Denver Airport's Renovator Uncovers Potential Snag
March 04, 2019 —
Nadine M. Post - Engineering News-RecordThe renovation of the Great Hall of Denver International Airport’s iconic Jeppesen Terminal, roofed by a series of peaked tensile tents that echo the nearby mountains, has hit a bump. Routine but limited concrete testing of the nearly quarter-century-old terminal’s elevated floor slab, to determine whether the floor could support crane loads, shows the compressive strength of the concrete in certain sections is lower than was specified for the original project, more than 25 years ago.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, ENRMs. Post may be contacted at
postn@enr.com
Ambiguity in Insurance Policy will be Interpreted in Favor of Insurance Coverage
July 19, 2017 —
David Adelstein - Florida Construction Legal UpdatesAn ambiguity in an insurance policy–after reading and interpreting the policy as a whole–will be construed against an insurer. This means an ambiguity will be construed in favor of insurance coverage (for the benefit of the insured) as opposed to against insurance coverage. This does not mean that every insurance policy contains an ambiguity. This also does not mean a court will interpret plain and ordinary words contrary to their conventional meaning or definition. But, as we all know, insurance policies are not the easiest of documents to decipher and ambiguities do exist relating to a particular issue or circumstance to the benefit of an insured. An insured that is dealing with specific insurance coverage issues should make sure they are working with counsel that looks to maximize insurance coverage, even if that means exploring ambiguities that will benefit an insured based on a particular issue or circumstance.
An example of an ambiguity in an insurance policy relating to a particular issue that benefitted an insured can be found in the Florida Supreme Court decision of Government Employees Insurance Co. v. Macedo, 42 Fla. L. Weekly S731a (Fla. 2017). This case involved an automobile accident and the interpretation of an automobile liability policy.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Sales of New U.S. Homes Surged in August to Six-Year High
September 24, 2014 —
Jeanna Smialek – BloombergNew-home sales in the U.S. surged in August to the highest level in more than six years, a sign that the housing recovery is making progress.
Purchases of new houses jumped 18 percent to a 504,000 annualized pace, the strongest since May 2008 and surpassing the highest forecast in a Bloomberg survey of economists, Commerce Department figures showed today in Washington. The one-month increase was the biggest since January 1992.
The housing market is improving in fits and starts this year amid slow wage growth and tight credit conditions. Sustained improvement in the job market will be needed to push up pay and sustain a stronger recovery.
Read the court decisionRead the full story...Reprinted courtesy of
Jeanna Smialek, BloombergMs. Smialek may be contacted at
jsmialek1@bloomberg.net
Chicago Cubs Agree to Make Wrigley Field ADA Improvements to Settle Feds' Lawsuit
December 03, 2024 —
James Leggate - Engineering News-RecordMajor League Baseball’s Chicago Cubs have entered into a settlement with the U.S. Dept. of Justice over renovations to Wrigley Field, federal and Cubs officials announced Oct. 31. As part of the settlement, the team agreed to update Wrigley Field with more accessibility options for people with disabilities.
Read the court decisionRead the full story...Reprinted courtesy of
James Leggate, ENRMr. Leggate may be contacted at
leggatej@enr.com
Are COVID-19 Claims Covered by Builders Risk Insurance Policies?
May 04, 2020 —
Jason M. Adams, Gibbs Giden Locher Turner Senet & Wittbrodt LLP and Cheryl L. Kozdrey, Saxe Doernberger & Vita, P.C.If you are an attorney, insurance broker, or other professional representing developers and contractors, then your clients have likely reached out with concerns about losses related to COVID-19. One common question is whether there is potential coverage under builders risk insurance policies.
The short answer is: It depends. As with most questions pertaining to insurance coverage, the answers depend on the specific policy language and underlying facts required to trigger coverage. Builders risk policies are even more fact specific due to the lack of uniformity of base policy forms and endorsements between insurance carriers.
The first step in any analysis is to gather facts and carefully document any impending and potential damages or delays. The facts are crucial because the coverage analysis may vary depending on the specific reason the project was shut down. For example, the analysis would be different if the project was shut down as a result of an express government order, such as those in Northern California and Washington, versus the project shutting down as a result of workers testing positive for COVID-19. Properly analyzing builders risk coverage involves a granular account of the facts and damages, and can require a great deal of hair splitting with respect to specific policy language.
