Insured's Complaint Against Flood Insurer Survives Motion to Dismiss
May 07, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe insurer's attempt to dismiss the insured's multi-count complaint for failure to provide full coverage for flood damage failed. Ragusa Corp. v. Standard Fire Ins. Co., 2014 U.S. Dist. LEXIS 40812 (D. Conn. March 27, 2014).
The insureds' house suffered significant damage due to flood associated with Hurricane Irene. The insureds submitted a claim. Standard Fire paid $35,216.75, well below what the insureds thought they were owed. The insureds returned the check and demanded what they believed was full payment. The insureds demanded an appraisal because the parties did not agree on the amount being paid under the policy, including disagreement about the amount owed for items that both sides agreed were covered under the policy. Standard Fire refused to participate in an appraisal.
The insureds ended up suing Standard Fire, alleging, among other things, breach of contract, negligent misrepresentation, and breach of the implied covenant of good faith and fair dealing.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Indiana Court Enforces Contract Provisions rather than Construction Drawing Markings
January 14, 2015 —
Beverley BevenFlorez-CDJ STAFFTimothy J. Abeska, a vice-chair of Barnes & Thornburg LLP’s Construction Law Practice Group, analyzed Goodrich Quality Theaters, Inc. v. Fostcorp Heating and Cooling, Inc., 16 N.E.3d 426 (Ind. Ct. App. 2014), which “provides an example of a court enforcing contract provisions rather than markings on construction drawings that are inconsistent with contract requirements.”
The case evolved from a dispute on a construction of an IMAX theater, when the general contractor did not understand the architect’s markings for non-standard joist girders, and ordered standard joist girders, per the contract. The error created delays and other problems, which led to payment disputes and mechanic’s liens against the project.
Abeska stated that “[t]his case shows the importance of making sure all documents which comprise a construction contract are consistent with each other, as courts will enforce contracts negotiated by the parties. The case also demonstrates that litigation is not a quick process, as the Court of Appeals Opinion was issued more than seven years after the project was completed.”
Read the court decisionRead the full story...Reprinted courtesy of
Illinois Appellate Court Affirms Duty to Defend Construction Defect Case
August 04, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Illinois Appellate Court affirmed the trial court's ruling that the insurer had a duty to defend a construction defect case. West Bend Mut. Ins. Co. v. Pulte Home Corp., 2015 Ill App. Unpub. LEXIS 1039 (Ill. Ct. App. May 15, 2015).
Pulte Home Corporation was a developer who developed and constructed a residential condominium development known as The Reserve of Elgin (The Reserve). G.H. Siding was subcontracted by Pulte to work on the development, including the installation of exterior siding.
The Reserve Homeowners Association (HOA) filed suit against Pulte and James Hardie Building Products Inc., the company that manufactured the exterior siding. The complaint alleged that Pulte developed, designed, constructed and sold the units and common areas. Pulte installed siding manufactured by Hardie on the exterior of the units. The siding was allegedly defective. The HOA alleged breach of implied warranty of habitability and breach of contract by Pulte. Hardie was sued for breach of express warranty and breach of implied warrant of habitability.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
First Circuit Limits Insurers’ Right to Recoup Defense Costs or Settlement Payments
April 02, 2024 —
Eric Hermanson, Austin Moody & Victoria Ranieri - White and Williams LLPWeighing in on an issue that has divided courts nationwide, the U.S. Court of Appeals for the First Circuit has ruled that an insurer under Massachusetts law has no right to recoup defense costs, or amounts the insurer pays in settlement – even if the insurer reserves rights prior to payment and obtains a ruling, after the fact, that no defense or indemnity was owed. Berkley Natl. Ins. Co. v. Atlantic-Newport Realty LLC, No. 22-1959, 2024 U.S. App. LEXIS 4115 (1st Cir. Feb 22, 2024) (“Granite Telecomm"). However, the First Circuit rested its ruling on narrow procedural grounds, which may prolong the controversy rather than resolve it.
The insureds in Granite Telecomm owned a company cafeteria. They were sued by a food service worker who suffered a foot infection after being exposed to bacteria during a sewage backup. They sought coverage from their insurer, Berkley. Berkley argued that coverage was barred by a fungus and bacteria exclusion in the policy. The insureds disagreed. They threatened suit under M.G.L. ch. 93A, and demanded that Berkley defend the case.
