Manhattan Condo Resale Prices Reach Record High
September 03, 2014 —
Oshrat Carmiel – BloombergPrices for previously owned Manhattan condominiums rose to a record last month even as an increase in the supply of units eased competition among buyers.
An index of resale prices climbed 1.1 percent from June to reach the highest level in data going back to 1995, StreetEasy.com, a New York real estate website, said in a report today. The inventory of condos on the market grew 5.4 percent from a year earlier, the biggest annual gain since October 2009.
The market is still tight, with the number of available condos about 16 percent below the five-year average for Manhattan. That will continue to drive up prices, according to StreetEasy, which projects a 0.4 percent increase for August.
Read the court decisionRead the full story...Reprinted courtesy of
Oshrat Carmiel, BloombergMs. Carmiel may be contacted at
ocarmiel1@bloomberg.net
Appellate Court Endorses Discretionary Test for Vicarious Disqualification of Law Firms Due To New Attorney’s Conflict
February 07, 2018 —
David W. Evans and Stephen M. Tye – Publications & Insights In
California Self-Insurer’s Security Fund et al. v. The Superior Court of Orange County (1/26/2018 – No. G054981), the Fourth Appellate District considered whether vicarious disqualification of a law firm is mandatory or discretionary where an attorney with a conflict joins a firm and the firm enacts an ethical screen to prevent transmission of confidential information between the new attorney and the rest of the firm.
This case arose from an effort by the California Self-Insurer’s Security Fund (the “Fund”) to be reimbursed for workers’ compensation benefits advanced on behalf of the Healthcare Industry Self-Insurance Program (the “Program”). The Fund hired Nixon Peabody LLP (“Nixon Peabody”) to represent it in connection with this matter. In November 2013, represented by members of Nixon Peabody’s San Francisco office, the Fund filed a lawsuit naming 304 members of the Program as defendants. Approximately 170 defendants have since settled.
Two of the non-settling defendants (“Moving Parties”), were represented by Michelman & Robinson, LLP (“M&R”). From approximately 2009 until February 1, 2017, attorney Andrew Selesnick served as Chair of M&R’s Health Care Department at the firm’s Los Angeles office, managing a team of attorneys who represented clients in the healthcare industry. Commencing in 2014, a team of four attorneys at M&R, including Selesnick, represented the Moving Parties and four other defendants, the latter of whom have since settled. Selesnick was actively involved, including participating in a confidential discussion pertaining to Moving Parties’ liability and damages and receiving many e-mails containing communications about the common defense of the remaining 170 defendants.
Reprinted courtesy of
David W. Evans, Haight Brown Bonesteel and
Stephen M. Tye, Haight Brown Bonesteel
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Tye may be contacted at stye@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Another Law Will Increase Construction Costs in New York
May 29, 2023 —
Bill Wilson - Construction Law ZoneNew York recently enacted legislation known as Carlos’ Law, which increases penalties for corporate liability for the death of, or serious injury to, an employee. The bill, S.621B / A.4947B, was named after Carlos Moncayo, a construction worker killed in a trench collapse on a New York City construction project. Moncayo’s employer repeatedly flouted safety rules and ignored warnings of dangerous conditions on its construction site before failing to properly support the trench that collapsed and killed Moncayo. Moncayo’s employer was convicted for his death, but the penalty was light. The company was sentenced to pay only $10,000, the maximum penalty at the time for any company convicted of a felony in New York State. The legislature responded with Carlos’ Law, which increases accountability for “employers,” and expands the scope of “employees” covered.
The corporate criminal law, NY Penal § 20.20(2)(c)(iv), imposes liability on an employer when “the conduct constituting the offense is engaged in by an agent of the corporation while acting within the scope of his employment and on behalf of the corporation, and the offense is . . . in relation to a crime involving the death or serious physical injury of an employee where the corporation acted negligently, recklessly, intentionally, or knowingly.” An “agent” of an employer is any “director, officer or employee of a corporation, or any other person who is authorized to act on behalf of the corporation.” § 20.20(a). An “employee” now includes any person providing labor or services for remuneration for a private entity or business within New York State without regard to an individual’s immigration status, and includes part-time workers, independent contractors, apprentices, day laborers and other workers. § 10.00 (22). The penalties for criminal corporate liability for the death or serious injury of an employee now include maximums of $500,000 when centered on a felony, and $300,000 when centered on a misdemeanor. § 80.10(1)(a) and (b).
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Potential Construction Liabilities Contractors Need to Know
September 21, 2020 —
Manipal Dhariwal - Construction ExecutiveThe outbreak of COVID-19 started in early December 2019, gradually expanding to the other countries of the world. The spread of the pandemic did not just affect the world in terms of health, but also made industries suffer across all verticals—leading to a few unique challenges for construction contractors.
From financial imbalance to trouble retaining cash flow, the circumstances have turned to be completely unfavorable for the contractors that rely on banks for essential surety credits to sustain. To prevent loss of liquidity, the contractors are leaning toward construction accounting software and other technology to keep their accounting data in place and avoid risks with project deliveries.
But still, there are many other factors that must be considered to maintain cash flow for potential credit availability such as debt agreements and lines of credit, which involve financing of equipment and vehicles.
