Giving Insurance Carrier Prompt Notice of Claim to Avoid “Untimely Notice” Defense
June 12, 2023 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to giving your insurance carrier notice of claim, I am an advocate of providing that notice as soon as possible, i.e., prompt notice. The reason is to take away the carrier’s argument to deny coverage because you, as the insured, failed to provide it with prompt notice—the “untimely notice” defense. It doesn’t matter whether it is a first party property insurance claim or third-party liability policy claim, provide notice as soon as reasonably possible to take away that “untimely notice” defense.
The “untimely notice” defense was the issue in Benson v. Privilege Underwriters Reciprocal Exchange, 48 Fla.L.Weekly D1085a (Fla. 6th DCA 2023) dealing with a first party property insurance policy. In this case, eighteen months after Hurricane Irma, the plaintiff noticed a smell and observed brown stains on walls and ceiling in his home. The plaintiff called roofing companies to inspect the damage and perform certain repairs. However, the plaintiff still noticed the smell so he called a company to test and remediate mold. The plaintiff, then, contacted his property insurer with numerous claims relative to the leaks and damage. Although there was an initial property insurance payment made, the carrier ultimately denied coverage for subsequent claims stating that “the late notice of the claim and the prior repairs to the roof substantially prejudiced its ability to complete an inspection of [plaintiff’s] property to evaluate the claim.” Benson, supra.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Association Bound by Arbitration Provision in Purchase-And-Sale Contracts and Deeds
January 11, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen an association files a lawsuit pertaining to matters of common interest, the lawsuit is typically filed as a class on behalf of the owners that make up the association (i.e., the association’s members). How do you deal with an arbitration provision that is included in an owner’s purchase-and-sale agreement or recorded in the deed? The recent opinion in Lennar Homes, LLC v. Martinique at the Oasis Neighborhood Association, Inc., 47 Fla. L. Weekly D15c (Fla 3rd DCA 2021) dealt with this exact issue with a homeowner’s association ruling that the association was required to arbitrate its latent construction defect claims against the developer (homebuilder).
In this case, a community in Miami consisted of 26 townhouse buildings. There was a broad arbitration provision in each owner’s purchase-and-sale agreement that included disputes relating to property damage. Further, with each closing, a special warranty deed was recorded that included a nearly identical arbitration provision.
The association became aware of latent defects relating to the exterior walls of the buildings and filed a lawsuit against the developer (homebuilder). The developer moved to compel the dispute to arbitration which was denied by the trial court because there was no specific agreement between the association and the developer that required arbitration and the lawsuit dealt with matters that the association was obligated to maintain.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Survey Finds Tough Labor Market Top-of-mind for Busy Georgia Contractors
July 30, 2019 —
Scott Hazy - Construction ExecutiveIn February 2019, the results of the third Annual Georgia Construction Outlook Survey were released. The survey respondents includes general contractors (44%), specialty contractors (53%) and heavy contractors (3%) with gross revenue size that ranged from in excess of $1 billion to less than $5 million. Three-quarters of respondents reported revenues of less than $25 million. Here’s what they had to say about the state of construction in Georgia.
Financial Performance and 2019 Outlook
It was no surprise to see the majority of respondents reporting increased revenues and margins in 2018. Average gross margins from all respondents increased to 11.3%, up from 9.33% in the prior year. Overall, 72% of respondents saw their gross margins increase and/or remain the same. The largest decrease in margins was seen in the heavy contractor sector, with 33% of respondents reporting a decrease in margins. When it comes to backlog, Georgia is seeing a record number of months in the pipeline and 57% of respondents reported higher backlogs than in the previous year. The increase in backlog helps explain why 84% of respondents are expecting increase in revenues in 2019 over 2018. Interestingly, of those expecting increase in revenue, 40% are anticipating an increase of more than 10% from the prior year. So, the overall financial health of Georgia contractors looks to remain strong at least through 2019.
Reprinted courtesy of
Scott Hazy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Hazy may be contacted at
scott.hazy@btcpa.net
The “Right to Repair” Construction Defects in the Rocky Mountain and Plains Region
October 16, 2018 —
Jean Meyer & Sheri Roswell - Colorado Construction Litigation BlogIn excess of 30 states have enacted tort reform legislation requiring property owners to notify construction professionals of the presence of alleged construction defects prior to the commencement of a lawsuit. These statutes also often permit construction professionals to make an offer of repair within a statutorily defined period of time after receipt of a notice of claim letter. Undoubtedly, the notice-of-claim process has played a meaningful part in bringing construction professionals and claimants to timely resolutions of construction defect concerns in isolated instances.
However, while these statutes are commonly referred to as “right of repair” legislation, their practical effect is often reduced to little more than procedural empty gestures serving as a prelude to litigation. This article will briefly survey the “right to repair” statutes in Colorado, Montana, North Dakota and South Dakota. In Nebraska, New Mexico, Utah and Wyoming there is no right to repair or notice-of claim statue.
Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell LLC and
Sheri Roswell, Higgins, Hopkins, McLain & Roswell LLC
Mr. Bracken, may be contacted at meyer@hhmrlaw.com
Ms. Russo may be contacted at roswell@hhmrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Gene Witkin Joins Ross Hart’s Mediation Team at AMCC
March 01, 2021 —
Arbitration Mediation Conciliation Center (AMCC)AMCC is pleased to announce Gene Witkin joining Ross Hart’s mediation team effective March 1 this year. Prior to joining our esteemed roster of neutrals, Mr. Witkin was active in complex litigation, insurance disputes, and conflict resolution in numerous different states and venues throughout the United States for more than thirty years. In 2000, he co-founded the law firm Menter & Witkin LLP that focused in large part on risk sharing and funding of large lawsuits, which gave him the diverse experience of representing both plaintiffs and defendants, as well as third-party defendants and insurance companies. Mr. Witkin completed mediator training at National Conflict Resolution Center in 2017, and is an AV Rated “Preeminent Attorney” by Martindale-Hubbell (highest rating) and “Super Lawyer” every year since 2015. He may be contacted at g.witkin@amccenter.com or through AMCC at (800) 645-4874.
Reprinted courtesy of
Arbitration Mediation Conciliation Center (AMCC) Read the court decisionRead the full story...Reprinted courtesy of
Settlement Agreement? It Ain’t Over ‘Til it’s . . . Final, in Writing, Fully Executed, and Admissible
April 12, 2021 —
Todd Likman - Colorado Construction LitigationAs litigators we have all been there: nearing the end of a hard-fought mediation that lasted all day. Your significant other texts to ask what is for dinner; daycare closes in thirty minutes; the dog needs to be let out. The mediator, a retired judge, gently reminds you of his prior commitment—a speaking engagement at a volunteer charity dinner event that night. Though the parties started the day at opposite ends of the spectrum, after numerous counteroffers, persistent negotiation, and mediation tactics, they finally strike a deal.
As the mediator prepares a document memorializing the terms of settlement, the parties wait with bloodshot eyes, and a sense of guarded accomplishment considering compromises were
made, but alas, an outcome seems certain. You text your significant other to indicate that you will pick something up for dinner on your way home.
Then, the mediator informs you that computer problems are preventing finalization and transmission of the document for signature. The mediator offers to send an e-mail setting forth the material settlement terms and asks each party to respond via e-mail to confirm the terms are correct, which the parties do. After a quick e-mail to your experts and case team asking them to cease trial preparation work, you leave for home.
Read the court decisionRead the full story...Reprinted courtesy of
Todd Likman, Higgins, Hopkins, McLain & RoswellMr. Likman may be contacted at
likman@hhmrlaw.com
Construction Termination Issues Part 4: What to Do When They Want to Fire You, the Architect or Engineer
August 14, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaWhat if you are told that your own design services are no longer needed or welcome on a project? Can they do that? What happens then? How do you protect yourself.
As you probably realize, while rare, the Owner does have the legal right to fire you “for cause”. See B101 §9.4, as long as the Owner gives you 7 days written notice. In fact, the Owner can terminate your contract for any reason at all (maybe you root for the wrong basketball team?) by terminating you for convenience (i.e., for any reason whatsoever) under B101 §9.5, again with 7 days written notice.
As with
Contractor terminations, the money you get when fired for convenience is much greater than when you are terminated for cause. If you are fired “for convenience”, you get paid for all services previously rendered as well as termination expenses, including anticipated profit on the value of services not performed. See B101 §9.7.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Be Mindful Accepting Payment When Amounts Owed Are In Dispute
August 29, 2022 —
Nicholas Korst - Ahlers Cressman & Sleight PLLCAfter completing work on a project, or even during a project, it is not uncommon for some portion of the contract balance and/or a claim to be in dispute. As a contractor or subcontractor, it is important to be careful what is signed (or not signed) upon receipt of any payment both during and after completion of work on a project. One of the most common documents signed related to a receipt of payment is a lien/claim release document. This can be in the form of a conditional, unconditional, progress and/or final release. The language included in the release document is critically important, especially as it pertains to disputed amounts. As a contractor or subcontractor, if there are known disputes related to amounts owing, whether it be contract balance, disputed change order(s), a delay or inefficiency claim, or any other amounts believed to be owed, it is important to include language in the lien release that expressly carves out the disputed amounts. The same should be done for disputes related to extensions of time. This allows the contractor to accept the payment and release rights for the undisputed work, but continue to reserve its right to pursue the amounts in dispute later. If disputed amounts are not carved out, those amounts may effectively be waived and the subcontractor or contractor may lose all rights to recovery.
As a subcontractor in Alaska recently learned, there are potentially other ways a contractor may waive or lose its rights to recover amounts in dispute – without even signing a waiver or release document. In Smallwood Creek, Inc. v. Build Alaska General Contracting, LLC et al., the general contractor sent the subcontractor a check described as “final payment.” The subcontractor believed it was owed more than what the general contractor had sent and refused to accept the check. Months later, the subcontractor deposited the check. The subcontractor reversed course again and attempted to repay the general contractor the amount deposited. The general contractor refused, claiming the subcontractor’s acceptance of payment constituted satisfaction of all amounts owing to the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas Korst, Ahlers Cressman & Sleight PLLCMr. Korst may be contacted at
nicholas.korst@acslawyers.com