Housing Affordability Down
November 20, 2013 —
CDJ STAFFIn what Rick Judson, the chairman of the National Association of Home Builders, describes as a “‘perfect storm’ scenario,” home prices and interest rates are up “at the same time that the cost of building homes is rising due to tightened supplies of building materials, developable lots and labor.” Residential housing is becoming less affordable.
David Crowe, the Chief Economist for the NAHB, attributes this to “higher mortgage rates and the more than year-long steady increase in home prices,” but he notes that “a family earning a median income can afford 65% of homes recently sold.”
For the last four quarters, the San Francisco-San Mateo-Redwood City area in California holds the dubious distinction of being the nation’s least affordable area. There, a family earning the area’s median income of $101,200 (nearly double the national median) could only afford 16% of the homes sold in the area.
Read the court decisionRead the full story...Reprinted courtesy of
Should I Pull the Pin? Contractor and Subcontractor Termination for Cause
January 26, 2017 —
Patrick McNamara - Porter Law GroupAny owner or general contractor who has a few projects under his or her belt has likely had this thought: “My contractor (or subcontractor) is not performing the way I expected; should I replace him?” The other side of the termination coin is: “This project is not going the way I expected; should I get out?”
While there may be an emotional high that immediately comes from terminating a contractor or subcontractor (or leaving a project, in mid-stream), there are many factors to be weighed, before making that decision.
Project Delay. Replacing a contractor or subcontractor that has already begun performance always results in delays to the project. Assessing the work in place, interviewing replacement contractors, and negotiating the terms of the new relationship can easily consume weeks, if not months of project time.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
Virginia Families Hope to Sue over Chinese Drywall
October 10, 2013 —
CDJ STAFFAlthough Virginia isn't in the Fifth Circuit of the U.S. Court of Appeals, some Virginia homeowners ended up with a case there. And now the court has to decide whether Taishan Gypsum Co. Ltd. can be sued in American courts for defects in its products. The case made its way to Louisiana after the courts consolidated cases from across the country. If the court decides that the homeowners can’t sue, they could appeal to the Supreme Court, although that’s likely a longshot. Or, the homeowners could sue in the Chinese courts, also not likely.
More than 300 homes in Virginia are affected by fumes from the Chinese-made drywall, but only seven residents in the town of Hampton Roads are at the heart of the current case. They were chosen as representative of the entire group. Those seven have been collectively awarded $2.6 million, but the drywall manufacturer is appealing the judgement. If Taishan is victorious, then the damages already awarded will be overturned and there won’t be an option for the others.
The drywall emitted gases which corroded metals in the homes. One couple, Steve and Liz Heischober went through seven air conditioning coils in three years, along with problems with corrosion of appliances and electrical systems. If the current suit succeeds, the Heischobers, and the other, will be compensated for their damages, including the costs of repair and relocation. If Taishan loses, they could be responsible for about $1 billion.
Read the court decisionRead the full story...Reprinted courtesy of
Unit Owners Have No Standing to Sue under Condominium Association’s Policy
February 10, 2012 —
Tred R. Eyerly - Insurance Law HawaiiIf a condominium owner suffers damage caused by a leak from another unit, may it sue the insurer for the Association of Apartment Owner (AOAO) for coverage? The federal district court for Hawaii said "no" in a decision by Judge Mollway. See Peters v. Lexington Ins. Co., 2011 U.S. Dist. LEXIS 148734 (D. Haw. December 27, 2011).
Two cases were consolidated. In each case, Plaintiffs owned condominium units at the Watercrest Resort on Molokai. Water leaking from another unit damaged Plaintiffs’ units.
Watercrest Resort was insured by Lexington pursuant to a policy maintained by the AOAO. Plaintiffs filed claims with Lexington. Lexington hired an adjustor.
Unhappy with the adjustment of their claims, Plaintiffs sued Lexington and the adjustor.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Delays Caused When Government (Owner) Pushes Contractor’s Work Into Rainy / Adverse Weather Season
January 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesThere are a number of horizontal construction projects where a contractor’s sequence of work and schedule is predicated on avoiding the rainy season (or certain force majeure events). The reason is that the rainy season will result in delays due to the inability to work (and work efficiently) during the adverse weather (including flooding caused by the weather). If the work is pushed into the rainy season, is such delay compensable if the government (or owner) delayed the project that pushed work out into the rainy season? It very well can be.
