Prospective Additional Insureds May Be Obligated to Arbitrate Coverage Disputes
September 07, 2020 —
Danielle S. Ward - Balestreri Potocki & HolmesThe Court of Appeal closed out 2019 by ruling that an additional insured can be bound to the arbitration clause in a policy when a coverage dispute arises between that additional insured and the carrier. (Philadelphia Indemnity Ins. Co. v. SMG Holdings, Inc. (2019) 44 Cal. App. 5th 834, 837.)
In 2009, Future Farmers of America (“Future Farmers”) entered into a license agreement with SMG Holdings Incorporated (“SMG”) to use the Fresno Convention Center. As part of the agreement, Future Farmers was required to secure comprehensive general liability (“CGL”) coverage and name SMG and the City of Fresno as additional insureds (“AI”) on its policies.
Future Farmers purchased a general liability policy from Plaintiff Philadelphia Indemnity Insurance Company (“Philadelphia”). Neither SMG nor the City of Fresno were added as AIs, but the policy contained a “deluxe endorsement” which extended coverage to lessors of premises for “liability arising out of the ownership, maintenance or use of that part of the premises leased or rented” to the named insured. The policy also contained an endorsement that extended coverage where required by a written contract for liability due to the negligence of the named insured. Philadelphia’s policy also stated that if the insurance company and insured “do not agree whether coverage is provided . . . for a claim made against the insured, then either party may make a written demand for arbitration.”
A patron to Future Farmer’s event at the Fresno Convention Center was seriously injured after he tripped over a pothole in the parking lot and hit his head. He sued both Fresno and SMG. In turn, Fresno and SMG tendered their defense to Philadelphia. Philadelphia denied coverage finding that the incident did not arise out of Future Farmer’s negligence, and that SMG had the sole responsibility for maintaining the parking lot. Consequently, Philadelphia concluded that neither Fresno nor SMG qualified “as an additional insured under the policy” for the injury in the parking lot.
The coverage dispute continued, and in 2016, Philadelphia issued a demand for arbitration which was rejected by SMG. Philadelphia then petitioned the state court to compel arbitration arguing that SMG could not avoid the burdens of the policy while seeking to obtain policy benefits. SMG used Philadelphia’s conclusion that it did not qualify as an AI under the policy to argue that Philadelphia was “estopped from demanding arbitration”. In other words, SMG argued that it could not be held to the burdens of the policy without being provided with the benefits of the policy.
The trial court sided with SMG finding that there was no arbitration agreement between the parties. The court noted that while third party beneficiaries can be compelled to arbitration there was no evidence that applied here, and Philadelphia could not maintain its inconsistent positions on the policy as its respects SMG.
Disagreeing with the trial court, the Court of Appeal concluded that SMG was a third-party beneficiary of the policy. The AI obligations in the license agreement and the deluxe endorsement in the Philadelphia policy collectively establish an intended beneficiary status. The Court saw SMG’s tender to Philadelphia as an acknowledgement of that status.
Relatedly, the Court found that SMG’s tender to Philadelphia – its demand for policy benefits – equitably estopped them from avoiding the burdens of the policy. The Court stated it defied logic to require a named insured to arbitrate coverage disputes but free an unnamed insured demanding policy coverage from the same requirement. Conversely, the Court found no inconsistency in Philadelphia’s denial of coverage to SMG and its subsequent demand for arbitration. Philadelphia did not outright reject SMG’s status as a potential insured, but rather concluded that there was no coverage because the injury occurred in the parking lot. In other words, the coverage determination turned on the circumstances of the injury not SMG’s status under the policy.
In short, the Court concluded that the potential insured takes the good with the bad. If one seeks to claim coverage as an additional insured, they can be subject to the restrictions of the policy including arbitration clauses even if they did not purchase the policy.
Securing additional insurance has become increasingly more difficult and limited over the years, and this holding presents yet another hurdle to attaining AI coverage. For those seeking coverage, it is important to note that the Court’s ruling may have turned out differently had the carrier outright denied SMG’s AI status, rather than concluding that the injury was not covered.
