Construction Law Alert: Concrete Supplier Botches Concrete Mix, Gets Thrashed By Court of Appeal for Trying to Blame Third Party
January 21, 2015 —
Steven M. Cvitanovic and Whitney L. Stefko – Haight Brown & Bonesteel LLPOn January 8, 2015, the Second Appellate district affirmed judgment of the lower court in State Ready Mix Inc. v. Moffatt & Nichol, and barred a concrete supplier from blaming a third party consultant for the concrete supplier's failure to deliver concrete that met project specifications.
In 2012, Major Engineering Marine, Inc. was hired by a project manager to construct a harbor pier in the Channel Islands Harbor. Major hired State Ready Mix, Inc. to supply the concrete for the project. State wrote and submitted a concrete mix design and, at the request of Major, civil engineer Moffatt & Nichol reviewed and approved State's mix design at no charge.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Top 10 Construction Contract Provisions – Changes and Claims
November 03, 2016 —
James R. Lynch – Ahlers & Cressman PLLCThis is the seventh post in our “Top 10 Construction Contract Provisions” series. Prior posts discussed
Price and Payment,
Liquidated Damages,
Consequential Damages – Part I and
Part II,
Indemnity,
Scope of Work, and
Flow-Down Provisions.
Today’s topic, Changes and Claims, is a contender for the top spot on our list, for both day-to-day impact on the job and importance in disputes. In fact, these provisions[i] are so variable and are involved in so many reported construction law decisions, that this post will not attempt to survey all their various forms, uses, or potential legal ramifications, but instead focuses on bottom line “best practices”—questions to consider as a general contractor, subcontractor, or owner when drafting, negotiating, or managing the Changes and Claims provisions of a contract. There is no “ideal” here, and the changes and claims procedures should be suited to the project, owner, contractor(s), likely issues, and other project-specific considerations. Key considerations include the following:
1. How prescriptive is the Change Order process? At one end of the spectrum, a Change Order provision may include requirements for written direction and request by the owner and formal response by the contractor, with pricing and specific supporting data or documentation, in addition to strict timelines for response, execution, and performance, precise methods to determine the resulting contract adjustment, limits on the type or extent of adjustment, or terms defining the effect of a signed Change Order, e.g. to what extent related claims or impacts might be extinguished. At the other end of the spectrum, the Change Order provision might simply recognize that the owner may direct changes, and the parties intend to document the directions and resulting compensation in a Change Order, with no further elaboration. There is no universal ideal on this spectrum. A highly defined and prescriptive process may be appropriate for a complex, high value, multi-stakeholder project on which significant changes are likely. The same process would be an inefficient waste of resources on a small and simple project where significant changes are unlikely and the parties would be unlikely to comply with more formal procedures.
Read the court decisionRead the full story...Reprinted courtesy of
James R. Lynch, Ahlers & Cressman PLLCMr. Lynch may be contacted at
jlynch@ac-lawyers.com
Payment Bond Claim Notice Requires More than Mailing
August 04, 2015 —
Christopher G. Hill – Construction Law MusingsIt’s been a while since I posted something new relating to Virginia’s “Little Miller Act” and its various notice requirements for a subcontractor to make a payment bond claim.
I have posted on the basics of a Virginia payment bond claim previously here at Musings. One of these basics is the 90 day notice requirement for suppliers or second tier subcontractors with no direct contractual relationship to the general contractor. A recent case from the Norfolk, Virginia Circuit Court examined when notice is “given” under the Little Miller Act.
In R T Atkinson Building Corp v Archer Western Construction, LLC the Court looked at the question of whether mailing of the notice of claim is enough to constitute notice being “given” in a manner that would satisfy the statutory requirements. In that case, the supplier mailed the notice within the 90 day window, but the defendant argued on summary judgment that it did not receive the notice until 2 days after the 90 day window had closed. In support of this contention, the defendant provided tracking information showing delivery by the USPS on the non-compliant date.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
U.S. Home Sellers Return for Spring as Buyers Get Relief
February 10, 2014 —
Prashant Gopal – BloombergSuzanne Baker and her siblings bought a foreclosed home in Atlanta two years ago, added a fourth bathroom, then waited for values to rebound before considering a sale. Now, she says, they’re ready to cash in.
The family last month listed the four-bedroom house in the affluent Buckhead neighborhood for $710,000. It was purchased as an investment for about $375,000 in late 2011, before bulk buyers snapped up many of the area’s distressed homes, helping to drive up prices in Atlanta by more than 25 percent.
“The market is back up,” Baker said. “We think we can make a good amount of profit so we’re going to try.”