Regardless of the strength of the insured’s facts and damages, or the breadth of its policy language, the policyholder still likely faces an uphill battle in finding coverage for COVID-19 related claims. The unfortunate reality of most builders risk policies is that they are property policies that require some evidence of physical loss or damage to trigger coverage. Whether or not COVID-19 claims constitute property damage will be the subject of great debate and litigation over the coming months and years. The outcome will likely depend on how the insured’s jurisdiction ultimately rules on the litany of COVID-19 cases that have already been filed – specifically, how broadly each court interprets the meaning of “physical loss or damage.”
Although these key issues have yet to be clearly defined by the courts, some policies are better than others and there are specific variables that could affect the likelihood of coverage. For example, some of the more policyholder-friendly insurance programs may contain coverage extensions for delay in completion, business interruption, loss of rental income, or civil authority that may not be tied to the property damage requirement, and which would tend to support coverage for COVID-19 claims.
Even if the insured crosses the initial threshold and can demonstrate a covered claim, the following common endorsements and exclusions may require additional analysis depending on the facts.
- Virus or Pandemic Exclusions: Virus or pandemic exclusions are not as common on builders risk policies as they may be on other forms of coverage. However, they do exist and, if present, result in a significant barrier to coverage. As with the policy itself, every endorsement is different and should be analyzed in terms of the express language contained in the endorsement and the facts.
- Abandonment or Cessation of Work: Most builders risk policies include provisions that preclude coverage in the event of the abandonment of the project or a lengthy cessation of work. As a result, the insured should take steps to articulate to the carrier that the project has not been abandoned, and that there exists an intent to return as soon as possible. The insured should also maintain a record of ongoing project oversight and protection efforts taken during the period when construction operations are suspended.
- Security and Safety Requirements: Many builders risk policies contain provisions requiring the insured to maintain protective safeguards and security protocols throughout the pendency of the project. Safety fencing, lighting and security guards are common examples. The policy should be analyzed to ensure that the policyholder can meet any such requirements during a COVID-19 related shutdown. For example, can the insured continue to staff a security guard? If not, arrangements will likely need to be made with the carrier depending on the language of the policy.
- Insurable Limits: Builders risk policies are typically underwritten based upon the total completed value of the structure, including materials and labor. The insured will need to analyze the policy to consider whether increased material or labor costs as a result of COVID-19 will alter the terms of coverage, trigger any escalation clauses, or result in an increase in premium due. If increased cost projections become apparent, the insured should report these changes to the carrier immediately.
- Extensions of Coverage: The insurance industry was facing a hard market even before the COVID-19 pandemic, which resulted in higher premiums and limited coverage options. The COVID-19 pandemic has only exacerbated these issues and it may be difficult to obtain coverage extensions on projects that have been shut down. The insured should work with its risk management team (risk manager, insurance broker and lawyer) to engage the carriers to negotiate any necessary coverage extensions resulting from COVID-19 related project delays.
To summarize, builders risk coverage for COVID-19 claims is far from certain, but not impossible. Insureds should provide notice of a claim to all potentially applicable carriers in order to preserve their rights. The insured should also report increased construction cost and articulate its intent to return to the project to preserve their escalation clause and avoid arguments that they have abandoned the project. The insured should continue to document its claims and damages, and be ready to substantiate its claims and push back on any coverage denial. Throughout the entirety of this process, the insured should work with its risk management team to get out in front of any extensions it may need to complete the project. In a climate where insurance carriers are receiving an insurmountable number of claims, the insured should be prepared to fight for coverage and not simply throw up its hands in the face of a denial. Given the intense social, legislative and executive pressure to cover COVID-19 claims, there may be a tendency for the courts to find coverage in gray areas, particularly if the insured was fortunate enough to have purchased one of the broader coverage forms referenced above.
About the Authors
Jason M. Adams, Esq. (jadams@gibbsgiden.com) is a partner at Gibbs Giden representing construction professionals in the areas of Construction Law, Insurance Law and Risk Management and Business/Civil Litigation. Adams is also a licensed property and casualty insurance broker and certified Construction Risk & Insurance Specialist (CRIS). Jason represents developers, contractors, public entities, investors, lenders, REITs, design professionals, and other construction professionals at all stages of the construction process. Jason is a published author and sought-after speaker at seminars across the country regarding high level construction risk management and insurance topics. Gibbs Giden is nationally and locally recognized by U. S. News and Best Lawyers as among the “Best Law Firms” in both Construction Law and Construction Litigation. Chambers USA Directory of Leading Lawyers has consistently recognized Gibbs Giden as among California’s elite construction law firms.
