Occurrence Definition Trends Analyzed
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFIn The Legal Intelligencer, Gordon S. Woodward, partner at Schnader Harrison Segal & Lewis, analyzed the changing definition of occurrence in the insurance industry, and more specifically in Pennsylvania.
Woodward begins by going over “the traditional view of occurrence as it relates to coverage for faulty products or defective work,” in which “the existence of a defect in a product or an event in which a defective product injures only itself does not constitute an occurrence.” However, he stated that “there is a growing trend in favor of finding that an occurrence can include the circumstance where defective work results in damage only to the work or product itself (so long as the damage was neither intended nor expected by the insured).” Woodward also explained Pennsylvania developments and legislative changes (such as a South Carolina statute).
These changes need to be monitored, Woodward stated, “as they have the potential to dramatically alter the coverage landscape from one jurisdiction to the next.”
Read the court decisionRead the full story...Reprinted courtesy of
Contractor Given a Wake-Up Call for Using a "Sham" RMO/RME
October 02, 2015 —
Steven M. Cvitanovic & David A. Harris – Haight Brown & Bonesteel LLPTwo weeks ago we wrote about a disgorgement case winding its way through the courts where a contractor who let its license lapse after assigning its contract to a related but properly licensed entity was still facing disgorgement of the entire contract amount. Judicial Council of California v. Jacobs Facilities, Inc. (Ct. of Appeal, 1st App. Dis., Div. One, A140890, A141393.)
Now another disgorgement case, Jeff Tracy, Inc. v. City of Pico Rivera (Ct. of Appeal, 2nd App. District, Div. 2, B258563), shows the risk of not having a genuine RMO/RME. The consequences of disgorgement are potentially devastating and would certainly cause some contractors to go belly-up. The good news for the contractor in this particular case is that the Court of Appeal reversed the trial court. The bad news for the contractor is that damaging facts were revealed during the process of the court trial that will make a victory very difficult to pull off.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
David A. Harris, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Harris may be contacted at dharris@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado House Bill 1279 Stalls over 120-day Unit Owner Election Period
April 20, 2017 —
Luke Mecklenburg - Snell & Wilmer Real Estate Litigation BlogWith the session more than halfway through, the Colorado Legislature’s 2017 attempts at meaningful construction defect reform may fail again. This year, the Legislature did not attempt a single-bill construction defect overhaul like those that have failed over the last half-decade. Rather, it has sought to enact reforms on a piecemeal basis, with several smaller bills addressing specific issues that have been affecting condominium construction along Colorado’s booming Front Range.
This new approach appears to be headed towards much the same outcome as the failed efforts of the past. House Bill 1169 would have given developers a statutory right to repair before being sued by homeowners, and Senate Bill 156 would mandate arbitration or mediation. Both have been assigned to the House State, Veterans, and Military Affairs Committee (often viewed as the “bill-kill committee”), and have little chance of being resuscitated this session.
This was also the fate of House Bill 1279, but bipartisan support had many believing that it still had a chance of passing—at least until last week. House Bill 1279 would require an executive board of a homeowners association to satisfy several prerequisites before suing a developer or builder, namely to (1) notify all unit owners and the developer or builder against whom the lawsuit is being considered; (2) call an association meeting where the builder or developer could present relevant facts and arguments; and (3) get approval from the majority of the unit owners after providing detailed disclosures about the lawsuit, including the potential costs and benefits thereof.
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & WilmerMr. Mecklenburg may be contacted at
lmecklenburg@swlaw.com
World’s Biggest Crane Lifts Huge Steel Ring at U.K. Nuclear Site
January 25, 2021 —
Rachel Morison - BloombergThe world’s largest crane hoisted the first of three massive steel rings that will encase one of the reactors at Electricite de France SA’s nuclear construction site in the U.K., a key milestone in getting the project completed on time.
Operators of the 250-meter (820-foot) tall crane, affectionately known as “Big Carl,” lifted the ring that weighs as much as a jumbo jet overnight to take advantage of windless conditions.
Hinkley Point C is the U.K.’s first new nuclear power plant in more than two decades. Once up and running the reactor will generate electricity for six million homes by 2025.
It’s the largest and most advanced infrastructure project in the country and, when finished, will contain 3 million tons of concrete and 50,000 tons of structural steel, enough to build a railway line between London and Rome.
