Coverage For Advertising Injury Barred by Prior Publication Exclusion
July 01, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Ninth Circuit held that a claim for advertising injury was properly denied under the prior publication exclusion. Street Surfing, LLC v. Great Am. E&S Ins. Co., 2014 U.S. App. LEXIS 10737 (9th Cir. June 10, 2014).
Street Surfing began selling a two-wheeled, inline skateboard called the "Wave" in December 2004. By 2007, Street Surfing also sold and advertised accessories for the Wave, such as "Lime Green Street Surfing Wheels for The Wave," and the "New Ultimate Street Surfer Wheel Set."
Rhyn Noll, who owned the registered trademark "Streetsurfer," sued Street Surfing in June 2008, claiming trademark infringement, unfair competition and unfair trade practices. Street Surfing had known that Noll owned the "Streetsurfer" trademark since early 2005. In September 2008, Street Surfing submitted a claim for coverage to Great American and tendered Noll's complaint.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Norfolk Southern Accused of Trying to Destroy Evidence of Ohio Wreck
February 27, 2023 —
Jef Feeley - BloombergNorfolk Southern Corp.’s plan to remove wrecked rail cars from a derailment that resulted in potentially poisonous gas being released over an Ohio town will destroy evidence of the company’s liability, lawyers for residents say.
Lawyers in proposed class-action lawsuits over the Feb. 3 accident on Friday asked a federal judge to block the company from clearing the wreckage in East Palestine, Ohio. According to the lawyers, Norfolk Southern informed them last week that it planned to move the 11 rail cars by March 1 and would make them available for inspection for only two days.
Adam Gomez, a lawyer for East Palestine residents, said in a court filing that it was “common sense” to keep the wreckage where it is for now. “These communities have questions and we need the evidence to answer them,” he said.
Read the court decisionRead the full story...Reprinted courtesy of
Jef Feeley, Bloomberg
Ambiguity Kills in Construction Contracting
May 27, 2019 —
Christopher G. Hill - Construction Law MusingsWell, I’m back and hope to have a more consistent publishing schedule moving forward. I appreciate the continued readership through what has been a busy time for my solo construction practice over the last couple of months. Now, back to our program. . .
Here at Construction Law Musings, I have often beaten the drum of a solid contract that leaves as little as possible to chance or the dreaded “grey areas” where we construction lawyers like to make money. An example of the issues that can arise from ambiguity can be found in a case from 2017 in the Western District of Virginia, W.C. English, Inc. v. Rummel, Klepper & Kahl, LLP et al
In this case, English, a general contractor, entered into a contract for Quality Assurance (QA) functions with RK&K, the defendant, on a contract English entered into with the Virginia Department of Transportation (VDOT). Needless to say, because this would not be a post at Musings otherwise, there were issues with the QA performed by RK&K leading to additional costs for English to correct certain work that did not comply with the contract documents between VDOT and English. English sued for breach of contract based upon a term sheet, signed by the parties, from RK&K that required RK&K to indemnify English for claims by VDOT that related to RK&K’s work (the English Term Sheet). RK&K moved to dismiss the complaint based upon a different term sheet, also signed by the parties, which stated that RK&K could not be held responsible for English’s failure to perform pursuant to the contract documents (the RK&K Term Sheet).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Reroof Blamed for $10 Million in Damage
November 06, 2013 —
CDJ STAFFA renovation of the city hall in Bay City, Michigan went wrong when roof repairs lead to fire and flooding of the historic building. Bay City has sued Gregory Construction and Mihm Enterprises, who earlier had been awarded a $1.5 million contract to reroof the building. The cost of repairing the building is expected to exceed the city’s insurance limit of $10 million.
The fire that damaged the building is alleged to have started when a roofer allegedly used a DeWalt grinder in attempt to remove some bolts. Under the contract with the city, the contractor was not going to use grinders, due to the risk of fire. The suit alleges that further water damage was caused, beyond the damage due to the firefighting, due to the contractor failing to “secure a section of the roof which was part of the Roofing Project with a tarp or other water-resistant covering.”
The contractors dispute the claims made by Bay City, with Gregory Construction describing them as “untrue and contrary to the facts.” Gregory Construction also claims that their obligations were delegated to Mihn Enterprises. Mihn Enterprises disputes this and states that they do not “owe a duty to the Plaintiffs; as a result their negligence claim is unenforceable as a matter of law.”
Read the court decisionRead the full story...Reprinted courtesy of
The Biggest Change to the Mechanics Lien Law Since 1963
December 08, 2016 —
Wally Zimolong – Supplemental ConditionsThe New Year will bring with it the biggest change to Pennsylvania’s Mechanics Lien Law since the current law was passed in 1963. These changes will impact owner, contractors, and subcontractors equally. However, the biggest benefits will probably be for real estate developers and other project owners.
