Wisconsin Supreme Court Holds that Subrogation Waiver Does Not Violate Statute Prohibiting Limitation on Tort Liability in Construction Contracts
October 21, 2019 —
Gus Sara - The Subrogation StrategistIn Rural Mut. Ins. Co. v. Lester Bldgs., LLC 2019 WI 70, 2019 Wisc. LEXIS 272, the Supreme Court of Wisconsin considered whether a subrogation waiver clause in a construction contract between the defendant and the plaintiff’s insured violated Wisconsin statute § 895.447, which prohibits limitations of tort liability in construction contracts. The Supreme Court affirmed the lower court’s decision that the waiver clause did not violate the statute because it merely shifted the responsibility for the payment of damages to the defendant’s insurance company. The waiver clause did not limit or eliminate the defendant’s tort liability. This case establishes that while
§ 895.447 prohibits construction contracts from limiting tort liability, a subrogation waiver clause that merely shifts responsibility for the payment of damages from a tortfeasor to an insurer does not violate the statute and, thus, is enforceable.
In Rural Mutual, the plaintiff’s insured, Jim Herman, Inc. (Herman), entered into a contract with Lester Buildings, LLC (Lester) to design and construct a barn on Herman’s property. The contract included a provision that stated the following:
Both parties waive all rights against each other and any of their respective contractors, subcontractors and suppliers of any tier and any design professional engaged with respect to the Project, for recovery of any damages caused by casualty of other perils to the extent covered by property insurance applicable to the Work or the Project, except such rights as they have to the proceeds of such property insurance and to the extent necessary to recover amounts relating to deductibles of self-insured retentions applicable to insured losses. . . . This waiver of subrogation shall be effective notwithstanding allegations of fault, negligence, or indemnity obligation of any party seeking the benefit or production [sic] of such waiver.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Florida Extends Filing Time for Claims Subject to the Statute of Repose
June 13, 2018 —
William L. Doerler - The Subrogation StrategistUnder Florida’s construction-related statute of repose, Fla. Stat. § 95.11, actions based on the design, planning or construction of an improvement to real property are barred if not commenced within 10 years after the later of several possible dates, including the date of actual possession by the owner and the date of the issuance of a certificate of occupancy. The Florida Legislature recently amended the statute to extend the time within which defendants subject to a suit filed close to the end of the 10-year period can file claims. Under the revised law, a defendant can file “counterclaims, cross-claims and third-party claims up to 1 year after the pleading to which such claims relate is served.” Regardless of when the cause of action at issue accrued, the law applies to actions commenced on or after July 1, 2018, except that any action that would not have been barred under Fla. Stat. § 95.11(3)(c) prior to the amendment may be commenced before July 1, 2019.
The revised law provides relief to defendants because, under the prior law, they had to file claims against other potentially responsible third parties before the expiration of the statute of repose. Under the new law, defendants can bring third parties into the action after the expiration of the 10-year statute of repose period.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Snooze You Lose? Enforcement of Notice and Timing Provisions
November 11, 2024 —
Cornelius F. "Lee" Banta, Jr. - ConsensusDocsDeadlines are an inescapable part of the construction industry. Bid deadlines. Submittal deadlines. Material delivery deadlines. Substantial completion. Final completion. And so, inevitably, fighting about deadlines becomes a necessary byproduct. Was the deadline really a deadline? Was the schedule slippage on the critical path? Should there be an equitable extension to the date of substantial completion? Given the amount of attention and concern conferred on deadlines, those drafting construction contracts naturally seek to clarify which deadlines really matter with the inclusion of notice and timing provisions.
A contract’s change order and claims procedures are often a key friction point for those drafting and administering the contract. Should there be a requirement for prior written notice of a claim for cost/time relief? How much advance notice? Who should the request be sent to? Is a specific form of notice required? What are the consequences of failing to provide timely notice? A practitioner should pay careful attention to negotiating these terms on the front end, because rest assured, these contract provisions will garner scrutiny when a change order dispute boils over.
Read the court decisionRead the full story...Reprinted courtesy of
Cornelius F. "Lee" Banta, Jr., Peckar & Abramson, P.C.Mr. Banta may be contacted at
lbanta@pecklaw.com
Contractual Waiver of Consequential Damages
January 02, 2019 —
David Adelstein - Florida Construction Legal UpdatesContractual waivers of consequential damages are important, whether they are mutual or one-sided. I believe in specificity in that the types of consequential damages that are waived should be detailed in the waiver of consequential damages provision. Standard form construction agreements provide a good template of the types of consequential damages that the parties are agreeing to waive.
