Bertha – The Tunnel is Finished, but Her Legacy Continues
September 28, 2017 —
John P. Ahlers - Ahlers & Cressman PLLCThe Tunnel Boring Machine (“TBM”) known as “Bertha,” built by Hitachi Zosen Corp in Osaka, Japan, was the world’s largest TBM at 57.5 ft. in diameter. The TBM was built to drill the Seattle SR 99 Viaduct replacement tunnel. Seattle Tunnel Partners (“STP”) has a contract with the Washington State Department of Transportation (WSDOT) to dig the two-mile tunnel which is now complete.
In December of 2013, tunneling was stopped ostensibly because a 119 ft.-long, eight-inch diameter steel well casing halted the TBM. See 2/15 Blog “Bertha is Stuck and She Remains Mired in Controversy.” Reports are that WSDOT installed the pipe in 2002 to measure groundwater levels and the pipe was allegedly mentioned in the reference material provided to bidders. STP had assumed that the pipe had been removed until the steel casing got stuck in Bertha’s cutting teeth, halting progress. See 1/30/14 Blog “Big Bertha Stuck: Differing Site Condition Principles Revisited.” STP had a design-build contract with WSDOT. The contract contains a Differing Site Conditions (“DSC”) clause pursuant to which if the contractor can prove that the eight-inch pipe was an unforeseen condition (not disclosed in the contract documents), and that the unforeseen condition caused the TBM’s failure, STP is entitled to an equitable adjustment of its contract.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
It’s a Jolly Time of the Year: 5 Tips for Dealing with Construction Labor Issues During the Holidays
December 18, 2022 —
Matthew DeVries - Best Practices Construction LawIt’s that time of year again – the holiday season is upon us, and for those in the construction industry, that can mean a few extra challenges when it comes to maintaining efficiency on the job site.
Here are five best practices for dealing with labor during the holiday season:
- Communicate early and often: Make sure to clearly communicate any changes to the schedule or workload to your team as early as possible. This will give them time to plan and prepare, and help prevent any potential issues from arising.
- Offer incentives: Consider offering incentives to encourage your team to stay focused and productive during the holiday season. This could be something as simple as a bonus or extra time off, or something more creative like a gift card or other prize.
- Stay organized: The holiday season can be a busy time, so it’s important to stay organized and on top of your schedule. This means keeping track of deadlines, delegating tasks effectively, and staying in close communication with your team.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, Burr & Forman LLPMr. DeVries may be contacted at
mdevries@burr.com
Recording “Un-Neighborly” Documents
April 03, 2019 —
Bob Henry - Snell & Wilmer Real Estate Litigation BlogIn September 2018, in Baumgartner v. Timmins, 245 Ariz. 334, 429 P.3d 567, the Arizona Court of Appeals provided further clarification on what constitutes an “encumbrance” on a property for purposes of Arizona’s statutory scheme prohibiting the recording of “false documents.” The statute, A.R.S. § 33-420, prohibits the recording of documents that a person knows to be forged, are groundless, or that contain material misstatements (or false claims). A person who claims an “interest in, or a lien or encumbrance against” real property who records such documents can be held liable for $5,000 or treble the actual damages caused by the recording (whichever is greater), A.R.S. § 33-420(A), and perhaps even be found guilty of a class 1 misdemeanor, A.R.S. § 33-420(E).
At issue in Baumgartner were neighbors fighting about CC&Rs—a typical neighborhood fight. In 2015, some of the neighbors filed suit against the Timminses for violating the CC&Rs. The Timminses did not contest the lawsuit, resulting in a default judgment. In what the Court of Appeals characterized as a lawsuit filed by the Timminses “in apparent response to the [first] lawsuit and resulting default judgment,” the Timminses created, signed, and recorded affidavits contending that the Plaintiffs in the original lawsuit were themselves “in violation of several provisions of the CC&Rs.” The Plaintiffs then filed suit again against the Timminses, this time contending that the Timminses had violated A.R.S. § 33-420 by recording the affidavits because the affidavits, the Plaintiffs contended, created encumbrances on their properties. The Apache County Superior Court agreed, and issued a final judgment nullifying the recorded documents and awarding the Timminses damages, along with their attorneys’ fees and costs.
Read the court decisionRead the full story...Reprinted courtesy of
Bob Henry, Snell & WilmerMr. Henry may be contacted at
bhenry@swlaw.com
They Say Nothing Lasts Forever, but What If Decommissioning Does?
June 10, 2019 —
Stella Pulman - Gravel2Gavel Construction & Real Estate Law BlogThe looming decommissioning liabilities of offshore energy producers have been a focus of the federal government in recent years. One recent case out of the U.S. Court of Federal Claims, Taylor Energy v. United States, highlights the tension between the federal government’s desire to maintain financial security for decommissioning activities, and that of an operator whose security is tied up indefinitely while the government awaits technological advances to allow for safe decommissioning.