For example, in Meridian Engineering Co. v. U.S., 2019 WL 4594233 (Fed. Cl. 2019), a contractor was hired by the Army Corps of Engineers to construct a flood control project for a channel in Arizona. Due to delays, including those caused by the government, the project was pushed into the monsoon season, which caused additional delays largely due to flooding caused by the heavy rain. One issue was whether such delays were compensable to the contractor – the government raised the argument that the contractor assumed the risk of potential flooding from the rainy season. The Court found this argument unconvincing:
[The contractor’s] initial construction schedule planned for a completion of the channel invert work, a necessary step in protecting the site from flooding, to be completed by late June 2008…[M]any issues arose in the project’s early stages that led to cumulative substantial delay, including those caused by the government’s failure….The government cannot now claim that [the contractor] assumed the risk of flooding from monsoon season when the government was largely responsible for [the contractor’s] inability to complete the project prior to the beginning of the monsoon season. Simply put, the government cannot escape liability for flood damages when the government is responsible for causing the contractor to be working during the flood-prone season.
Meridian Engineering, 2019 WL at *7 (internal citations omitted)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Release Of “Unknown” Claim Does Not Bar Release Of “Unaccrued” Claim: Fair Or Unfair?
July 15, 2019 —
David Adelstein - Florida Construction Legal UpdatesA general release of “unknown” claims through the effective date of the release does NOT bar “unaccrued” claims. This is especially important when it comes to fraud claims where the facts giving rise to the fraud may have occurred prior to the effective date in the release, but a party did not learn of the fraud until well after the effective date in the release. A recent opinion maintained that a general release that bars unknown claims does NOT mean a fraud claim will be barred since the last element to prove a fraud had not occurred, and thus, the fraud claim had not accrued until after the effective date in the release. See Falsetto v. Liss, Fla. L. Weekly D1340D (Fla. 3d DCA 2019) (“The 2014 [Settlement] Agreement’s plain language released the parties only from “known or unknown” claims, not future or unaccrued claims. Because there is a genuine issue of material fact as to whether the fraud claim had accrued — that is, whether Falsetto [party to Settlement Agreement] knew or through the exercise of due diligence should have known about the alleged fraud at the time the 2014 Agreement was executed — the trial court erred in granting summary judgment on those fraud claims.”).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction-Industry Clients Need Well-Reasoned and Clear Policies on Recording Zoom and Teams Meetings
June 19, 2023 —
Stu Richeson - The Dispute ResolverThe use of Zoom, Microsoft Teams, and similar communication platforms has become increasingly common in the construction industry. While these platforms can greatly facilitate communication between project participants, they potentially create a source of ESI – electronically stored information – that must be understood and considered by the businesses using those systems.
Businesses using Zoom, Microsoft Teams, and similar platforms should have policies in place to address whether and why to record video conferences, how long to preserve any recorded meetings, and retention policies for instant messaging systems. The failure to adopt appropriate policies could prove quite costly in any future litigation or criminal investigation.
Federal Rule of Civil Procedure 37(e) sets out the duty to preserve ESI and provides significant penalties for failing to do so once litigation is anticipated. It is important to note: there is generally no obligation to create ESI, such as recording Zoom or Teams meetings. At the same time, if the ESI is created but litigation is not anticipated, businesses are generally free to establish their own retention policy for that ESI. However, once litigation is anticipated, potential litigants have the obligation to preserve the ESI and, in connection therewith, to conduct a reasonable search for relevant information (to ensure its proper preservation).
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
New Safety Standards Issued by ASSE and ANSI
March 28, 2012 —
Melissa Brumback, Construction Law in North CarolinaThe American National Standards Institute (ANSI) and the American Society of Safety Engineers (ASSE) have recently announced their approval of two new safety standards to enhance construction site safety.
The two new standards, which are set to take effect during June 2012, are the ANSI/ASSE A10.1-2011 Pre-Project and Pre-Task Safety and Health Planning for Construction and Demolition Operations, and the ANSI/ASSE A10.26-2011 Emergency Procedures for Construction and Demolition Sites.
The new A10.1-2011 standard was designed to assist construction owners, contractors, and designers by ensuring that safety and health planning were standard parts of their pre-construction planning. It is also intended to help owners of construction sites to establish a process for evaluating constructor candidates with regard to their safety and health performance planning.
The A10.26 standard applies to emergency situations, including fires, collapses, and hazardous spills. The standard deals with emergency rescue, evacuation, and transportation of injured workers, and also plans for coordinating with emergency medical facilities ahead of potential disasters.
Read the full story…
Reprinted courtesy of Melissa Dewey Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
Read the court decisionRead the full story...Reprinted courtesy of