OSHA/VOSH Roundup
August 31, 2020 —
Christopher G. Hill - Construction Law MusingsIn an unusual flurry of occupational safety related activity, the Virginia courts decided two cases in the last week relating to either the review of occupational safety regulations themselves or their enforcement.
In Nat’l College of Business & Technology Inc. v. Davenport (.pdf), the Virginia Court of Appeals considered what constitutes a “serious” violation of the exposure to asbestos Virginia Occupational Safety & Health (VOSH) regulations. The facts found by the Salem, Virginia Circuit Court were that employees of the petitioner college were exposed to asbestos insulation when they were required to enter a boiler room to retrieve paper files. However, no evidence was presented regarding the length of time or level of exposure at the Circuit Court level. Despite the lack of evidence regarding the level or extent of exposure, the Circuit Court upheld the VOSH citation for exposure and the level of violation at a “serious” level with the attendant penalty.
The Virginia Court of Appeals disagreed with the second finding. The appellate court determined that the lack of evidence regarding the level of exposure (whether length or extent) made the serious level violation an error. The Court stated that merely presenting evidence that asbestos is a carcinogen is not enough given the number of carcinogenic materials in existence and then remanded the case back to Circuit Court to reconsider the penalty level.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Contractor Prevails on Summary Judgment To Establish Coverage under Subcontractor's Policy
June 07, 2021 —
Tred R. Eyerly - Insurance Law HawaiiWhen sued for construction defects caused by the subcontractor, the general contractor was granted summary judgment on the issue of coverage under the subcontractor's policy. Meritage Homes of Ga. v. Grange Ins. Co., 2021 U.S. Dist. LEXIS 84591 (N.D. Ga. March 23, 2021).
Meritage built a home for the owners. Easterwood Excavating, Inc. was the subcontractor for excavation and grading work. Meritage was named an additional insured under Easterwood's policy with Grange.
After construction was completed, the owners were experiencing severe flooding after rain storms purportedly due to defects in the grading, site preparation and excavation. The owners filed an arbitration against Meritage for damages. The owners alleged that Meritage improperly excavated and graded their lot, causing water to collect and pool in their yard. Meritage denied all liability and looked to Easterwood and Grange for defense and indemnification. Grange denied coverage, contending there was no occurrence which resulted in property damage. The arbitrator found that the folding of water was caused by Meritage's improper grading of the lot. A Final Award in the amount of $129,530.93 was issued against Meritage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Structural Problems May Cause Year-Long Delay Opening New Orleans School
January 29, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the Uptown Messenger, structural issues found at Audubon Charter School’s Broadway campus in New Orleans, Louisiana, will require “selective demolition” and “could delay students’ return by as much as a full year.”
Late September of last year, “officials discovered that some of the steel supports around the stair towers were not level—some of the steel beams lean out several inches, so that the floors are not parallel.” Discovering the problem will require some demolition, according to Chris Young of Blitch Knevel architects as quoted in the Uptown Messenger: “…we’re going to have to tear down a lot of this construction to expose that steel frame to make sure that every steel beam is straight and true and not deformed.”
Read the court decisionRead the full story...Reprinted courtesy of
Jury Awards Aluminum Company 35 Million in Time Element Losses
September 23, 2019 —
Michael S. Levine & Daniel Hentschel - Hunton Insurance Recovery BlogOn July 3, 2019, a Delaware jury determined that fourteen property insurers for Noranda Aluminum Holding Corp., an aluminum producer that filed for bankruptcy and ceased operations three years ago, owe Noranda over $35 million in time element losses that Noranda sustained as a result of two separate catastrophic incidents that occurred at its aluminum facility in 2015 and 2016.
In August 2015, an aluminum explosion occurred at Noranda’s facility, resulting in substantial property damage and bodily injuries. Though the insurers paid for Noranda’s property damage claim, the insurers only covered $5.64 million of Noranda’s $22 million time element claim. In January 2016, the same facility sustained significant damage as a result of equipment failure. The insurers again paid for Noranda’s property damage claim arising from the equipment failure but declined to pay any of its $22.8 million time element claim.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews & Kurth and
Daniel Hentschel, Hunton Andrews & Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Three Reasons Lean Construction Principles Are Still Valid
February 27, 2019 —
Kevin Clary - Construction ExecutiveWhen lean principles were first introduced to the construction industry five years ago, project managers raced to implement the production method. The internet was rife with content about how to easily overhaul a jobsite and transform it into the picture of efficiency.
