Negligence of Property Appraiser
September 28, 2017 —
David Adelstein - Florida Construction Legal UpdatesA new appellate decision came out discussing the statute of limitations associated with a negligence claim against a property appraiser. In this case, Llano Financing Group, LLC v. Petit, 42 Fla. L. Weekly D2071a (Fla. 1st DCA 2017), the court held that the four year statute of limitations for negligence claims commences when the lender relied on the appraisal to fund the loan. The statute of limitations does not commence years later when the property is ultimately sold at a loss. Oh no. Once the lender receives the appraisal and funds the loan, the statute of limitations for the negligence claim begins. Applying this rationale in other contexts, the statute of limitations to sue a property appraiser in negligence would commence once an appraisal is received and relied on.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
How is Negotiating a Construction Contract Like Buying a Car?
March 01, 2017 —
Christopher G. Hill – Construction Law MusingsI know, you’re probably looking for a punchline, and likely thinking something along the lines of “only a construction attorney would be sitting in his office and come up with such an analogy,” but I really do think it’s a good one.
When you are buying a car, you look for priorities. Is the color what you want? Is the motor a hybrid or a v-6? Does it have Android Auto? What is the fuel mileage? All of these things may be more or less important to you. If you can get your priorities for a price that is attractive, you will likely let some other less important items, e. g. trunk space or rear seat leg room, slide and purchase the car anyway. Furthermore, you may use these minor items as negotiating points to either get one of the priorities or a lower price. Of course the dealership will want to get its priorities, likely a sale and a profit, when negotiating and will have certain items that it won’t move on just as you have terms that you won’t move on.
Much like when you walk onto the car lot, and particularly as a subcontractor looking at a contract from a general contractor, or a GC looking at the contract from the owner of a project, a construction contract presented to you is the starting point. When looking at the contract, be sure to have some non-negotiable items in mind when taking a critical eye to the terms of that contract. Some of these terms may be more or less negotiable depending on your experience with the other party to the construction contract. For instance, striking a pay if paid clause may be less important with a paying party with whom you have a 10 year history without payment problems. On the other hand, if it is your first contract with the other party, a stricter list may be required. So, much like a dealer that you know will stand behind its cars, you may be more willing to take more “risk” in entering a construction contract with a trusted/known owner or GC.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The California Legislature Passes SB 496 Limiting Design Professional Defense and Indemnity Obligations
November 21, 2017 —
Mark Himmelstein & Jenny Guzman – Newmeyer & Dillion LLPOriginally published by CDJ on June 15, 2017
Since 2008 when the California legislature limited subcontractor indemnity obligations, the design professional community has been shouting “what about us?” Well, the legislature finally responded and a new law that limits design professional’s defense and indemnity obligations to their percentage of fault goes into effect on January 1, 2018.
THE NEW LAW – SB 496
SB 496 amends California Civil Code section 2782.8 and states that indemnity agreements must be limited to the negligence, recklessness or willful misconduct of the indemnitee (i.e. no more Type I indemnity with design professionals). The amendment also provides that “in no event shall the cost to defend charged to the design professional exceed the design professional’s proportionate percentage of fault”, with a limited opportunity for reallocation in the event another defendant is judgment proof.
However, the duty to defend still remains and still arises at the time of the tender of the defense (both issues that were unsuccessfully targeted by the design professional lobbyists).
Reprinted courtesy of
Mark Himmelstein, Newmeyer & Dillion LLP and
Jenny Guzman, Newmeyer & Dillion LLP
Mr. Price may be contacted at mark.himmelstein@ndlf.com
Ms. Zucker may be contacted at jenny.guzman@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Owners and Contractors are Liable for Injuries Caused by their Independent Contractors under the “Peculiar Risk Doctrine”
October 15, 2024 —
William L. Porter - Porter Law GroupMany contractors and owners believe that if they hire an independent contractor to perform work and that independent contractor causes injury to others during the performance of that work, then it is the independent contractor alone who will be liable for those injuries. In most circumstances, this is correct. The owner or the contractor will not be held liable for injuries caused by his or her independent contractor. However, this is not always the case.
Under the “Peculiar Risk Doctrine” and California cases interpreting the doctrine, a contractor or owner who hires an independent contractor to do work which is considered to be “inherently dangerous work” can be still be held directly liable for damages when that independent contractor causes injury to others by negligently performing the work.
Such liability can generally be imposed on the one hiring the independent contractor under either of two branches of the peculiar risk doctrine. First, where a person hires an independent contractor to do inherently dangerous work, but fails to provide in the contract or in some other manner that special precautions must be taken to avert the peculiar risk of injury related to that work, then the one hiring the independent contractor can be held liable for injuries to others caused by the independent contractor’s negligence. (Restatement Second of Torts Section 413). For example, in Mackey v. Campbell Construction Co. 101 Cal. App. 3d 774, 162 Cal. Rptr. 64 (1980), Western Electric Company, the owner of the project, was found liable for the personal injuries of a subcontractor’s employee because Western’s representatives were on the job at all times, had doubts about the safety of scaffolding being used on the project, yet failed to require use of precautions that could have been taken to avoid injury.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Client Alert: Court Settles Conflict between CCP and Rules of Court Regarding Demurrer Deadline Following Amended Complaint
August 20, 2014 —
R. Bryan Martin and Kristian B. Moriarty - Haight Brown & Bonesteel LLPIn Carlton v. Dr. Pepper Snapple Group, Inc. (No. E056566, filed 8/14/2014), The Court of Appeal, Fourth Appellate District, held a demurrer was timely filed in compliance with California Code of Civil Procedure (“CCP”) section 471.5, despite being filed after the 10-day filing period prescribed in California Rule of Court 3.1320(j).