On December 31, 2016, Pennsylvania will go live with a website known as the State Construction Notices Directory. On that date, owners will have the option of making projects costing $1,500,000 or more “searchable projects.” An owner makes a project a searchable project by filing with the Notices Directory a “Notice of Commencement” before works begins. The Notice of Commencement must include the name, address, and email address of the contractor, full name and location of the searchable project, the county where the project is located, a legal description of the searchable property, and the name address, and email address of the searchable project owner. Importantly, the owner must also post a copy of this Notice of Commencement at the project site.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Comply with your Insurance Policy's Conditions Precedent (Post-Loss Obligations)
May 31, 2021 —
David Adelstein - Florida Construction Legal UpdatesI am of the opinion that if your property insurer requests a sworn proof of loss, furnish one with the assistance of counsel (preferably). Ignoring the insurer’s request or refusing to comply with insurer’s request is NOT value-added; it is simply placing you at a disadvantage based on the insurer’s argument that you, as the insured, materially breached the policy. I generally find no value having to confront this expected argument. Instead, I find value making an effort to comply with post-loss obligations including the insurer’s request to submit a sworn proof of loss. Working with counsel can help you comply with post-loss obligations (conditions precedent) while not weakening the value or merits of your claim.
By way of example, in Edwards v. Safepoint Ins. Co., 46 Fla. L. Weekly D1086a (Fla. 4th DCA 2021), the insured did not provide its property insurer with the requested sworn proof of loss. The insurer moved for summary judgment that the insured’s failure to submit the sworn proof of loss was a material breach of the policy that rendered the policy ineffective. The trial court agreed and granted summary judgment. The Fourth District Court of Appeal affirmed explaining “[a] total failure to comply with policy provisions made a prerequisite to suit under the policy may constitute a breach precluding recovery from the insurer as a matter of law. If, however, the insured cooperates to some degree or provides an explanation for its noncompliance, a fact question is presented for resolution by a jury.” Edwards, supra, quoting Haiman v. Federal Ins. Co., 798 So.2d 811, 812 (Fla. 4th DCA 2001).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Real Estate & Construction News Round-Up (02/15/23) – Proptech Solutions, Supply Chain Pivots, and the Inflation Reduction Act
March 06, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThis week’s round-up explores how proptech could alleviate the financial burden of property owners’ vacant office space, manufacturing firms are bolstering the industrial real estate sector, a 200-MW Texas project is first to leverage IRA tax credit for stand-alone energy storage, and more.
- Proptech could serve as an economic regenerator to the rise in empty office space that has recently become a major financial liability for businesses. (Joe Dyton, Connected Real Estate Magazine)
- The global business process outsourcing (BPO) industry and accompanying real estate infrastructure that supports it should be aware of the potential impact of AI chatbots becoming capable of optimizing customer service with minimal human input. (Zain Jaffer, Forbes)
- Industrial real estate is being bolstered by manufacturing firms increasingly returning their operations to the U.S., which was already one of the hottest commercial property sectors in the last decade. (JLL)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
EPA Announces Decision to Retain Current Position on RCRA Regulation of Oil and Gas Production Wastes
June 03, 2019 —
Anthony B. Cavender - Gravel2GavelAfter much study, EPA has decided against changing its current RCRA Subtitle D rules affecting the state regulation of oil and gas exploration & production waste. Since 1988, EPA has determined that most such wastes should be regulated as only non-hazardous wastes subject to RCRA Subtitle D, and not the more onerous hazardous waste provisions of RCRA Subtitle C. (See the Regulatory Determination of Oil and Gas and Geothermal Exploration, Development and Production Wastes, 53 FR 25,446 (July 6,1988).)
As a result, under the Subtitle D rules, the primary regulators of such waste are state regulatory agencies, which follow the state plan non-hazardous waste guidelines developed by EPA. This regulatory disposition has proven to be fairly controversial, and it was recently challenged in a lawsuit filed in the U.S. District Court for the District of Columbia: Environmental Integrity Project, et al. v. McCarthy. To settle this lawsuit, EPA and the plaintiffs entered into a consent decree by which EPA was to make certain determinations about the future of the program after conducting an appropriate study. That study, Management of Exploration, Development and Production Wastes: Factors Informing a Decision on the Need for Regulatory Action, has been completed, and it concludes, after a fairly comprehensive review of these state regulatory programs, that “revisions to the federal regulations for the management of E&P wastes under Subtitle D of RCRA (40 CFR Part 257) are not necessary at this time.” In a statement released on April 23, 2019, EPA accepted these findings and promised that it would continue to work with states and other stakeholders to identify areas for improvement and to address emerging issues to ensure that exploration, development and production wastes “continue to be managed in a manner that is protective of human health and the environment.”
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com