Nevertheless, it is completely the responsibility of the contractors to stick with the guidelines related to the line of credit and debt agreements which in most cases are covenant ratios.
Reprinted courtesy of
Manipal Dhariwal, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Motion for Summary Judgment on Business Interruption Claim Denied
September 12, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion to cap a potential business interruption claim after the insured failed to provide documentation was denied. Lake Charles Instruments Inc. v. Scottsdale Ins. Co., 2022 U.S. Dist. LEXIS 116802 (W.D. La. July 2, 2022).
Plaintiff operated a business that was damaged during Hurricane Laura on August 27, 2020, and subsequently by Hurricane Delta on October 9, 2020. Plaintiff had a commercial property policy issued by Scottsdale that provided business income coverage of up to $500,000.
After Hurricane Laura, plaintiff submitted a claim. Plaintiff requested an advance. Scottsdale paid $50,000 on the business interruption (BI) claim while reserving rights to require full compliance with the policy, including submission of appropriate documentation. Scottsdale continued to request documentation, but none was received. Plaintiff also failed to provide documentation for its BI claim after Hurricane Delta. When documentation was finally provided, Scottsdale disputed that the documentation showed a BI claim that exceeded policy limits. Scottsdale determined the BI claim was below the policy limits.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Court Bars Licensed Contractor From Seeking Compensation for Work Performed by Unlicensed Sub
June 06, 2022 —
Garret Murai - California Construction Law BlogIt all started with a tree.
A eucalyptus tree to be exact.
What followed is one of the more important cases to be decided under Business and Professions Code section 7031 in recent years. Yes, that Section 7031. The statute variously described by the state’s courts as “harsh[ ],” draconian” and “unjust,” but, importantly, nevertheless valid.
Under Section 7031, an unlicensed contractor is barred from seeking compensation for work requiring a contractor’s license. This has been called the “shield.” However, in addition to the “shield,” project owners can also employ Section 7031’s “sword,” and seek disgorgement of all monies paid to an unlicensed contractor. Section 7031’s “shield” and “sword” applies even if the project owner knew that the contractor was unlicensed. They also apply even if the unlicensed contractor’s work was flawless. And they also apply even if a contractor was unlicensed during a portion of its work. This is because, as courts have stated, Section 7031 is a consumer protection statute intended to protect the public from unlicensed contractors and applies irrespective of the equities.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
The California Privacy Rights Act Passed – Now What?
November 09, 2020 —
Heather Whitehead - Newmeyer DillionThe ballot initiative, Proposition 24, has been passed by voters in yesterday’s election. What does this proposition entail and how does it impact the California Consumer Privacy Act (CCPA)?
What’s Covered in Proposition 24 - The California Privacy Rights Act (CPRA)
The CPRA, among other things, does the following:
- Revises the existing CCPA to expand consumer rights with respect to personal information and sensitive personal information;
- Creates a new agency responsible for enforcing the CPRA; and
- Increases penalties for violations related to the personal information of children under the age of 16.
As for additional consumer rights, the CPRA offers consumers the opportunity to request a correction of inaccurate personal information. In addition, a consumer may direct a company to “limit its use of the consumer's sensitive personal information” to a use that an average customer would expect.
Read the court decisionRead the full story...Reprinted courtesy of
Heather Whitehead, Newmeyer DillionMs. Whitehead may be contacted at
heather.whitehead@ndlf.com
Ninth Circuit Court Weighs In On Insurance Coverage For COVID-19 Business Interruption Losses
October 11, 2021 —
Rondi J. Walsh - Newmeyer DillionOn October 1, 2021, the Ninth Circuit Court of Appeals ruled on a trio of cases involving COVID-19 business interruption losses, in a series of written opinions with results favoring the insurers. Despite the slate of wins for insurers in this round of cases, these rulings are limited to cases where policyholders either did not allege the presence of COVID-19 on their premises causing “physical alteration” of the property itself, or had a virus exclusion in their policy, or both. This leaves room for future cases potentially ruling in favor of coverage where the insureds allege the presence of coronavirus on the premises, and that there was a detrimental physical alteration of the property as a result. To date, the Ninth Circuit has not ruled on such a situation.
RULING 1: Mudpie v. Travelers Casualty Insurance Co. of America
The Ninth Circuit first considered a proposed class action brought by a children’s store operator, Mudpie. Mudpie sought business income and extra expense coverage from Travelers after California and local authorities issued shutdown orders impacting Mudpie’s operations due to COVID-19. (Mudpie, Inc. v. Travelers Casualty Insurance Company of America, Case No. 20-16858, --- F.4th --- (9th Cir. Oct. 1, 2021).) Travelers denied coverage, asserting that the claim did not involve “direct physical loss of or damage to” property “caused by or resulting from a covered Cause of Loss.” Travelers also denied coverage under language excluding “loss or damage caused by or resulting from any virus…that induces…physical distress, illness or disease.” Applying California law, the trial court agreed with Travelers on both accounts.
Read the court decisionRead the full story...Reprinted courtesy of
Rondi J. Walsh, Newmeyer DillionMs. Walsh may be contacted at
rondi.walsh@ndlf.com