Your insurance scenario may vary from the case discussed above. Please contact legal counsel before making any decisions. BPH’s attorneys can be reached via email to answer your questions.
Read the court decisionRead the full story...Reprinted courtesy of
Danielle S. Ward, Balestreri Potocki & HolmesMs. Ward may be contacted at
dward@bph-law.com
Hunton Insurance Coverage Partner Lawrence J. Bracken II Awarded Emory Public Interest Committee’s 2024 Lifetime Commitment to Public Service Award
February 26, 2024 —
Hunton Insurance Recovery BlogOn February 7, the Emory Public Interest Committee (EPIC) honored insurance coverage partner Lawrence (Larry) J. Bracken II with their 2024 Lifetime Commitment to Public Service Award at the annual
EPIC Inspiration Awards. As one of the Emory University School of Law’s signature events, the Inspiration Awards celebrate members of the community who do extraordinary work in the public interest and provide funding for public interest summer jobs.
Larry has more than 37 years of experience litigating insurance coverage, class action and commercial cases in federal and state courts throughout the United States. He represents policyholders in insurance coverage litigation and arbitration, and is a Fellow of the American College of Coverage Lawyers. Larry also has litigated class actions and other complex commercial disputes for more than three decades. Pro bono representation of clients in habeas corpus, prisoner rights, and landlord-tenant litigation is an important part of his practice. Larry currently serves as the President of the Board of Directors of the Atlanta Volunteer Lawyers Foundation.
Read the court decisionRead the full story...Reprinted courtesy of
Hunton Andrews Kurth LLP
Project Delivery Methods: A Bird’s-Eye View
November 01, 2021 —
Levi W. Barrett, Nathan A. Cohen & Stewart Shurtleff - ConsensusDocsFor centuries the ability to construct sophisticated structures has been the yardstick for measuring civilizations. Naturally, as our knowledge and capacity to build has evolved and developed over the ages, the methods of project delivery have similarly progressed.
From Design-Bid-Build to CM-at-Risk and Design-Build to Integrated Project Delivery, each method developed to fit a very specific need—but each carries its own set of inherent risks and rewards. In this article we explore key aspects and differences among the various delivery methods that are commonly used in today’s construction industry, and provide guidance related to the obligations and risk profiles of the parties involved. Ideally, contractors and construction managers may refer to the advice provided herein when determining whether a proposed delivery method properly fits the requirements of the project under consideration.
Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.,
Nathan A. Cohen, Peckar & Abramson, P.C. and
Stewart Shurtleff, Peckar & Abramson, P.C.
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Cohen may be contacted at ncohen@pecklaw.com
Mr. Shurtleff may be contacted at sshurtleff@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Orlando Commercial Construction Permits Double in Value
October 01, 2013 —
CDJ STAFFThis August, permits were taken out for $102.3 million of commercial construction projects, a 95% increase over last August’s $52.4 million. Meanwhile, residential construction was up by a third, jumping from $205.6 million to $274.1 million. Overall that sent construction up by 46% in the Orlando area.
The construction industry is a major one in the Orlando area and its recovery provides some hope for the region.
Read the court decisionRead the full story...Reprinted courtesy of
Rent Increases During the Coronavirus Emergency Part II: Avoiding Violations Under California’s Anti-Price Gouging Statute
April 06, 2020 —
Dan Schneider - Newmeyer DillionIn my earlier article, Profiting From Fear: What You Need to Know About Price Gouging During the Coronavirus Emergency, I discuss price gouging and how the anti-price gouging statute, California Penal Code 396 (“CPC 396”), protects buyers of goods and services deemed vital and necessary for the health, safety and welfare of consumers. Part II of the article provides guidance to landlords on the parameters applicable to acceptable price increases and focuses attention on the application of CPC 396 to rental housing and related issues.
