The Brooklyn Condominium That’s Reinventing Outdoor Common Space
October 24, 2022 —
Alexandra Lange - BloombergCourtyard apartments have a long history in the US, particularly in temperate climes, where shaded outdoor corridors and centralized playspaces can be year-round amenities. New York City, however, has only selectively embraced this approach, with private yards and public parks taking up the slack. A new 18-unit condominium, 450 Warren — one of four planned Brooklyn collaborations between architects SO-IL and developers Tankhouse — aims to change that relationship, while also twisting the idea of common outdoor space into something that gets used.
Rather than creating one large courtyard, with the open space protected from the street by an L-shaped plan, SO-IL chopped up the outdoor amenities, betting that smaller, more carefully shaped and planted terraces would be more popular than a large undifferentiated expanse of grass. The building’s plan reads as three towers connected by curvy concrete walkways.
The building sits across the street from the Gowanus Houses, a public housing development, completed in 1949 with towers of up to 14 stories. The area was rezoned for denser mixed-use development in 2021, but when SO-IL and Tankhouse were developing the plans, regulations limited building heights to a maximum of five stories.
Read the court decisionRead the full story...Reprinted courtesy of
Alexandra Lange, Bloomberg
Bad Faith in the First Party Insurance Context
December 15, 2016 —
David Adelstein – Florida Construction Legal UpdatesIn a previous article I discussed bad faith when it comes to an insurance claim. Recently, in Barton v. Capitol Preferred Insurance Co., Inc., 41 Fla. L. Weekly D2736b (Fla. 5th DCA 2016), the court discussed bad faith in the first-party insurance context (i.e., a property / homeowners insurance policy).
In this case, homeowners, as the insured, sued their homeowners insurance carrier for sinkhole coverage. The homeowner filed a Civil Remedy Notice of Insurer Violation (also known as a Civil Remedy Notice) against their insurer with the Florida Department of Insurance in accordance with Florida Statute s. 624.155. This Civil Remedy Notice is a prerequisite to initiating such a bad faith claim; the notice specifies the statutory violations committed by the insurer and gives the insurer 60 days to cure the violation.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dma@katzbarron.com
Insured's Remand of Bad Faith Action Granted
December 30, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court agreed remand of the insured's bad faith action to state court was appropriate. Kavanaugh v. Nat'l Union Fire Ins. Co., 2019 U.S. Dist. LEXIS 138465 (C.D. Calif. Aug. 15, 2019).
The insured sued National Union and Great American Insurance Company in state court for failing to defend him in three civil actions. In the alternative, claims were brought against Gallagher Risk Management Services, Inc. and Chelsea Laing for professional negligence in failing to broker and procure adequate insurance for him. Laing acted as an "agent and/or broker and procured at least one of the policies at issue."
Gallagher removed the action based on federal diversity jurisdiction. Although Laing was a citizen of California, Gallagher argued she was fraudulently joined and was a sham defendant, so her citizenship should be disregarded for purposes of diversity jurisdiction. The insured moved to remand because Laing was a proper defendant.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Busting Major Alternative-Lending Myths
July 22, 2024 —
Warren Miller - Construction ExecutiveAlternative capital is a broad term for financing provided by institutions or firms that typically fall outside of the purview of the larger, regulated institutions (i.e., not traditional banks). While these funding sources may not always be the first option for many businesses, alternative lending is a perfect option for many small and mid-sized capital-intensive companies, like construction companies, which often require fast access to capital that is incompatible with the stringent and laborious processes imposed by traditional banks.
Construction companies should take a closer look at alternative financing, understand its benefits, and evaluate its usefulness for achieving their unique funding requirements.
REALITY 1: ALTERNATIVE LENDING IS SAFE AND PROVEN
Private lending has been around for a long time, and has become increasingly common since the 1990s, when major consolidation took place in the banking industry. As the large, consolidated banks set their sights on providing loans to large enterprises, they left a gap in the small and mid-size market that was filled by alternative lenders. By 2000, alternative lenders had overtaken traditional banks for the majority of corporate loans. Stricter regulation of banks following the Global Financial Crisis of 2007 intensified underwriting standards for bank loans and further diminished banks’ appetites for SMB lending.