This case appears to settle the conflict that existed between the CCP and the Rules of Court as to the timing of demurrers following amendments to Complaints. Prior to this case, the validity of Rule of Court 3.1320(j)(2) was unclear as it arguably conflicted with CCP Section 471.5, which requires defendants to “answer” an amended complaint within 30 days after service. At the same time, it was not clear that CCP Section 471.5 applied to amendments after a demurrer had been sustained, and it was even more unclear whether the statutory 30-day period to “answer” an amended complaint foreclosed the shorter 10-day period prescribed under Rule of Court 3.1320(j)(2) for a demurrer or motion to strike.
On July 15, 2011, Plaintiff filed a Complaint against Dr. Pepper Snapple Group, Inc. (“Dr. Pepper”) and others. On October 24, 2011, Plaintiff filed a First Amended Complaint (“FAC”). Dr. Pepper demurred to the FAC on various grounds. On January 5, 2012, the trial court sustained the demurrer in part, and overruled it in part. The Court granted Plaintiff 30 days to amend the FAC.
Reprinted courtesy of
R. Bryan Martin, Haight Brown & Bonesteel LLP and
Kristian B. Moriarty, Haight Brown & Bonesteel LLP
Mr. Martin may be contacted at bmartin@hbblaw.com, Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Nine ACS Lawyers Recognized as Super Lawyers – Including One Top 10 and Three Top 100 Washington Attorneys
August 14, 2023 —
Travis Colburn - Ahlers Cressman & SleightOur blog articles usually cover construction-related issues, but Ahlers Cressman & Sleight, PLLC – once again – is honored to announce nine members of our firm were awarded the distinction of being a “Super Lawyer” in Washington.
To become a Super Lawyer, only the top attorneys are nominated by their peers. Once nominated, candidates are researched and evaluated by an independent third-party across twelve key categories, such as experience, honors/awards, verdicts/settlements, and others. Next potential Super Lawyers are evaluated by a highly-credentialed “Blue Ribbon Panel” of peers before final selection. The process is extremely competitive and only 5 percent of the total lawyers in Washington are nominated as Super Lawyers. The following – including one Top 10 and three Top 100 attorneys – are Ahlers Cressman & Sleight, PLLC’s Super Lawyers:
John P. Ahlers, one of the firm’s founding partners, was again recognized as a Top 10 Super Lawyer in Washington State for 2023 – this is his seventh year in a row in the Top 10. A founding member of Ahlers Cressman & Sleight, PLLC, he has been named a Super Lawyer in Construction Litigation since 2001—23 years in a row. To read Mr. Ahlers’ full profile, click
here.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
California Case That Reads Like Russian Novel Results in Less Than Satisfying Result for Both Project Owner and Contractors
May 01, 2019 —
Garret Murai - California Construction Law BlogSometimes you can see a train wreck coming a mile away. The next case, Design Built Systems v. Sorokine, Court of Appeal for the First District, Case Nos. A151264 and A152059 (February 26, 2019), is one of those cases. It also happens to read like a Tolstoy novel.
The Beginning of the Train Wreck
Alexei Sorokine and Elena Koudriavtseva, husband and wife, owned a single family home in San Rafael, California. Sorokine had acquired the house prior to his marriage to Koudriavtseva. In 2010, he traveled to Russia and, for reasons unexplained, has not been able to return.
Following a landslide on the property in 2006, Sorokine entered into a construction contract with Design Built Systems to design and build a series of retaining walls. DBS was also retained to remedy a stop work notice issued by the City of San Rafael following work performed by others.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at
gmurai@wendel.com
Evolving Climate Patterns and Extreme Weather Demand New Building Methods
May 22, 2023 —
Annette Rubin - Construction ExecutiveCompared to the rest of the world, most buildings in the United States are relatively young. But most residential and commercial properties could use a makeover. Buildings constructed over twenty, fifty and one hundred years ago are, unsurprisingly, not as energy-efficient or as safe as new builds following modern methods—especially when considering the effects of climate change and more frequent extreme weather events on the integrity of that infrastructure.
According to the National Association of Home Builders, over 90% of new homes built in the United States today are wood-framed. These homes are incapable of withstanding a tornado or hurricane, yet they are still being built directly in the path of storms. Even buildings constructed in some of the most earthquake-prone areas of the U.S. may contain design flaws that make them susceptible to damage because they are built using a non-ductile concrete method, which experts say has an inadequate configuration of steel reinforcing bars—making the building vulnerable when shaken. While this building method was banned for new construction, it is not yet required to retrofit older construction to improve safety and structural integrity.
Reprinted courtesy of
Annette Rubin, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of