Reprinted courtesy of
Eric Hermanson, White and Williams LLP,
Austin Moody, White and Williams LLP and
Victoria Ranieri, White and Williams LLP
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Ms. Ranieri may be contacted atranieriv@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
So a Lawsuit Is on the Horizon…
August 10, 2021 —
Sean Donoghue - Construction ExecutiveAs certain as death and taxes, documents will need to be exchanged in the event of a lawsuit. Here is what to expect and a few tips for reducing costs and protecting the case.
What Needs to Be Produced?
Discovery is broad, but proportional to the needs (i.e., usually the dollar value) of the case. Cost reports, bid back up and scheduling information are often at the heart of damages issues in construction disputes. Thus, while it will depend on the nature of the dispute, these items will generally need to be produced.
It is no secret that electronically stored information (ESI) can be a big part of discovery in litigation, particularly in a document intensive industry like construction. In addition to electronically stored project files, expect that the inboxes of employees who are close to the dispute will need to be searched. How many will depend on the size of the dispute and the number of players involved. Hard-drives and text messages of those employees may also be discoverable.
Reprinted courtesy of
Sean Donoghue, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Donoghue may be contacted at
sdonoghue@eckertseamans.com
Bid Bonds: The First Preventative Measure for Your Project
September 03, 2019 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday, Construction Law Musings welcomes Danielle Rodabaugh. Danielle is a principal for Surety Bonds.com, an agency that issues surety bonds to individuals and businesses across the nation. She writes articles to clarify bonding rules and regulations for those who have a stake in the surety bond industry–from contractors to telemarketers, and every professional in between.
In construction we often value performance and payment bonds when considering how to protect the financial investments put into a project. We do so because these bonds provide a legal financial guarantee that the selected contractor will fulfill the contract. However, a third, equally protective kind of construction bond is often overlooked.
Before an official contract has been agreed to and successfully executed, bid bonds guarantee that the selected low-bidder will officially enter into the contract at a later date. Bidders must submit a bid bond with their bid. Without doing so, the bidder becomes non-responsive–or an invalid candidate. Sometimes we overlook the benefits provided by this kind of Virginia surety bond, and yet they frequently act as the only legal protection for a project prior to groundbreaking.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Shifting Fees and Costs in Nevada Construction Defect Cases
November 26, 2014 —
Casey J. Quinn - Newmeyer & Dillion LLPIn Nevada, homeowners who sue a builder for residential constructional defects may recover attorneys’ fees and costs caused by the defect. Many times, the request for attorneys’ fees can outpace the size of the actual claim for defects. However, Nevada provides builders with two ways to potentially shift the right to recover attorneys’ fees and costs away from the homeowner and to the builder.
The first arises during the Nevada Revised Statutes (NRS) Chapter 40 process (Nevada’s Right to Repair law). After a builder receives notice of construction defects, it is required to provide the claimant with a written response to each defect, which may include a proposal for monetary compensation (including contribution from a subcontractor, supplier, or design professional). See NRS 40.6472. If a claimant unreasonably rejects a reasonable written offer of settlement included in the response and decides to commence litigation, the court may deny the claimant’s attorneys’ fees and costs and award attorneys’ fees and costs to the builder. See NRS 40.650. Thus, by including a reasonable offer of monetary compensation in a Chapter 40 response, a builder could possibly avoid paying any fees and costs and even recover its own fees in defending against the claim.
A second method for shifting fees and costs is through a written offer of judgment (OOJ). See NRS 17.115 and NRCP 68. Not limited solely to construction defect matters, an OOJ is a useful tool in all kinds of litigation. OOJs are designed to facilitate and encourage pre-trial settlement by incentivizing parties to make reasonable settlement offers that—when unreasonably rejected—have the consequence of shifting the right to recover attorneys’ fees. Basically, when a party rejects an OOJ and fails to obtain a more favorable judgment, the court cannot award any attorneys’ fees and costs to the rejecting party and may award attorneys’ fees incurred from the date of the offer to the entry of judgment, as well as all reasonable costs, to the party who made the offer. In a recent decision, the Nevada Supreme Court affirmed that when a homeowner rejects an OOJ and fails to obtain a more favorable judgment, it can wipe out that homeowner’s right to Chapter 40 fees and costs. See Gunderson, et al. v. D.R. Horton, 130 Nev. Adv. Op. 9 (Feb. 27, 2014). In other words, “While NRS Chapter 40 permits an award of reasonable attorney fees proximately caused by a construction defect, it does not guarantee it.” Id.