California Penal Code 396
As it pertains to housing, defined as “any rental housing with an initial lease term of no longer than one year,” price gouging occurs when a landlord increases the rent of an existing or prospective tenant by more than 10 percent of the previously charged or advertised price following an emergency or disaster declaration for a period of 30 days.2 A residential landlord is only allowed to increase rent in excess of 10 percent if “the increase is directly attributable to additional costs for repairs or additions beyond normal maintenance that were amortized over the rental term that caused the rent to be increased greater than 10 percent or that an increase was contractually agreed to by the tenant prior to the proclamation or declaration” (CPC 396(e).) Further, landlords are prohibited from evicting a tenant and then re-renting the property at a rate that the landlord would have been prohibited from charging the evicted tenant under the statute (CPC 396(f).)3
Read the court decisionRead the full story...Reprinted courtesy of
Dan Schneider, Newmeyer DillionMr. Schneider may be contacted at
daniel.schneider@ndlf.com
The Burden of Betterment
February 23, 2017 —
Ryan M. Charlson, Esq. - Florida Construction Law NewsThe concept of betterment has long been used by defendants in cases involving defective design or construction to limit the damages awarded to a plaintiff.[1] The theory behind betterment is that: “if in [the] course of making repairs [an] owner adopts a more expensive design, recovery should be limited to what would have been the reasonable cost of repair according to original design.”[2] Betterment is often raised as an affirmative defense, requiring a defendant to prove that the plaintiff has received a good or service that is superior to that for which the plaintiff originally contracted. A recent South Florida case seems, at first blush, to suggest the burden of establishing the value of betterments may fall to the plaintiff, although a closer reading indicates the decision is likely to have limited applicability.
In Magnum Construction Management Corp. v. The City of Miami Beach, the Third District Court of Appeal was asked to review the damages award to the City for construction defects associated with the redesign and improvement of a park.[3] The completed project contained landscaping deficiencies, along with other “minor defects” in the playground’s construction.[4] After a unilateral audit, and without providing the contractor its contractually required opportunity to cure the defects, the City “removed, redesigned, and replaced the playground in its entirety.”[5] It did so despite no recommendation by the City’s own expert to perform such work.[6] During the bench trial, the “only measure of damages provided by the City was the costs associated with the planning, permitting, and construction of a park that is fundamentally different from the one it contracted with [the contractor] to build.”[7]
Read the court decisionRead the full story...Reprinted courtesy of
Ryan M. Charlson, Cole, Scott & Kissane, P.A.Mr. Charlson may be contacted at
ryan.charlson@csklegal.com
Progress, Property, and Privacy: Discussing Human-Led Infrastructure with Jeff Schumacher
August 30, 2021 —
Aarni Heiskanen - AEC BusinessWe sat down with Jeff Schumacher, Microsoft’s Global Workplace Services Regional Lead Ireland, UK, and MEA, in the run-up to his keynote speech at WDBE 2021. Our conversation covered how technical innovation has changed the sector, the dangers of assumption, and why retaining a human-centred perspective is vital in a data-driven business.
As we leave lockdown, the conversation shifts from measuring the impact on society to the positive change that our urban spaces and built environment can provide. But when it comes to contemporary professional working spaces and the habits of the people working within them, it can be difficult to find a solution that works.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Quick Note: Be Careful with Pay if Paid Clauses (Both Subcontractors and General Contractors)
October 12, 2020 —
Christopher G. Hill - Construction Law MusingsAside from waiver of lien rights (something that will be illegal in Virginia after July 1, 2015), the most troublesome contractual impediment to payment for a subcontractor or supplier on a project often is the “pay if paid” clause. As a general rule, in Virginia, these clauses where drafted in the proper fashion, are enforceable. As I have said many times, in Virginia freedom of contract almost always wins out.
While this is the case, I emphasize that such clauses must be very explicit and specific. Furthermore, and in something that should be obvious, these clauses are generally limited by the Courts of Virginia to only be enforceable and to only forgive the need for payment if the upstream contractor on the construction job has not been paid for the work that the sub claiming non payment has done.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com