But, what if there is no specificity in the waiver of consequential damages provision? What if the provision just states that the parties mutually agree to waive consequential damages or that one party waives consequential-type damages against the other party? Let me tell you what would happen. The plaintiff will argue that the damages it seeks are general damages and are NOT waived by the waiver of consequential damages provision. The defendant, on the other hand, will argue that the damages are consequential in nature and, therefore, contractually waived. FOR THIS REASON, PARTIES NEED TO APPRECIATE WHAT DAMAGES ARE BEING WAIVED OR LIMITED, AND POTENTIALLY THOSE DAMAGES NOT BEING WAIVED OR LIMITED, WHEN AGREEING TO A WAIVER OF CONSEQUENTIAL DAMAGES PROVISION!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Massachusetts Pulls Phased Trigger On Its Statute of Repose
December 21, 2020 —
Kyle Rice - The Subrogation SpecialistIn D’Allesandro v. Lennar Hingham Holdings, LLC, 486 Mass 150, 2020 Mass. LEXIS 721, the Supreme Judicial Court of Massachusetts answered a certified question regarding how to apply the Massachusetts statute of repose, Mass. Gen. Laws ch. 260, § 2B, in regards to phased construction projects. The court held that, in this context, the completion of each individual “improvement” to its intended use, or the substantial completion of the individual building and the taking of possession for occupancy by the owner or owners, triggers the statute of repose with respect to the common areas and limited common areas of that building. Additionally, the court held that where a particular improvement is integral to, and intended to serve, multiple buildings (or the development as a whole), the statute of repose is triggered when the discrete improvement is substantially complete and open to its intended use.
In D’Allesandro, the action arose out of the construction, marketing, sale and management of the Hewitts Landing Condominium (the Condominium) project. Ultimately, 150 units were constructed over 24 phases of construction, enclosed in 28 different buildings. Throughout construction, the project’s architect submitted declarations to the Town of Hingham swearing that the individual units were “substantially complete” and could be occupied for their intended use. The Town of Hingham then issued certificates of occupancy for the unit or building.
Read the court decisionRead the full story...Reprinted courtesy of
Kyle Rice, White and WilliamsMr. Rice may be contacted at
ricek@whiteandwilliams.com
Florida Representative Wants to Change Statute of Repose
December 10, 2015 —
Beverley BevenFlorez-CDJ STAFFCurrently in Florida, the ten year clock for construction defect claims typically starts ticking after the final payment is made by the owner. However, WFSU reported, Representative Keith Perry wants to change it so that the completion of the construction triggers the statute of repose.
This change “could favor the construction industry, by shifting the power to start the clock from home owners to builders,” WFSU claimed. Representative Dwight Dudley worries about “what would happen if a contractor felt she was finished but the property owner didn’t agree.”
Read the court decisionRead the full story...Reprinted courtesy of
Flushing Away Liability: What the Aqua Engineering Case Means for Contractors and Subcontractors
October 21, 2024 —
Heather Zipperer - Colorado Construction Litigation BlogThe recent Town of Mancos v. Aqua Engineering case is an insightful example of how well written contracts and timely legal action can make all the difference in resolving disputes between municipalities, general contractors, and subcontractors. The ruling favored Aqua Engineering; a subcontractor that played a role in a wastewater treatment facility project gone wrong. The court’s decision highlighted key legal principles, including the economic loss rule and the importance of well-structured contracts in construction disputes. Whether you are a subcontractor looking to avoid undue liability or a general contractor seeking to ensure subcontractors shoulder their fair portion of responsibility, this case offers valuable lessons for all parties involved in construction projects.
The Background: A Wastewater Project with Issues
In 2008, the Town of Mancos, Colorado, hired Souder, Miller & Associates (“SMA”) to design a new wastewater treatment facility. SMA subcontracted Aqua Engineering to help implement a specific wastewater treatment system known as the Multi-Stage Activated Biological Process (“MSABP”). However, after construction, the facility never worked as expected. For years, the Town faced ongoing issues, and despite Aqua’s involvement in attempts to fix the problems, the facility remained dysfunctional.
Read the court decisionRead the full story...Reprinted courtesy of
Higgins, Hopkins, McLain & Roswell, LLC
Construction Contract Clauses Which Go Bump in the Night – Part 1
November 10, 2016 —
Garret Murai – California Construction Law BlogScope, time and cost provisions may be the most important clauses in your construction contract but they’re not the only ones which can impact your bottom line. The first in a multi-part series, here are some other important construction contract clauses you may (or may not realize you should) be losing sleep over.
Provision: Incorporation and Flow-Down Provisions
- Typical Provision: “The term ‘Contract Documents’ shall include, without limitation, the Prime Contract, drawings, specifications and other agreements between Contractor and Owner, insofar as they relate in any way, directly or indirectly, to Subcontractor’s Work under this Agreement, and are hereby incorporated by reference. Subcontractor agrees to be bound to Contractor in the same manner and to the same extent as Contractor is bound to Owner under the Contract Documents. Where, in the Contract Documents, reference is made to Contractor, and the work and specifications therein pertain to Subcontractor’s trade, craft, or type of work, such work or specifications shall be interpreted to apply to Subcontractor rather than Contractor.”
- What it Means: An incorporation provision literally “incorporates” another document or documents into a contract by merely referring to them by title or description and it is not uncommon for a lower-tiered contractor to never see those documents.
A flow-down provision requires a lower-tiered contractor to comply with all obligations which a higher-tiered contractor, typically a direct contractor, owes to a higher-tiered party, typically, the owner. The intent of the provision to ensure that a lower-tiered subcontractor has no greater rights against a direct contractor has against the owner.
- What You Can Do: Lower-tiered contractors should obtain a copy of all documents to be incorporated into their contract and review them to ensure that they understand the obligations and any limitations to their rights.
Lower-tiered contractors should also seek to include language requiring that a higher-tiered contractor assume toward the lower-tiered contractor all obligations and limitations on their rights that the owner assumes toward or is subject to with respect of the general contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at