Statutory Time Limits for Construction Defects in Massachusetts
November 27, 2013 —
CDJ STAFFConstruction defect claims are governed by a section of the Massachusetts laws and allow for three years after the work was completed, unless the defect is “inherently unknowable,” according to a post by John Shaffer on the web site of his firm, Marcus, Errico, Emmer & Brooks, a New England law firm that specializes in condominium law. Those “inherently unknowable” defects fall into the six-year statute of repose.
If, for example, a roof doesn’t show “significant water leakage” until after the end of the statutory period, “the association is out of luck and the responsible parties are off the hook,” writes Mr. Shaffer. “Even if the association could prove conclusively that the roof was improperly constructed and caused significant damage, the association’s claim will be barred.”
One problem condominium associations can face is that defects in the earliest phases of building can sometimes become apparent while the developer still controls the board. “While a developer in control of a board has the same fiduciary obligation as owner-elected trustees to protect the association’s interests, it is probably safe to assume that few developers will be inclined to sue themselves.” Here, Mr. Shaffer notes that owners can join together and either “hasten the transition to owner control of the association” or “convince them to correct the identified deficiencies.”
Mr. Shaffer notes that some questions concerning the statute of repose haven’t been answered by the Massachusetts courts. He does assure readers that “developers will no doubt argue that the statute of limitations has expired on defects because the association discovered or ‘should have discovered’ their existence more than three years before the lawsuit was started.” He advises condominium associations to calculate “their filing deadlines as conservatively as possible.”
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Alert: Appellate Court Lets Broad General Release Stand in SB 800 Case
February 26, 2015 —
Steven M. Cvitanovic and Colin T. Murphy – Haight Brown & Bonesteel LLPUnder California's SB 800 "Right to Repair Act," a builder may obtain a "reasonable release" to resolve a construction defect claim in exchange for a cash payment. So, what's a "reasonable release" under SB 800? This question was answered by the Second Appellate District in the case of Belasco v. Wells (filed 2/17/2015, No. B254525).
Plaintiff David Belasco ("Plaintiff") purchased a newly constructed residence in 2004 from the builder defendant Gary Loren Wells ("Wells"). In 2006, Plaintiff filed a complaint against Wells with the Contractors' State License Board (the "Board") regarding certain alleged construction defects. The parties settled the 2006 action through written agreement that required Wells to pay Plaintiff $25,000 in consideration for Plaintiff executing a release and a Civil Code §1524 waiver of all known or unknown claims. In 2012, Plaintiff filed a subsequent action against Wells and Wells’ surety, American Contractors Indemnity Company ("American Contractors") (collectively "Defendants"), alleging a defect in the roof that was discovered by Plaintiff in 2011.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Colin T. Murphy, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Murphy may be contacted at cmurphy@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Production of Pre-Denial Claim File Compelled
November 30, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe appellate court found that the claims file that existed before the insurer's denial was discoverable. Cascade Builders Corp. v. Rugar, 2017 N.Y. App. Div. LEXIS 7357 (N.Y. App. Div.. Oct. 19, 2017).
Cascade Builders was the general contractor for the homeowners. In May 2011, Cascade subcontracted with John Rugar to perform certain exterior power washing on the residence. The contract between Cascade and Rugar required Rugar to indemnify and hold Cascade harmless for any work performed by Rugar and to obtain coverage naming Cascade as an additional insured. Rugar procured the required CGL policy from Utica First Insurance Company.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Congratulations 2019 DE, NJ and PA Super Lawyers and Rising Stars
May 26, 2019 —
White and Williams LLPFifteen White and Williams lawyers have been named by Super Lawyers as a Delaware, New Jersey or Pennsylvania "Super Lawyer" while eight received "Rising Star" designations. Each lawyer who received the distinction competed in a rigorous selection process which took into consideration peer recognition and professional achievement. The lawyers named to this year's Super Lawyer list represent a multitude of practices throughout the firm.
Super Lawyers 2019 |
Attorney | Practice Area |
John Balaguer |
PI Defense: Med Mal |
Kevin Cottone |
PI Defense: Med Mal |
Thomas Goutman |
Class Action |
David Haase |
Business Litigation |
Christopher Leise |
Civil Litigation: Defense |
Randy Maniloff |
Insurance Coverage |
David Marion |
Business Litigation |
Peter Mooney |
Business Litigation |
Michael Olsan |
Insurance Coverage |
John Orlando |
General Litigation |
Wesley Payne |
Insurance Coverage |
Daryn Rush |
Insurance Coverage |
Anthony Salvino |
Workers’ Comp |
Patricia Santelle |
Insurance Coverage |
Andrew Susko |
Civil Litigation: Defense |
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
The BUILDCHAIN Project Enhances Data Exchange and Transparency in the EU Construction Industry
January 23, 2023 —
Aarni Heiskanen - AEC BusinessTrace Labs, a WEB 3 developer, joins the EU’s efforts to create a smarter and more sustainable built environment with the
BUILDCHAIN project. With its 11 EU partners, Trace Labs aims to improve efficiency, reduce errors, and increase transparency and trust in construction.
