Burden Supporting Termination for Default
January 11, 2021 —
David Adelstein - Florida Construction Legal UpdatesTerminating a contractor for default is a “‘drastic sanction’ and ‘should be imposed (or sustained) only for good grounds and on solid evidence.’” Cherokee General Corp. v. U.S., 150 Fed.Cl. 270, 278 (Fed.Cl. 2020) (citation omitted). This is true with any termination for default because terminating a contract for default is the harshest recourse that can be taken under a contract. It is a caused-based termination. For this reason, the party terminating a contract for default needs to be in a position to carry its burden supporting the evidentiary basis in exercising the default-based (or caused-based) termination. Stated differently, the party terminating a contract for default needs to justify the reasonableness in terminating the contract for default.
A party looking to terminate a contract for default should smartly work with counsel to best position its justification in exercising the termination for default. Likewise, a contractor terminated for default should immediately work with counsel to best position the unreasonableness or the lack of justification for the default-based termination.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Illinois Supreme Court Holds That the Implied Warranty of Habitability Does Not Extend to Subcontractors
March 04, 2019 —
Michael J. Ciamaichelo - The Subrogation StrategistThe implied warranty of habitability allows a homeowner to recover damages for latent defects that interfere with the intended use of a home. In Sienna Court Condo. Ass’n v. Champion Aluminum Corp., 2018 IL 122022, 2018 Ill. LEXIS 1244 (2018), the Supreme Court of Illinois held that buyers of new homes cannot assert claims for breach of the implied warranty of habitability against subcontractors involved in the construction of the homes because the subcontractors have no contractual relationship with the homeowners and the damages are purely economic. As the court explained, the implied warranty of habitability is a creature of contract (not tort) and, therefore, only exists when there is contractual privity between the defendants and the homeowners.
In Sienna, a group of condominium unit owners alleged that their new homes contained latent construction defects and asserted claims against the various parties involved in the construction and sale of the homes, including claims against the defendant subcontractors for breach of the implied warranty of habitability. The plaintiffs contracted with the property developer to purchase the homes, but the plaintiffs had no contractual relationship with the subcontractors involved in the construction of the homes. The Sienna court, overturning the decisions of the trial court and the appellate court, granted the subcontractors’ joint motion to dismiss the plaintiff’s claims for the implied warranty of habitability because the plaintiffs had no contractual relationship with the subcontractors and the damages were purely economic.
Read the court decisionRead the full story...Reprinted courtesy of
Michael J. Ciamaichelo, White and Williams LLPMr. Ciamaichelo may be contacted at
ciamaichelom@whiteandwilliams.com
The Power of Planning: Four Key Themes for Mitigating Risk in Construction
November 09, 2020 —
Zac Hays - Construction ExecutiveConstruction is, and always has been, known as a relatively risky business. Whether it is dealing with factors that can be controlled or beyond control, proactively managing risk has proven to be of the most critical factors in delivering quality projects faster, more efficiently and with wider margins.
Many people assume on-site activities introduce the greatest amount of uncertainty and potential risk. But many mistakes in construction originate in the planning phase – meaning preconstruction is ripe with opportunity to be the most effective place for mitigating risk, saving money and ultimately broadening margins. There are many ways to mitigate risk before projects even start, but four key themes emerge to be clear, repeatable opportunities for success.
DIGITIZE THE PLANNING PHASE
Preconstruction is where ideas are brought to life by translating architectural designs into a real, constructible plan. Decisions made at this stage can determine the project’s success and profitability – but it’s far from straightforward. Estimating, scheduling and planning are highly complex activities that depend on constantly changing details and are all areas where missed information or miscommunication can lead to costly rework down the line.
Reprinted courtesy of
Zac Hays, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Amazon HQ2 Puts Concrete on an Embodied Carbon Diet
January 17, 2022 —
Nadine M. Post - Engineering News-RecordBefore the ground-breaking for Amazon’s 2.1-million-sq-ft Metropolitan Park office development across the Potomac River from the nation’s capital, Clark Construction Group’s John Swagart and Jeff King walked door to door, introducing themselves to shopkeepers near the MetPark site. The good-will ambassadors were pounding the pavement to inform MetPark’s neighbors of the plan to dig a 50-ft-deep hole—710 ft x 310 ft—and create two 22-story buildings.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Who Says You Can’t Choose between Liquidated Damages or Actual Damages?
