New Jersey Supreme Court Hears Insurers’ Bid to Overturn a $400M Decision
January 25, 2021 —
Lawrence J. Bracken II, Michael S. Levine & Daniel Hentschel - Hunton Andrews KurthNew Jersey’s highest court heard arguments Monday in the appeal of a ruling that the New Jersey Transit Corp.’s (“NJ Transit”) insurers are required to insure $400 million of water damage loss caused by Hurricane Sandy.
The matter stems from an insurance claim NJ Transit made after the super storm rocked the East Coast in 2012. NJ Transit claimed over $400 million in losses as a result of damage to its tracks, bridges, tunnels and power stations. In response, its tower of property insurers took the position that a $100 million flood sublimit applied to limit NJ Transit’s recovery under its insurance tower, not the policy’s $400 million overall limits.NJ Transit filed a coverage action in state court. The trial court granted summary judgment to NJ Transit, holding that NJ Transit was entitled to full coverage of $400 million under the tower’s named windstorm coverage. The insurers appealed, again arguing that the flood sublimit applied to the claim.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Wildfire Risk Scores and Insurance Placement: What You Should Know
July 15, 2024 —
Louis "Dutch" Schotemeyer & Molly L. Okamura - Newmeyer DillionWhat Are Wildfire Risk Scores and How Are They Calculated?
Wildfire risk scores are scores assigned to properties by third-party vendors based on the likelihood of direct or indirect exposure to a wildfire. Wildfire risk scores can be a factor used by insurance companies when making coverage decisions. Additionally, wildfire risk scores can be a helpful metric for real estate developers to consider when determining whether to buy a piece of property.
There are a variety of vendors that use unique methods to calculate wildfire risk scores. For example, CoreLogic, FireLine, and RedZone are vendors used by insurance companies in California. Some vendors' scoring scales are from 1-10, and some are from 1-100, but generally the higher the score, the higher the likelihood of a wildfire impacting the property. There is no national, standardized scoring scale.
Reprinted courtesy of
Louis "Dutch" Schotemeyer, Newmeyer Dillion and
Molly L. Okamura, Newmeyer Dillion
Mr. Schotemeyer may be contacted at dutch.schotemeyer@ndlf.com
Ms. Okamura may be contacted at molly.okamura@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
11th Circuit Affirms Bad Faith Judgement Against Primary Insurer
July 24, 2023 —
Ashley Kellgren - Traub Lieberman Insurance Law BlogIn American Builders Insurance Co. v. Southern-Owners Ins. Co., 2023 U.S. Dist. LEXIS 15386, No. 21-13496 (11th Cir. June 20, 2023), the Eleventh Circuit affirmed a bad faith judgment against a primary insurer.
On April 1, 2019, Ernest Guthrie fell from a roof, causing him to became paralyzed from the waist down. At the time of the accident, Guthrie was employed by his own subcontracting company and was performing work for Beck Construction. Beck Construction was insured under a general liability policy issued by American Builders and an excess policy issued by Evanston. Each of those policies provided $1 million in liability limits. Guthrie’s company was insured under a policy issued by Southern-Owners, which provided a per occurrence limit of $1 million. Under the Southern-Owners policy, Beck Construction was an additional insured and coverage was provided to Beck Construction on a primary basis.
Read the court decisionRead the full story...Reprinted courtesy of
Ashley Kellgren, Traub LiebermanMs. Kellgren may be contacted at
akellgren@tlsslaw.com
2018 Construction Outlook: Mature Expansion, Deceleration in Some Sectors, Continued Growth in Others
January 24, 2018 —
Garret Murai – California Construction Law BlogU.S. construction starts are expected to increase 3 percent to $765 billion in 2018 according to
Dodge Data & Analytics in its 2018 Dodge Construction Outlook. But we may be approaching the end of a construction boom, at least in certain industry segments.
The construction industry as a whole is in a “mature stage of expansion,” indicates Robert Murray, Chief Economist for Dodge Data & Analytics. “After rising 11% to 13% per year from 2012 through 2015, total construction starts advanced a more subdued 5% in 2015. An important question entering 2017 was whether the construction industry had the potential for further expansion,” explained Murray.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black, Dean, LLP Mr. Murai may be contacted at
gmurai@wendel.com
Dump Site Provider Has Valid Little Miller Act Claim
October 19, 2020 —
Christopher G. Hill - Construction Law MusingsYou may have thought that a Virginia “Little Miller Act” bond claim, like a mechanic’s lien, could only be brought by those that provide materials and labor incorporated into the construction project. If you did, you aren’t alone.
In fact, Safeco Insurance Co. of America, a surety, made exactly the above argument in Yard Works LLC v. GroundDown Constructors LLC. In that case, a debris hauling company failed to pay Yard Works, the company that provided the dumping site for the debris. Yard Works sued pursuant to the Little Miller Act to get paid. In response, the surety sought to have the claim against the payment bond dismissed and argued that because Yard Works did not actually improve the property or provide improvements and that Yard Works only passively provided a dump site, Yard Works could not claim under the payment bond.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Eyerly may be contacted at
te@hawaiilawyer.com
Encinitas Office Obtains Complete Defense Verdict Including Attorney Fees and Costs After Ten Day Construction Arbitration
May 23, 2022 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPPartner Vik Nagpal and Associate Attorney Tim McNulty of the Encinitas office recently obtained a substantial victory on behalf of BWB&O’s client after a 10-day binding construction arbitration before a three-arbitrator panel of the American Arbitration Association.
BWB&O’s client was sued by the Owner of a commercial office building related to a multimillion-dollar tenant improvement project in San Diego. The Owner asserted construction defect damages, delay damages, architectural negligence, fraudulent billing practices and consequential damages of $3.6 million dollars. BWB&O’s client claimed breach of contract damages against the owner for failure to pay invoices.
The Owner who had substantial financial resources and a personal spite against the general contractor, unreasonably pursued the case with an extensive team of lawyers and experts. At an earlier full-day mediation, the owner rejected a reasonable settlement offer which included a settlement payment to the Owner and the client’s agreement to dismiss their affirmative claim for damages.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Lis Pendens – Recordation and Dissolution
July 28, 2016 —
David Adelstein – Florida Construction Legal UpdatesWhen you file a construction lien foreclosure lawsuit, you must also record a lis pendens in the official (public) records against the property. This lis pendens serves as written notice that there is a lawsuit concerning the real property, and more specifically, title relating to that real property. If the property is then sold or rented, the buyer or tenant will ultimately be bound by a final determination relating to the lawsuit concerning title to the property. This is the value in recording a lis pendens and why it is a MUST in any foreclosure lawsuit. (This is the same value in any mortgage foreclosure lawsuit and why lis pendens are recorded in these lawsuits too.) A lis pendens will show up in a title report. In most instances, title companies will not issue a title policy if there is a lis pendens or may require a certain amount of money escrowed as a result of the lis pendens and pending action in order to issue a title policy. Also, a buyer, in particular, and a tenant are not going to want to invest in property where the title to that property is at-issue in a lawsuit. Hence, the lis pendens impacts the sale and potential re-financing of the property.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Sub-Limit Restricts Insured's Flood Damage Recovery
March 15, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe insured's recovery for flood damage was controlled by the policy's sub-limit. David S. Brown Enters. v. Affiliated FM Ins. