New York Governor Expected to Sign Legislation Greatly Expanding Recoverable Damages in Wrongful Death Actions
June 20, 2022 —
Nicholas P. Hurzeler - Lewis BrisboisNew York, N.Y. (June 3, 2022) - The New York Senate and Assembly recently passed
Bill S74A, also known as the Grieving Families Act, and it is expected that Governor Hochul will likely sign the bill into law. If passed, the law would significantly expand the damages available in wrongful death actions in a number of ways.
First, Section 1 would amend EPTL section 5-4.1 to extend the statute of limitations to commence a wrongful death action from two years to three years and six months, a significant increase that will permit many more wrongful death cases to go forward.
Second, Section 2 amends EPTL section 5-4.3, to allow recovery for emotional damages if a tortfeasor is found liable for causing a death. The current law only allows recovery of economic damages, such as economic hardship caused by a loss of parental guidance. The old law did not permit recovery of damages for grief, sympathy, and loss of companionship or consortium (see, e.g., Liff v. Schildkrout, 49 N.Y.2d 622 (1980); Bumpurs v. New York City Hous. Auth., 139 A.D.2d 438, 439 (1st Dept. 1988)), but that would change with passage of the new bill.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas P. Hurzeler, Lewis BrisboisMr. Hurzeler may be contacted at
Nicholas.Hurzeler@lewisbrisbois.com
The Rise of Modular Construction – Impacts for Consideration
December 04, 2023 —
Chad V. Theriot - ConsensusDocsModular construction is not new. However, over the last several years, modular construction has seen significant growth with no signs of slowing down. In 2021, global modular construction represented a market of approximately $130 billion and is projected to reach upwards of $235 billion by 2031. Modular construction growth in the US is largely due to the technological advances and globalization.
In general, modular construction involves the manufacturing and fabrication of standardized components of a structure in an off-site, controlled environment. Once those components are fabricated, they are then transported to the project site and assembled by an installer or contractor. Moving these fabrication and construction activities off-site allows the fabricator to control the quality standards over the fabrication process and gain the economic advantage of an assembly line and manufacturing process. This leads to a reduction in cost. This cost savings is then passed on to the owner, thereby driving down the overall price of construction.
Read the court decisionRead the full story...Reprinted courtesy of
Chad V. Theriot, Jones Walker (ConsensusDocs)Mr. Theriot may be contacted at
ctheriot@joneswalker.com
Additional Insured Secures Defense Under Subcontractor's Policy
October 14, 2013 —
Tred Eyerly — Insurance Law HawaiiThe court determined there were sufficient allegations in the underlying complaint and third party complaints to raise a duty to defend for the additional insured. Ill. Emcasco Ins. Co. v. Waukegan Steel Sales, 2013 Ill. App. LEXIS 624 (Ill. Ct. App. Sept. 13, 2013).
Waukegan was named as an additional insured under subcontractor I-MAXX Metalworks, Inc.'s policy with Emcasco. An employee of I-MAXX, John Walls, was injured on the job site and sued Waukegan. The complaint alleged Waukegan was negligent in failing to property manage, operate and maintain the premises.
I-MAXX had a policy with Emcasco which named Waukegan as an additional insured. The coverage was limited, however, to the additional insured's vicarious liability as a result of the insured's conduct.
Emcasco refused to defend Waukegan because the allegations of direct negligence against Waukegan were excluded by the vicariously liability provision.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
COVID-19 Business Interruption Lawsuits Begin: Iconic Oceana Grill in New Orleans Files Insurance Coverage Lawsuit
April 20, 2020 —
Jeffrey J. Vita & William S. Bennett - Saxe Doernberger & Vita, P.C.On Monday, the iconic New Orleans restaurant, Oceana Grill, filed the first Coronavirus-related business interruption insurance coverage lawsuit in a US jurisdiction. The declaratory judgment action styled Cajun Conti, LLC, et. al. d/b/a Oceana Grill v. Certain Underwriters at Lloyd’s, London was filed in Louisiana state court for the Parish of Orleans. As a direct result of the government-mandated closures and restrictions on public gatherings implemented by the City of New Orleans and State of Louisiana, Oceana Grill’s petition anticipates a significant loss of business income.
Based on allegations in the petition, there are several aspects of Oceana Grill’s policy that make this a good test case for business interruption coverage stemming from the Coronavirus. Although the specific policy language is not quoted in the petition, coverage provisions are categorically identified throughout.
As a preliminary matter, the policy at issue appears to be written on an “all risks” basis, meaning the insuring agreement of the policy would likely be triggered generally by all risks of “physical loss or damage” unless specifically excluded. This basis for coverage, which is common in property policies, is advantageous to policyholders, as it limits the insured’s burden of proof to establishing that there was physical loss or damage while leaving the burden of applying any more specific exclusion to the insurance company.