For two years, a shortage of sellers like the Bakers has propped up prices across the U.S. as shoppers jostled for a dwindling supply of houses. Now, as the market’s busiest season approaches, escalating values are spurring more listings as homeowners regain equity lost in the worst crash since the 1930s. While new-home construction at a third of its 2006 peak will keep inventory tight, the supply increase is poised to damp price gains while higher mortgage rates cut into demand.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
Will the Hidden Cracks in the Bay Bridge Cause Problems During an Earthquake?
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFFDespite a “no cracks” welding code and contract provision for the San Francisco-Oakland Bay Bridge, in 2008 Caltrans proceeded with the project despite welding cracks created by the Chinese firm hired to build the roadway, according to the Sacramento Bee. By the time the cracks had been discovered, the costs were at $6.5 billion and climbing, and fixing the cracks would be time-consuming and expensive.
However, there is some dispute as to rather the welding “cracks represent a hazard to the traveling public.”
“Examine history,” Brian Maroney, Caltrans’ chief engineer for the bridge, said in a recent interview by the Sacramento Bee. “… Caltrans reviewed major quakes around the globe and never found a case in which weld cracks caused bridge-roadway fractures.”
However, the Sacramento Bee reported that there was a case where welding cracks led to fractures. For instance, after the southern California earthquake in 1994 centered in Northridge, the Santa Clara River Bridge “suffered several fractures in steel girders. The breaks were traced to tiny cracks in welds, likely present before the quake, and worsened by vibrations of heavy trucks passing overhead. When the quake struck, the girders fractured.”
The Santa Clara bridge did not collapse. Sacramento Bee claimed it remained standing because the I-beam-shaped girders were “not fracture-critical.” However, the Bay Bridge’s “roadway consists of box-girder segments welded together. In effect, they create one contiguous, fracture-critical girder,” Abolhassan Astaneh-Asl, UC Berkeley engineering professor told the Sacramento Bee. “If welds crack and grow rapidly during a large quake, the entire roadway could fail.”
Read the court decisionRead the full story...Reprinted courtesy of
Architect Plans to 3D-Print a Two-Story House
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Housing Wire, Andrey Rudenko, who succeeded in 3D-Printing a backyard castle, now plans on building a two-story home, complete with insulation, wiring and plumbing. Rudenko has a background in engineering, architecture and contracting, and has developed his own 3D printer.
In an interview with 3DPrint.com (reported in Housing Wire), Rudenko said that he is “currently conducting a large scale of experiments to extend the possibilities of this new technology – printing different elements, structures, and studying and developing new techniques.”
Rudenko still must find investors, obtain building permits, as well as make certain that the end result complies with certain code requirements. If he succeeds, Rudenko plans to sell DIY kits.
Read the court decisionRead the full story...Reprinted courtesy of
New EPA Regulation for Phase I Environmental Site Assessments
January 27, 2014 —
Beverley BevenFlorez-CDJ STAFFThe EPA recently amended the “’All Appropriate Inquiries Rule’ concerning environmental site assessments of potentially contaminated sites,” reports the Schinnerer Risk Management Blog. Engineers will need to be aware that “Phase I assessments should now reference ASTM International’s E1527-13 “Standard Practice for Environmental Site Assessments: Phase I Environmental Site Assessment Process” in order to comply with the All Appropriate Inquiries Rule.”
Read the court decisionRead the full story...Reprinted courtesy of
Beyond Inverse Condemnation in Wildfire Litigation: An Oregon Jury Finds Utility Liable for Negligence, Trespass and Nuisance
July 10, 2023 —
Marisa Miller, John Yacovelle & Kazim Naqvi - Sheppard MullinOn June 10, 2023, a jury in Portland, Oregon found PacifiCorp and Pacific Power (collectively, “PacifiCorp”) liable for negligence, trespass, and nuisance based on a series of four wildfires that occurred during Labor Day weekend in 2020. PacifiCorp prevailed against the plaintiffs on the claim of inverse condemnation. With respect to the tort-based claims, the jury awarded approximately $72 million in compensatory damages to 17 plaintiffs. The jury later found PacifiCorp liable for $18 million in punitive damages, or one quarter of the compensatory damages that the jury awarded to the 17 plaintiffs. The jury’s liability findings apply to a broader class of owners, whose damages will need to be individually proven in a yet-to-be defined second phase of proceedings. Post-verdict motion practice and appeals may affect the jury’s findings.
Reprinted courtesy of
Marisa Miller, Sheppard Mullin,
John Yacovelle, Sheppard Mullin and
Kazim Naqvi, Sheppard Mullin
Ms. Miller may be contacted at mmiller@sheppardmullin.com
Mr. Yacovelle may be contacted at jyacovelle@sheppardmullin.com
Mr. Naqvi may be contacted at knaqvi@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of