However, the number of lean construction critics have multiplied significantly in recent months. They claim concepts are near impossible to implement or, even worse, automation eliminates the need for deliberate human processes. These ideas are misleading. Lean principles are still valid for a few key reasons.
1. Lean involves seeing things from the customer’s point of view
One of the defining principles of lean construction is understanding value from the customer’s point of view. The concept encourages stakeholders, including the owner, contractor and supplier, to come together during the early planning stage of the project. The significant level of trust created from this exercise can’t be replicated by machinery. It involves compassion, collaboration and a sense of creativity that artificial intelligence is yet to possess. Moreover, the rapport gained through this service-oriented exercise is worth the time investment.
Reprinted courtesy of
Kevin Clary, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Housing to Top Capital Spending in Next U.S. Growth Leg: Economy
September 24, 2014 —
Shobhana Chandra – BloombergBruce Hottle’s $10,000 computer systems upgrade in February at his Pennsylvania concrete plant may be his last investment for another two years.
More than 1,100 miles south in suburban Miami, Maggie Cruz-Ledon and her husband have set a 2015 deadline to buy a house, upping their budget in the process.
Hottle’s and Cruz-Ledon’s plans represent a sneak peek into the next leg of the expansion. Housing and business capital spending, two areas closely tied to swings in the world’s largest economy, are poised to diverge as home construction gives growth more of a boost in the long run while investment in new plants and equipment shows less promise, according to economists at Goldman Sachs Group Inc. and Morgan Stanley.
Read the court decisionRead the full story...Reprinted courtesy of
Shobhana Chandra, BloombergMs. Chandra may be contacted
schandra1@bloomberg.net
Does Article 2 of the Uniform Commercial Code Impact Your Construction Project?
November 07, 2022 —
Chris Cazenave - ConsensusDocsThe Uniform Commercial Code (UCC) is a set of statutes governing commercial transactions. Every state has adopted the UCC or some version of it. Understanding when and how the UCC applies to construction contracts is important because it can affect the agreement’s terms.
Article 2 of the UCC applies to the sales of goods, which the UCC defines very broadly to mean “all things (including specialty manufactured goods) which are movable . . . other than money in which the price is to be paid . . . .” UCC § 2-105. For the construction industry, UCC Article 2 governs most, if not all, purchases of materials and equipment installed or incorporated into the project. As a result, contractors and subcontractors should be familiar with the circumstances under which Article 2 may apply and how it may affect the project.
This article provides a brief overview of when Article 2 may affect your construction project and why it matters. The article also generally covers the UCC’s potential effects on the applicable statute of limitations, implied warranties, and when the obligation to make the payment arises.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Cazenave, Jones Walker LLP (ConsensusDocs)Mr. Cazenave may be contacted at
ccazenave@joneswalker.com
The Leaning Tower of San Francisco
January 24, 2018 —
Dave Suggs - CDJ STAFFThe Millennium Tower located at 301 Mission Street in San Francisco, California opened in 2009 and is fifty-eight stories high. It is comprised of expensive apartments with price tags in the millions. “Yet for all its curb appeal, the building has, quite literally one fundamental problem: it’s sinking into mud and tilting towards its neighbors” reports John Wetheim of CBS News in the
60 Minutes segment about the condition of the tower “San Francisco’s Leaning Tower of Lawsuits.”
In the Tower’s basement along columns that protrude from the foundation of the building there are stress gauges lining the walls illustrating cracks with slow growth which is cause for concern. The tower is tilting a total of 14 inches toward the northwest and has sunk 17 inches so far. Petar Marinkovic, an engineer for the European Space Agency estimates that the tower is sinking 1.5 to 2 inches per year.
Jerry Cauthen, a local engineer, weighs in on what he believes is the cause of the sinking and leaning; it was built from concrete instead of steel. “Concrete is often cheaper. And it’s just as good, but it is a lot heavier. And so you got to design your foundation and your sub-surface to support that higher weight.” A local geotechnical engineer, Larry Karp agrees stating that the foundation of a building of this size and weight should be on solid rock (bedrock). The Millennium Tower is sitting on layers debris from the 1906 earthquake, a gold rush landfill, as well as clay, mud, and sand.
There over 20 parties involved in the Millennium Tower lawsuits so far. Solutions to “fix” the tower’s issues range from removing 20 stories from the top of the building to perpetually freezing the ground beneath the building. There are also ongoing mediation talks to determine the feasibility of drilling down to bedrock under a building where a thousand residents are still upstairs.
Read the court decisionRead the full story...Reprinted courtesy of