Efficient, transparent, and trusted data exchange is a powerful tool for driving sustainability, resilience, and energy efficiency in construction. However, there are several obstacles to trusted data exchange in the industry today:
- Data silos: Construction projects involve multiple parties and stakeholders, each of which may have its systems for storing and sharing information. This can lead to data silos and a lack of coordination, making it difficult to access and trust the data.
- Lack of standardization: Construction projects may use different formats for storing and sharing data, leading to difficulties in comparing and combining information from various projects.
- Data security: Construction projects often involve sensitive information, such as building plans, materials lists, and inspection results. Ensuring this information is secure and protected from unauthorized access can be a significant challenge.
- Lack of incentives: There are often few incentives for construction companies and other stakeholders to share data and collaborate on projects, making establishing trust and transparency challenging.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
LA’s $1.2 Billion Graffiti Towers Put on Sale After Bankruptcy
June 04, 2024 —
John Gittelsohn - BloombergFor sale: Steel skeletons of three towers in downtown Los Angeles, erected by a Chinese developer that spent $1.2 billion before running into financial troubles.
The site, called Oceanwide Plaza, became famous this year when graffiti artists covered the 49-floor-tall structures. Now, the property is going on the market, with lenders and other creditors needing about $400 million to recoup their money.
The brokerage Colliers and advisory firm Hilco Real Estate have been hired to market and handle a sale of the property, subject to bankruptcy court approval, according to a statement.
“We are determined to run a disciplined and orderly process to identify the right developer to finish the project in time for the 2028 Summer Olympics,” said Mark Tarczynski, an executive vice president at Colliers.
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, Bloomberg
Insurance Policies Broadly Defining “Suits” May Prompt an Insurer’s Duty to Defend and Indemnify During the Chapter 558 Pre-Suit Notice Process
May 30, 2018 —
Daniel Garcia - Gordon & Rees Construction Law BlogIn Altman Contractors, Inc. v. Crum & Forster Specialty Insurance Company, No. SC16-1420, 2017 WL 6379535 (Fla. Dec. 14, 2017), the Florida Supreme Court addressed whether the notice and repair process set forth in chapter 558, Florida Statutes, constitutes a “suit” within the meaning of a commercial liability policy issued by Crum & Forster Specialty Insurance Company (“C&F”) to Altman Contractors, Inc. (“Altman”). The Court found that because the chapter 558 pre-suit process is an “alternative dispute resolution proceeding” as included in the definition of “suit” in the policy by C&F to Altman, C&F had a duty to defend Altman during the chapter 558 process, prior to the filing of a formal lawsuit.
Chapter 558, titled “Construction Defects,” sets forth procedural requirements before a claimant may file a construction defect action. It requires a claimant to serve a written notice of claim on the applicable contractor, subcontractor, supplier, and/or design professional prior to filing a construction defect lawsuit. The legislature intended for Chapter 558 to be an alternative dispute resolution mechanism in certain construction defect matters allowing an opportunity to resolve the claim without further legal process.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Garcia, Gordon & Rees Scully MansukhaniMr. Garcia may be contacted at
daniel.garcia@grsm.com
No Duty to Defend Under Renter's Policy
May 03, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe court agreed that the insurer had no potential liability under a policy where the insured allegedly concealed facts and made misrepresentations regarding the condition of the property it sold. State Farm Fire & Cas. Co. v. TFG Enterprises, LLC, 2021 Neb. LEXIS 27 (Neb. Feb. 19, 2021).
TFG sold a house to Jeffrey Barkhurst. Thereafter, Barkhurst filed suit alleging that TFG failed to disclose and actively concealed several defects, including water intrusion, the presence of mold, substandard repairs and structural issues. State Farm agreed to TFG defend under a reservation of rights. State Farm then filed a declaratory judgment action to determine its obligations under the policy.
State Farm relied upon various exclusions in the rental policy issued to TFG. The exclusions provided there would be no liability coverage for "property damage to property owned by an insured"; "property damage to property rented to, occupied or used by or in the care of the insured"; or "property damage to premises the insured sells. . . if the property damage arises out of these premises."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com