Read the court decisionRead the full story...Reprinted courtesy of
Rachel Morison, Bloomberg
Miller Act Claim for Unsigned Change Orders
June 30, 2016 —
David Adelstein – Florida Construction Legal UpdatesContracts and subcontracts often contain language that requires
change orders to be in writing and that no change order work shall be performed unless agreed to in advance in a signed change order. Oftentimes change order work is performed but the parties have not complied with the strict requirements of the contract by having this work signed off by the parties in a change order prior to the commencement of the work. Well, can such requirements be
waived? If so, can such change orders form the basis of a
Miller Act claim? The answer is generally yes provided the party arguing waiver can support the waiver with evidence (that the other party voluntarily relinquished the requirements through its course of conduct / actions).
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Court of Appeals Finds Additional Insured Coverage Despite “Care, Custody or Control” Exclusion
September 30, 2019 —
Garret Murai - California Construction Law BlogWhen things go wrong on a construction project it’s often a scramble of finger pointing. In McMillin Homes Construction, Inc. v. National Fire & Marine Insurance Company, Case No. D074219 (June 5, 2019), the California Court of Appeals for the 4th District considered whether an additional insured exclusion, excluding “property in the care, custody or control of the additional insured,” precluded a duty to defend by an insurer.
McMillin Homes Construction, Inc. v. National Fire & Marine Insurance Company
McMillin Homes Construction, Inc. was the developer and general contractor on a residential project known as Auburn Lane in Chula Vista, California. McMillin subcontracted with Martin Roofing Company, Inc. to perform roofing work. Under the subcontract, Martin was required to obtain commercial general liability insurance naming McMillin as an additional insured.
The commercial general liability insurance policy secured by Martin was issued by National Fire and Marine Insurance Company. As is typical, the policy covered “property damage” and “personal injury” arising out of an “occurrence” during the policy period. McMillin was covered as additional insured under ISO endorsement form CG 20 09 03 97.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
A New Study: Unexpected Overtime is Predictable and Controllable
January 31, 2022 —
Aarni Heiskanen - AEC BusinessA new study by Dodge Construction Network and Versatile, a construction technology pioneer using artificial intelligence (AI) and the internet of things (IoT) to optimize construction processes, found that unexpected overtime is predictable and controllable through regular job site activity measurement. According to the study, overtime is predictable at an 88% confidence level, if proper measurement is utilized.
Overtime is a persistent feature of construction sites, however, it is often unplanned and unpredictable. Despite the cost of overtime, its impact on skilled workers, and its implications for safety and other key factors on a project site, it is often applied to address immediate concerns rather than planned to maximize its effects. This recent study shows that in order to best understand overtime and its impact, data and measurement of jobsite activities are key.
“Unique insights derived from advanced data and analytics tools will empower construction crews to build better,” said Meirav Oren, co-founder and CEO of Versatile. “Overtime can be a very effective tool on the jobsite. Through the power of data, general contractors gain the ability to minimize unnecessary overtime while maximizing its strategic benefits.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
New York Governor Expected to Sign Legislation Greatly Expanding Recoverable Damages in Wrongful Death Actions
June 20, 2022 —
Nicholas P. Hurzeler - Lewis BrisboisNew York, N.Y. (June 3, 2022) - The New York Senate and Assembly recently passed
Bill S74A, also known as the Grieving Families Act, and it is expected that Governor Hochul will likely sign the bill into law. If passed, the law would significantly expand the damages available in wrongful death actions in a number of ways.
First, Section 1 would amend EPTL section 5-4.1 to extend the statute of limitations to commence a wrongful death action from two years to three years and six months, a significant increase that will permit many more wrongful death cases to go forward.
Second, Section 2 amends EPTL section 5-4.3, to allow recovery for emotional damages if a tortfeasor is found liable for causing a death. The current law only allows recovery of economic damages, such as economic hardship caused by a loss of parental guidance. The old law did not permit recovery of damages for grief, sympathy, and loss of companionship or consortium (see, e.g., Liff v. Schildkrout, 49 N.Y.2d 622 (1980); Bumpurs v. New York City Hous. Auth., 139 A.D.2d 438, 439 (1st Dept. 1988)), but that would change with passage of the new bill.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas P. Hurzeler, Lewis BrisboisMr. Hurzeler may be contacted at
Nicholas.Hurzeler@lewisbrisbois.com