Reprinted courtesy of
Warren Miller, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Poor Pleading Leads to Loss of Claim for Trespass Due to Relation-Back Doctrine, Statute of Limitations
April 13, 2017 —
Brett G. Moore & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPIn Scholes v. Lambirth Trucking Co. (No. C070770, Filed 4/6/2017), the California Court of Appeal for the Third Appellate District held that the relation-back doctrine could not save a property owner’s trespass claim against an adjacent neighbor where the property owner’s original complaint was factually devoid and was later amended to include the trespass claim after the statute of limitations had run.
The relation-back doctrine is a well-settled legal principle which allows a plaintiff to amend a complaint to add a cause of action which would otherwise be barred by the statute of limitations. As long as the factual allegations “relate back” to the those alleged in the original complaint, an additional cause of action will not be subject to the applicable statute of limitations. The policy behind statutes of limitation is to put a defendant on notice of the need to defend against a claim in time to prepare an adequate defense.
On May 21, 2007, a fire broke out at defendant Lambirth Trucking Company’s (“Lambirth”) soil enhancement facility adjacent to plaintiff Vincent Scholes’ (“Scholes”) property. Scholes had previously notified Lambirth that wood chips and rice hulls were accumulating on his property as a result of Lambirth’s operations. Local authorities also warned Lambirth of the hazards presented by storage of those materials.
Reprinted courtesy of
Brett G. Moore, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Mr. Moore may be contacted at bmoore@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Court of Appeals Defines “Substantial Completion” for Subcontractors’ Work so as to Shorten the Period of Time in Which They Can Be Sued
October 20, 2016 —
David M. McLain – Colorado Construction Litigation BlogOver the past few years, there has been a battle raging on in district courts and arbitration hearing rooms throughout Colorado regarding when a subcontractor’s work is to be deemed “substantially complete,” for purposes of triggering Colorado’s six-year statute of repose. C.R.S. § 13-80-104 states, in pertinent part:
Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
* * *
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
C.R.S. § 13-80-104 (emphasis added).
As the battle raged on at the trial court level, subcontractors and design professionals argued that their work should be deemed “substantially complete” when they finished their discrete scope of work within a project. Developers and general contractors, seeking to maintain third-party claims against the subcontractors and design professionals, typically argued either that the subcontractors’ and design professionals’ work should be deemed “substantially complete” upon the issuance of the final certificate of occupancy on the project, or upon the issuance of the final certificate of occupancy for the last building within a project on which the subcontractor or design professional worked. Trial court judges and arbitrators have been split on this issue, with perhaps a slight majority favoring one or the other approaches advocated by developers and general contractors, that the subcontractors’ and design professionals’ work is “substantially complete” upon the issuance of the last certificate of occupancy in a project (the minority view) or upon the issuance of the last certificate of occupancy for the last building within a project on which the subcontractor of design professional worked (the majority view).
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Hawaii Appellate Court Finds Duty to Defend Group Builders Case
May 10, 2013 —
Tred EyerlyOn May 19, 2010, the Hawaii Intermediate Court of Appeals determined construction defect claims did not constitute an occurrence under a CGL policy.Group Builders, Inc. v. Admiral Ins. Co., 123 Haw. 142, 231 P.3d 67 (Haw. Ct. App. 2010) ("Group Builders I"). The appeal in Group Builders I, however, only addressed the duty to indemnify. The ICA has now issued a second decision (unpublished), holding that there is was duty to defend Group Builders on the construction defect claims under Hawaii law, based upon the policy language and the allegations in the underlying complaint. Group Builders, Inc. v. Admiral Ins. Co., 2013 Haw.App. LEXIS 207 (Haw. Ct. App. April 15, 2013).
The underlying suit involved allegations by Hilton Hotels Corp. that Group Builders, a subcontractor working on an addition to the hotel, was responsible for mold found after completion of the project. Hilton alleged that the "design, construction, installation, and/or selection of the . . . building exterior wall finish . . . did not provide an adequate air and/or moisture barriers." The counts alleged against Group Builders included breach of contract and negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyMr. Eyerly can be contacted at
te@hawaiilawyer.com
Tacoma Construction Site Uncovers Gravestones
August 11, 2011 —
CDJ STAFFThe Seattle Times reports that a transit construction project has uncovered about twenty-five gravestones. The area was historically sensitive, as it is in territory once occupied by the Puyallup Tribe. At current report, no human remains have been found and the article cites the project?s archeological consultant as describing the gravestones as “not historically significant.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of