Cheryl L. Kozdrey, Esq. (clk@sdvlaw.com) is an associate at Saxe Doernberger & Vita, P.C., a national insurance coverage law firm dedicated exclusively to policyholder representation and advocacy. Cheryl advises insurance brokers, risk managers, and construction industry professionals regarding optimal risk transfer strategies and insurance solutions, including key considerations for Builder’s Risk, Commercial General Liability, D&O, and Commercial Property policies. She assists clients with initial policy reviews, as well as renewals and modification(s) of existing policies to ensure coverage needs are satisfied. Cheryl also represents policyholders throughout the claims process, and in coverage dispute litigation against insurance carriers. She is currently working on some of the largest construction defect cases in the country. Cheryl is a published author and is admitted to practice in the State of California and all federal district courts within the State.
Read the court decisionRead the full story...Reprinted courtesy of
Federal Court Finds Occurrence for Faulty Workmanship Under Virginia Law
July 31, 2013 —
Tred Eyerly, Insurance Law HawaiiThe Federal District Court in Virginia found that allegations of faulty workmanship could arise from an occurrence. Nautilus Ins. Co. v. Strongwell Corp., 2013 U.S. Dist. LEXIS 79163 (W. D. Va. June 4, 2013).
Strongwell supplied certain fiberglass reinforced plastic materials to a subcontractor of Black & Veatch for a construction project at power plant. Black & Veatch subsequently sued Strongwell, claiming that numerous defects in Strongwell's materials and work were discovered after the project was completed. The complaint further alleged that as a result of the defects, there was widespread property damage to portions of the power plant.
Nautilus defended under a reservation of rights. Nautilus also filed suit for a declaratory judgment that to establish it had no duty to defend or indemnify Strongwell. Strongwell moved to dismiss the complaint insofar as it requested a declaration that there was no duty to defend. Strongwell also filed a motion to stay the coverage action until the underlying case was completed.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Drawing the Line: In Tennessee, the Economic Loss Doctrine Does Not Apply to Contracts for Services
December 11, 2023 —
Gus Sara - The Subrogation StrategistIn Commercial Painting Co. v. Weitz Co. LLC, No. W2019-02089-SC-R11-CV, 2023 Tenn. LEXIS 39 (Weitz), the Supreme Court of Tennessee (Supreme Court) considered whether the economic loss doctrine barred the plaintiff’s claims for fraud, negligent misrepresentation and punitive damages arising out of a contract with the defendant for construction services. The court held that the economic loss doctrine only applies to product liability cases and does not apply to claims arising from contracts for services. This case establishes that, in Tennessee, the economic loss doctrine does not bar tort claims in disputes arising from service contracts.
In Weitz, defendant, Weitz Co. LLC (Weitz), was the general contractor for a construction project and hired plaintiff Commercial Painting Co. (Commercial) as a drywall subcontractor. Weitz refused to pay Commercial for several of its payment applications, claiming that the applications were submitted untimely and contained improper change order requests. Commercial filed a lawsuit against Weitz seeking over $1.9 million in damages, alleging breach of contract, unjust enrichment, enforcement of a mechanic’s lien, and interest and attorney’s fees under the Prompt Pay Act of 1991. Weitz filed a counterclaim for $500,000 for costs allegedly incurred due to Commercial’s delay and defective workmanship. In response, Commercial amended its complaint to add claims for fraud, intentional and negligent misrepresentation, rescission of the contract and $10 million in punitive damages. Commercial alleged that Weitz received an extension of the construction schedule but fraudulently withheld this information from Commercial and continued to impose unrealistic deadlines.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Coverage for Faulty Workmanship Denied
June 29, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe court found there was no coverage for the insureds' alleged negligent failure to construct a building. Evanston Ins. Co. v. DCM Contracting, 2020 U.S. Dist. LEXIS 63977 (N.D. Ga. Feb. 28, 2020).
Turning Point Church sued DCM Contracting for faulty workmanship on a construction project. Turning Point sent a demand letter to DCM on August 18, 2017 and filed suit in December. Evanston did not receive notice of Turning Point's claims and the lawsuit until May 15, 2018.
Evanston filed suit for a declaratory judgment and moved for summary judgment. The court first considered the late notice. The policy required notice "as soon as practicable" DCM was also required to provide copies of demands, notices, or legal papers to Evanston. Here, DCM did not give notice to Evanston until nine months after receipt of Turning Point's demand. A phone communication with DCM's agent between August 2017 and May 2018 was insufficient. DCM provided no documents, including the summons and complaint, to the agent. DCM waited five months to forward the underlying lawsuit. This was a breach of the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com