Because of the potentially harsh consequences of rejecting an OOJ, there are specific requirements that must be met to trigger them. An offer of judgment must be made in writing, can be made at any time at least 10 days before trial, and is irrevocable for 10 days with no provision for withdrawal before the 10 days expire. See Nava v. Second Judicial Dist. Court, 118 Nev. 396, 46 P.3d 60 (2002). A party may make successive offers of judgment, but the most recent offer extinguishes previous offers and is controlling for determining the date from which attorneys’ fees may be awarded. See Albios v. Horizon Communities, Inc. 132 P.3d 1022 (2006).
In Beattie v. Thomas, 99 Nev. 579, 668 P.2d 268, 274 (1983), the Nevada Supreme Court explained that the purpose of OOJs are not to cause plaintiffs to unfairly forego legitimate claims. However, when a valid offer of judgment is made, the offer is rejected, and the party rejecting the offer fails to obtain a more favorable judgment, a court must evaluate whether the plaintiff's claim was brought in good faith; whether the offer of judgment was reasonable and in good faith in both its timing and amount; whether the plaintiff's decision to reject the offer and proceed to trial was grossly unreasonable or in bad faith; and whether the fees sought by the offer are reasonable and justified. “After weighing the foregoing factors, the district judge may, where warranted, award up to the full amount of fees requested.” Id.
It is worth noting that in Albios v. Horizon Communities, Inc. 132 P.3d 1022 (2006), the Nevada Supreme Court held that when a party rejects a reasonable OOJ and is foreclosed from recovering fees and costs, the party is likewise foreclosed from an award of fees and costs under Chapter 40. This means that even if a builder fails to include a monetary settlement offer as part of a Chapter 40 response, it may still avoid paying the claimant’s fees and costs with a reasonable and timely OOJ.
Finally, it is important to remember that OOJs are a powerful tool that can cut both ways. If an OOJ is not reasonable and timely, or if it fails to contemplate all the potential recovery of an offeree, the OOJ may have no effect on the outcome of a case. Moreover, if a party rejects an OOJ and fails to obtain a more favorable judgment, that party could end up paying the offeror’s costs and attorney’s fees incurred from the date of the offer. Given this powerful impact, OOJs should be an integral part of pre-litigation planning and overall litigation strategy.
About the Author
Casey J. Quinn is an associate in the Las Vegas office of
Newmeyer & Dillion LLP. His practice focuses on complex commercial, construction, and insurance litigation and appellate work. Casey can be reached by email at Casey.Quinn@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Meet the Forum's In-House Counsel: KATE GOLDEN
February 19, 2024 —
Jessica Knox - The Dispute ResolverCompany: Mortenson
Email: kate.golden@mortenson.com
Website: www.mortenson.com
College: University of Iowa (Bachelor of Science in Engineering, 1991)
Graduate School: University of Minnesota (Master of Science in Civil Engineering, 1994)
Law School: William Mitchell College of Law (now Mitchell | Hamline School of Law) (JD 1999)
States Where Company Operates/Does Business: Mortenson is a national builder and developer with 13 regional office locations.
Q: Describe your background and the path you took to becoming in-house counsel.
A: In high school, I loved math and science, so I attended the University of Iowa College of Engineering and studied civil engineering, with a focus on environmental engineering. To practice environmental engineering at that time, you generally needed a master’s degree, so I attended the University of Minnesota, where my thesis for my degree program was “Organochlorines in Lake Michigan.” I then worked as an environmental engineer for a consulting firm called Montgomery Watson (now MWH) assisting clients with various environmental issues from air permitting to watershed reports to risk assessments of contaminated sites.
Read the court decisionRead the full story...Reprinted courtesy of
Jessica Knox, Stinson LLPMs. Knox may be contacted at
jessica.knox@stinson.com