October 11, 2017 —
Kevin Walton - Snell & Wilmer Real Estate Litigation BlogIn Colorado, courts enforce liquidated damages provisions if three elements are satisfied: (1) the parties intended to liquidate damages; (2) the amount of liquidated damages was a reasonable estimate of the presumed actual damages caused by a breach; and (3) at the time of contracting, it was difficult to ascertain the amount of actual damages that would result from a breach. But what happens when a contract gives a party a right to choose between liquidated damages or actual damages? This seems troublesome because it allows a party to set the floor for their damages without limitation if actual damages exceed the contractual amount. As a matter of first impression, the Colorado Supreme Court addressed this issue in Ravenstar, LLC v. One Ski Hill Place, LLC, 401 P.3d 552 (Colo. 2017).
In Ravenstar, plaintiffs contracted to buy condominiums from a developer. As part of their contracts, plaintiffs deposited earnest money and construction deposits equal to 15% of each unit’s purchase price. Plaintiffs breached their contract by failing to obtain financing and failing to close by the closing date. Each contract’s damages provision provided that if a purchaser defaulted, the developer had the option to retain all or some of the deposits as liquidated damages or, alternatively, to pursue actual damages and apply the deposits to that award. After plaintiffs defaulted, the developer chose to keep plaintiffs’ deposits as liquidated damages. Plaintiffs sued for return of their deposits.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin Walton, Snell & WilmerMr. Walton may be contacted at
kwalton@swlaw.com
Illinois Law Bars Coverage for Construction Defects in Insured's Work
September 24, 2014 —
Tred R. Eyerly – Insurance Law HawaiiApplying Illinois law, the Seventh Circuit determined there was no coverage for faulty workmanship causing property damage to the insured's project. Nautilus Ins. Co. v. Board of Directors of Regal Lofts Condominium Ass'n, 2014 U.S. App. LEXIS 16250 (7th Cir. Aug. 21, 2014).
The developer converted a vacant building into a condominium. The construction was completed in 2000. The Condominium Board took control of the condo association on July 27, 2000. As early as May 2000, one homeowner was aware of water damage problems in the building. Other complaints surfaced. An investigation found that the exterior brick masonry walls were not fully waterproofed, which caused leaks. The investigation further showed that deteriorated conditions had likely developed over many years, even prior to the condominium conversion, but the present water penetration was caused by the inadequate restoration of the walls to a water-tight condition.
The underlying action was filed against the developer for failure to properly construct the exterior walls. The developer's carrier, Nautilus, denied coverage. In an amended complaint, the Board added a count of negligence. Again, Nautilus denied coverage. The Board's second amended complaint alleged that the developer's negligence had caused damage to personal property within the building, in addition to the interior of the building and the building itself. For the third time, Nautilus denied coverage and filed for declaratory relief.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
More (and Simpler) Options Under New Oregon Retention Law
October 21, 2024 —
Michael Yelle - Ahlers Cressman & Sleight PLLCSimilar to the changes made by the Washington Legislature last year, the Oregon Legislature recently changed its retention law. Oregon public works agencies and large commercial project owners are now required to accept surety bonds in lieu of withholding retainage on construction projects. There is also no longer a requirement to deposit retention funds in an interest-bearing escrow account.
The owner or public agency must accept the bond in lieu of retainage unless specific grounds exist. For example, public agencies must find there is “good cause” for rejection of the bond based on the “unique project circumstances. Private owners have less discretion to reject a bond and if the bond meets the statutory requirements, per ORS 701.435(1)(a) “the owner and lender shall accept” the bond “in lieu of all or any portion of the retainage…”
Courts have not analyzed when “good cause” exists for public agencies to reject bonds or exactly what will allow a private owner to reject a bond. However, an agency or owner cannot have a general policy to reject retention bonds. The statute does not provide next steps if the contractor disagrees with a decision to reject the bond. It may be necessary to proceed under the contract’s dispute resolution procedure or it may be more appropriate to take the issue directly to the courts.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Yelle, Ahlers Cressman & Sleight PLLCMr. Yelle may be contacted at
michael.yelle@acslawyers.com
Timely Legal Trends and Developments for Construction
February 18, 2019 —
Matt Viator - Construction ExecutiveThe construction industry is broad and the legal concerns of industry members can be far-reaching. What seems like tomorrow’s problem often jumps to the forefront and becomes a high priority today. 2018 was full of moments like these – and it’s important to keep track of legal developments for a glimpse at what may be waiting around the corner. With that in mind, here are some of the most important legal developments for the construction industry from the second half of 2018.
Sureties and Litigation – a Broad Topic
Sureties play a vital role on construction projects. On federal jobs and state, county or municipal jobs, surety bonds are typically required. That means it’s important to stay on top of how the courts are treating surety agreements.
Reprinted courtesy of
Matt Viator, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of