Tuesday, November 17, 2020. All modifications to existing prohibitions set forth herein shall expire at 11:59 p.m., Monday, December 14, 2020, unless otherwise extended. If an activity is not listed below, currently existing guidance shall continue to apply. If current guidance is more restrictive than the below listed restrictions, the most restrictive guidance shall apply. These below modifications do not apply to education (including but not limited to K-12, higher education, trade and vocational schools), childcare, health care, and courts and judicial branch-related proceedings, all of which are exempt from the modifications and shall continue to follow current guidance. Terms used in this proclamation have the same definitions used in the Safe Start Washington Phased Reopening County-by-County Plan.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers Cressman Sleight PLLCMr. Hill may be contacted at
brett.hill@acslawyers.com
Additional Insured Not Entitled to Indemnity Coverage For Damage Caused by Named Insured
February 23, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe additional insured unsuccessfully sought to recover damages to its building caused by the named insured. Brit UW, Ltd. v. Tripar, Inc., 2017 U.S. Dist. LEXIS 2462 (N.D. Ill. Jan. 6, 2017).
Davis Russell Real Estate and Management LLC hired Tripar, Inc., a general contractor, to renovate a 12-unit apartment building. The entire roof was to be replaced by a roofing subcontractor. Davis Russell drafted a Professional Services Agreement (PSA) that governed the project. Tripar was to obtain a CGL policy and provide a certificate of insurance evidencing the coverage. Davis Russell was to be named as an additional insured.
Tripar's insurance broker prepared a certificate of insurance reflecting that a CGL policy was issued to Tripar by Brit UW, Ltd. But the certificate clearly stated that it was not issued by the insurer and that it did not alter coverage. The certificate of insurance further stated that it conferred no rights upon the holder.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Ambitious Building Plans in Boston
November 18, 2011 —
CDJ STAFFAlthough most are unlikely to change the Boston skyline, there are several large projects on the drawing boards. The site BostInnovation covered ten of them in a recent post. Downtown Boston will be the site of several of these large projects, including three towers to be added to the Christian Science Plaza, a 404-unit residential tower in the Theater District, and perhaps the largest of these projects, a 47-story tower to be built over Copley Plaza, which will tower over the adjacent buildings. None of the planned buildings will challenge the Hancock Tower’s 60 stories.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Illinois Court Assesses Factual Nature of Term “Reside” in Determining Duty to Defend
October 30, 2023 —
James M. Eastham - Traub LiebermanIn State Farm Fire & Cas. Co. v. Guevara, 2023 IL App (1st) 221425-U, P2, the Illinois First District Court of Appeals addressed an insurance carrier’s duty to defend under a homeowners insurance policy. The underlying suit stemmed from an alleged injury suffered at a residence located in Berwyn, Illinois and owned by named insured Luz Melina Guevara, a defendant in the suit. After Guevara tendered the suit, State Farm filed a complaint for declaratory judgment seeking a declaration that it had no duty to defend or indemnify Guevara because Guevara did not “reside” at the insured premises.
The policy defined the "insured location" as the "residence premises," and residence premises was defined as "the one, two, three or four-family dwelling, other structures, and grounds or that part of any other building; where you reside and which is shown in the Declarations." In response to the underlying lawsuit, Guevara had filed an answer and affirmative defenses in which Guevara denied the allegation that "At all relevant times, [Guevara] resided in Berwyn, Cook County, Illinois." Guevara admitted that she owned the Berwyn property but denied that she "resided in, maintained and controlled the property". The declaratory judgment complaint alleged (among other things) that, based on admissions by Guevara in her answer, the Berwyn residence was not an "insured location" under the State Farm policy. State Farm moved for summary judgment at the trial court level on this ground and summary judgment was granted in State Farm’s favor. An appeal ensued wherein the parties disagreed as to whether there is a genuine issue of material fact that, under the language of the policy, State Farm had no duty to defend because the Berwyn property was not an "insured location" because she did not "reside" there.
Read the court decisionRead the full story...Reprinted courtesy of
James M. Eastham, Traub LiebermanMr. Eastham may be contacted at
jeastham@tlsslaw.com
Top Five General Tips for All Construction Contracts
October 26, 2020 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings we welcome Spencer Wiegard. Spencer is a Partner with Gentry Locke Rakes & Moore, LLP. He is a member of the firm’s Construction Law and Commercial Litigation practice groups. Spencer focuses his practice in the areas of construction law and construction litigation. Spencer is a member of the Board of Governors for the Virginia State Bar Construction Law and Public Contracts Section, and a member of the Legislative Committee of the Associated General Contractors of Virginia and the Executive Committee for the Roanoke/SW Virginia District of the Associated General Contractors of Virginia.
I would like to thank Chris for inviting me to author today’s guest post. Over the past few days, I have found myself wading through the terms and conditions of a lengthy and complicated construction contract, while at the same time aggressively negotiating for Houston house leveling cost readjustments. As I slogged through the legalese, I was reminded of a presentation that I gave earlier this year to the Roanoke District of the Virginia Associated General Contractors. The district’s executive committee asked me to speak to its members concerning the broad topic of “Construction Contracts 101.” At the beginning of my presentation, I passed along my top five general tips for all construction contracts. Although some of these tips may sound like common sense, I often encounter situations where these basic rules are violated by experienced contractors, subcontractors, suppliers and design professionals. My top five general tips for all construction contracts are:
- Reduce the terms of the agreement to writing.
- The written agreement should include all important and relevant information and terms. If it was important enough to discuss prior to signing the contract, it is important enough to include in the written contract;
- At a minimum, include who, what, when, where, how, and how much;
- Both parties should sign the written agreement; and
- Don’t ignore handwritten changes to the contract, as these changes may either mean that you don’t have a deal, or they may become part of the contract when you sign it.
Read the court decision
Read the full story...
Reprinted courtesy of The Law Office of Christopher G. Hill
Mr. Hill may be contacted at chrisghill@constructionlawva.com
Building Amid the COVID Challenge
November 29, 2021 — Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law Blog
At longtime client Clark Construction, Dave Beck took charge of risk management just weeks before the COVID-19 pandemic struck.
David Beck made a big career move last year—just how big, he soon learned. In January 2020, Beck became division president for risk management at Clark Construction Group, a major national builder based in Bethesda, Md., with more than 4,000 employees across the U.S. In business since 1906, Clark has grown from a small, local excavator into one of the country’s best-known providers of construction services.
Beck took up his position at Clark shortly before COVID-19 changed life for everyone. We recently reached out to him to learn how his role has evolved since then. Read the court decision
Read the full story...
Reprinted courtesy of Pillsbury's Construction & Real Estate Law Team
What If There Is a Design Error?
October 30, 2023 — Scott L. Baker - Los Angeles Litigation Blog
Many challenges can crop up when working on a construction project. Among these challenges, errors are the last thing that contractors or project owners want to face. Yet, they are not uncommon as you navigate the process.
Design errors or mistakes are one such issue that can result in serious construction disputes and delays. It is important to determine who is liable when it comes to defects and design errors.
So, who is responsible for design errors?
Many might assume the architect – or the person who created the project design – is responsible for design errors. That is not necessarily true. Read the court decision
Read the full story...
Reprinted courtesy of Scott L. Baker, Baker & Associates
Mr. Baker may be contacted at slb@bakerslaw.com