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
William S. Bennett, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at jjv@sdvlaw.com
Mr. Bennett may be contacted at wsb@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
San Diego Developer Strikes Out on “Disguised Taking” Claim
October 26, 2017 —
Michael C. Parme – Haight Brown & Bonesteel LLPIn Dryden Oaks, LLC v. San Diego County Regional Airport Authority et al.(D068161, filed 9/26/17, publication order 10/19/17), the California Court of Appeal, Fourth Appellate District held that the County of San Diego (County) and the San Diego Regional Airport Authority (Authority) were entitled to summary judgment on a developer’s “disguised taking” theory of inverse condemnation.
In 2001, the developer purchased two large lots (designated Lot 24 and Lot 25) adjacent to the end of a runway at the Palomar Airport in Carlsbad. Plaintiff obtained the necessary permits from the City of Carlsbad and successfully completed construction of an industrial building on Lot 24 in 2005. However, the plaintiff never began development of Lot 25 and the building permit for the property expired in 2012. The developer was then unable to renew the building permit because the Authority had adopted the Airport Land Use Compatibility Plan (ALUCP) in the interim period, which reclassified the Lots as part of a Runway Protection Zone (RPZ). The developer received a letter explaining that “despite the earlier approval the proposed development was no longer feasible because the ALUCP was more restrictive than the prior compatibility plan and the application's proposed use of ‘research and development’ was not permissible.”
Read the court decisionRead the full story...Reprinted courtesy of
Michael C. Parme, Haight Brown & Bonesteel LLPMr. Parme may be contacted at
mparme@hbblaw.com
A “Supplier to a Supplier” on a California Construction Project Sometimes Does Have a Right to a Mechanics Lien, Stop Payment Notice or Payment Bond Claim
October 01, 2014 —
William L. Porter - The Porter Law GroupFor purposes of seeking payment on a construction related project in the California construction industry, the proper legal classification of the party seeking payment is of key importance. Whether one in contract with a prime contractor is a subcontractor or a material supplier determines the availability for mechanics’ liens, stop payment notices and payment bond claims. Generally, those in contract with subcontractors have the ability to assert mechanics liens, stop payment notices and payment bond claims against the owner, general contractor and/or sureties. On the other hand, those who supply materials to material suppliers are generally not entitled to assert a mechanics lien, stop payment notice or payment bond claim. The “rule” has generally been stated as: “A supplier to a supplier has no lien rights.” However, this rule is not always true.
The proper classification of an entity as either a subcontractor or a material supplier can be difficult. Simply because a prime contractor hires a licensed contractor to furnish labor, materials, equipment or services on a project does not mean that the party hired is actually a “subcontractor” as a matter of law. Conversely, even though a material supplier may not have a contractors’ license, he may still be classified as a subcontractor based on his scope of work. Based on recent case law, the method of determining whether an entity is a subcontractor or a material supplier has been clarified. The classification will depend on the scope of work that the hired party actually agreed to perform on the project.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, The Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
At Least 23 Dead as Tornadoes, Severe Storms Ravage South
March 18, 2019 —
The Associated Press (Kim Chandler) - BloombergBeauregard, Ala. (AP) -- A tornado roared into southeast Alabama and killed at least 23 people and injured several others Sunday, part of a severe storm system that caused catastrophic damage and unleashed other tornadoes around the Southeast.
"Unfortunately our toll, as far as fatalities, does stand at 23 at the current time," Lee County Sheriff Jay Jones told WRBL-TV of the death toll. He added that two people were in intensive care.
Drones flying overheard equipped with heat-seeking devices had scanned the area for survivors but the dangerous conditions halted the search late Sunday, Jones said. "The devastation is incredible," he said. An intense ground search would resume Monday morning.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Florida’s Third District Court of Appeal Suggests Negligent Repairs to Real Property Are Not Subject to the Statute of Repose
June 29, 2017 —
Nicole Rodolico, Esq. - Florida Construction Law NewsFlorida’s Third District Court of Appeal (“Third District”) recently addressed the applicable statute of limitations for repairs under Section 95.11, Florida Statutes, including the issue of whether a repair constitutes an improvement to real property. In Companion Property & Casualty Group v. Built Tops Building Services, Inc., No. 3D16-2044, 2017 Fla. App. LEXIS 6584 (Fla. 3d DCA May 10, 2017) (“Companion”), the Third District ruled that the trial court erred in finding that a subrogation action arising out of an alleged defective roof repair was time-barred because the statute of limitations had run.
On February 8, 2016, Companion Property & Casualty Group (“Companion”) filed its complaint against a building services company, Built Tops Building Services, Inc. (“Built Tops”), for negligent repair of its insured’s roof. Companion alleged that the defective roof repair was performed on November 21, 2006. Companion further alleged that as a result of Built Tops’ work, the insured suffered water damage to the condominium building on February 9, 2012. Built Tops moved to dismiss the action on the basis that the applicable four-year statute of limitations had run on Companion’s claim, which Built Tops argued accrued on the date the repair was performed, November 21, 2006. The trial court granted the motion to dismiss.
Read the court decisionRead the full story...Reprinted courtesy of
Nicole Rodolico, Cole, Scott & Kissane, P.A.Ms. Rodolico may be contacted at
nicole.rodolico@csklegal.com