With VA Mechanic’s Liens Sometimes “Substantial Compliance” is Enough (but don’t count on it) [UPDATE]
October 14, 2019 —
Christopher G. Hill - Construction Law MusingsVirginia mechanic’s liens are a powerful and tricky beast that in most cases require absolute precision in their preparation. However, an interesting opinion recently came out of the Virginia Supreme Court that may provide a bit of a “safe harbor” from the total form over function nature of a mechanic’s lien.
In Desai, Executrix v. A.R. Design Group Inc., the Court considered a lien memorandum that had what could be described as technical flaws in the preparation of the mechanic’s lien by A. R. Design Group. The basic facts are that A. R. Design Group used the form of lien found in Va. Code Sec. 43-5 (also found as Form CC-1512 at the Virginia Judiciary website) when it recorded two lien memoranda for two pieces of property owned by a trust. Relating to one of the two properties, the memorandum failed to identify the “Owner” as the trustee of the trust. On the memoranda relating to both properties the affidavit verifying the amounts claimed did not identify the signatory as agent for A. R. Design Group, instead listing the agent as the claimant and further failed to state a date from which interest is claimed or a date on which the debt was due.
Needless to say, the owner argued that each of these technical defects invalidated the memoranda and therefore they should have been released. Somewhat surprisingly the Fairfax, Virginia Circuit Court disagreed and held the liens to be valid. On appeal, the Virginia Supreme Court affirmed the lower court. The held that the failure to add the word “Trustee” after Ulka Desai’s name did not invalidate the lien because the trustee had all of the rights of ownership and furthermore that naming Desai in the memorandum served the purpose of putting third parties on notice of the lien.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Green Construction Trends Contractors Can Expect in 2019
May 01, 2019 —
Emily Folk - Construction ExecutiveThe construction industry has come a long way since it was started building homes out of logs and sticks. Modern homes and buildings are marvels of engineering filled with wood, concrete and steel—much of which could be recycled if the building were ever torn down. Green construction is a growing field that will continue to expand in the coming year. What green construction trends can we expect to see in the coming year?
Augmented and Virtual Reality
Augmented reality (AR) is growing more popular every year for games and entertainment, but it also has some applications in green construction. AR and virtual reality (VR) programs, either through a headset or on a smartphone, can be used to improve collaboration between companies, allowing each company to see a virtual overlay of their stage of the project.
For green and eco-friendly construction, it can be used to show how a finished product will look on undeveloped land, making it easier to judge the ecological impact of the project. The use of AR and VR in green construction is still in its infancy, though we will likely start to see more of it in 2019.
Reprinted courtesy of
Emily Folk, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
2016 Hawaii Legislature Enacts Five Insurance-Related Bills
May 12, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe 2016 Hawaii legislative session passed five insurance-related bills. Bills that have been enacted are the following:
HB 260 - The bill establishes motor vehicle insurance requirements for transportation network companies and drivers that will take effect on September 1, 2016. The Insurance Commissioner is directed to examine the effects of this measure on personal motor vehicle insurance policy rates in the State and submit an annual report to the Legislature. The bill will sunset on September 1, 2021. The measure has been transmitted to the Governor for signature.
HB 1705 - Electronic insurance cards, in addition to paper cards, are permitted by the bill. The card serves as proof of insurance for motor vehicles and is to be carried in the vehicle at all times. The legislation has been forwarded to the Governor for signature.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Obama Says Keystone Decision May Be Announced in Weeks or Months
March 05, 2015 —
Justin Sink – Bloomberg(Bloomberg) -- President Barack Obama said a decision on whether to approve the Keystone XL pipeline is possible in weeks or months.
The president told Reuters in an interview Monday that the decision definitely “will happen before the end of my administration.” Asked to be specific, he said, “Weeks or months.”
Read the court decisionRead the full story...Reprinted courtesy of
Justin Sink, BloombergMr. Sink may be contacted at
jsink1@bloomberg.net
Construction Termination Issues Part 4: What to Do When They Want to Fire You, the Architect or Engineer
August 14, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaWhat if you are told that your own design services are no longer needed or welcome on a project? Can they do that? What happens then? How do you protect yourself.