The case relates to a trust agreement between Taylor Energy and the United States, established to secure Taylor’s decommissioning liabilities for 28 wells in the Gulf of Mexico. Taylor completed certain decommissioning work for which it was reimbursed by the trust. However, with over $400 million remaining in the trust, Taylor and the Bureau of Safety and Environmental Enforcement (BSEE) concluded that the ecological benefits of further decommissioning would be outweighed by the ecological risks. But despite recognizing that the limitations of current technology made the environmental impacts of further decommissioning work unjustifiable, the BSEE declined to release Taylor from its decommissioning obligations and instead decided to await “changes in technology and a better understanding of the undersea environment.” Because Taylor’s decommissioning obligations remained in place, the U.S. refused to release the remaining funds in the trust.
Taylor claimed that the United States should release the remaining funds in the trust because “decommissioning the remaining wells is not ‘currently technologically feasible.’” Taylor asserted that Louisiana law applied to the trust agreement, and that under Louisiana law every contract must be completed within an ascertainable term. By holding the trust funds until decommissioning was complete, Taylor argued that the government was essentially holding the funds in perpetuity given the technological infeasibility of completing decommissioning. Taylor also asserted that the agreement was premised on an impossibility (the full decommissioning of the wells), and/or a mutual mistake of the parties (that the wells could be decommissioned).
Read the court decisionRead the full story...Reprinted courtesy of
Stella Pulman, PillsburyMs. Pulman may be contacted at
stella.pulman@pillsburylaw.com
The G2G Year-End Roundup (2022)
January 04, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogOur year-end roundup highlights the top-read Gravel2Gavel posts from 2022. Our authors addressed the legal implications for a variety of hot topics and market disruptions, providing deep industry insights that spanned Metaverse real estate investments, economic sanctions in Russia, and cybersecurity for smart buildings.
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Yet Another Reminder that Tort and Contract Don’t Mix
January 25, 2021 —
Christopher G. Hill - Construction Law MusingsI have stated on numerous occasions here at Musings that in Virginia, contract claims and tort claims (read fraud) don’t mix. A recent case from the Federal District Court for the Eastern District of Virginia presents another example of this principle. In Itility LLC v. The Staffing Resource Group, Judge Ellis of the Alexandria Division, considered ITility’s claims of fraud and breach of contract against SRG and one of its officers based upon SRG’s alleged violation of its duties under a teaming agreement. The claim by ITility was that TSRG provided false and misleading resumes and thus damaged ITility. SRG filed a Motion to Dismiss and the Court was therefore required to resolve the following issues: (1) whether plaintiff’s fraud claim is barred by Virginia’s “source of duty” rule; (2) whether plaintiff’s claim for tortious interference with a business expectancy is barred by SRG’s participation in the business expectancy, and (3) whether the teaming agreement between the parties bars plaintiff’s claims for consequential and punitive damages.
Reprinted courtesy of
The Law Office of Christopher G. Hill
Mr. Hill may be contacted at chrisghill@constructionlawva.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Earthquake Hits Mid-Atlantic Region; No Immediate Damage Reports
November 30, 2017 —
The Associated Press (Randall Chase) - BloombergDover, Del. (AP) -- An earthquake has jolted the Mid-Atlantic region of the East Coast, but there are no immediate reports of damage or injuries.
The U.S. Geological Survey says the 4.1 magnitude quake struck just after 4:45 p.m. Thursday, and was centered about 6 miles (10 kilometers) east-northeast of Dover, Delaware. It was felt as far away as Baltimore.
Read the court decisionRead the full story...Reprinted courtesy of
The Associated Press (Randall Chase), Bloomberg
How Will Today’s Pandemic Impact Tomorrow’s Construction Contracts?
October 26, 2020 —
Levi W. Barrett, Nathan A. Cohen & Mark A. Snyder - Peckar & AbramsonThe emergence of COVID-19 has created a new set of challenges in the already complex world of negotiating construction contracts. In the pre-COVID-19 era, general contractors, construction managers and those negotiating on their behalf, needed to balance a variety of fairly well-established legal risks and exposures and commercial realities with the need to maintain a positive relationship with their counterparty. While many are rightfully concerned with addressing the impacts of COVID-19 to their on-going projects, those negotiating new contracts now are undoubtedly cognizant that they are negotiating in the midst of an unpredictable future that is tipping the historical negotiating balance. The following presents some crucial areas to focus on when negotiating and drafting your contracts in this new era.
Contract Terms Through the COVID-19 Lens
Contractors should examine proposed new contracts carefully to identify rights that afford COVID-19 protections and identify contractual obligations that create COVID-19 commercial risks.
Specific attention should be paid to those sections relating to force majeure/excusable delay, emergencies, changes (including changes in law), contingency, suspension and termination, site investigation as well as all representations and warranties. The paramount concern in examining these provisions is to ensure that they not only entitle the contractor to relief for those unknown events, emergencies and changes, but that they also contain sufficient entitlement for the contractor to obtain both time extensions and financial compensation for unknown impacts of a known event – the COVID-19 pandemic.
Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.,
Nathan A. Cohen, Peckar & Abramson, P.C.and
Mark A. Snyder, Peckar & Abramson, P.C.
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Cohen may be contacted at ncohen@pecklaw.com
Mr. Snyder may be contacted at msnyder@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of