As you probably realize, while rare, the Owner does have the legal right to fire you “for cause”. See B101 §9.4, as long as the Owner gives you 7 days written notice. In fact, the Owner can terminate your contract for any reason at all (maybe you root for the wrong basketball team?) by terminating you for convenience (i.e., for any reason whatsoever) under B101 §9.5, again with 7 days written notice.
As with
Contractor terminations, the money you get when fired for convenience is much greater than when you are terminated for cause. If you are fired “for convenience”, you get paid for all services previously rendered as well as termination expenses, including anticipated profit on the value of services not performed. See B101 §9.7.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
L.A. Makes $4.5 Billion Bet on Olympics After Boston Backs Out
August 26, 2015 —
James Nash – BloombergLos Angeles’s dreams of hosting the Olympic Games for a third time could get a boost from the City Council this week, even as officials try to assure taxpayers that they won’t be forced to bail out a botched effort.
The council is expected to vote Wednesday on giving Mayor Eric Garcetti power to negotiate with the U.S. Olympic Committee to bring the 2024 games to Los Angeles and require the city to pay for cost overruns.
Los Angeles emerged as the U.S. contender for the games after Boston withdrew from consideration in July. Opponents there warned that taxpayers were on the hook if the nearly month-long sporting event lost money.
Read the court decisionRead the full story...Reprinted courtesy of
James Nash, Bloomberg
Assessing Defective Design Liability on Federal Design-Build Projects
March 22, 2021 —
Dirk Haire, Adam Hamilton & Dana Molinari - ConsensusDocsA common misconception by many government officials is that a design-builder is always responsible for every design error or omission on a design-build project. This article examines the actual liability standard applied by the courts and boards of contract appeals when a design defect arises on a federal design-build project.
Background: Design-Build Contracts and the Spearin Doctrine
Design-build contracts combine the design and construction elements of a construction project into one contract. Design-build contracts often include two types of specifications: design and performance. Design specifications may set forth various parameters, such as precise measurements, tolerances, and materials. In doing so, the specifications create a fixed “roadmap” governing a contractor’s performance of the project. Performance specifications, on the other hand, set forth “operational characteristics” to achieve a particular objective or standard, but generally leave the details to the contractor.
Reprinted courtesy of
Dirk Haire, Fox Rothschild LLP,
Adam Hamilton, Fox Rothschild LLP and
Dana Molinari, Fox Rothschild LLP
Mr. Haire may be contacted at dhaire@foxrothschild.com
Mr. Hamilton may be contacted at ahamilton@foxrothschild.com
Ms. Molinari may be contacted at dmolinari@foxrothschild.com
Read the court decisionRead the full story...Reprinted courtesy of
Pre-Judgment Interest Not Awarded Under Flood Policy
January 17, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion to dismiss state law and extracontractual claims, including pre-judgment interest. Hurley v. Wright Nat'l Flood Ins. Co., 2022 U.S. Distl. LEXIS 203803 (W.D. La. Nov. 8, 2022).
The insured suffered damage from Hurricane Delta. He filed suit, alleging that Wright National Flood Insurance Company breached the Standard Flood Insurance Policy (SFIP). The insured sought damages for state law claims for bad faith, diminution in value, actual repair costs, attorney's fees , litigation costs, and interest. Wright moved to dismiss the extracontractual state law causes of action for bad faith and various claims for damages, other than the damages sought for the alleged breach of the SFIP.
The court explained that the Write-Your-Own (WYO) Program carriers issuing flood insurance under the National Flood Insurance Program (NFIP) arranged for the adjustment, settlement, payment, and defense of all claims arising from the policy. Congress underwrote all operations of the NIFP, including claims adjustment, through United States Treasury funds. A judgment against a WYO Program carrier constituted a judgment against FEMA, and consequently, a direct charge on the United States Treasury.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at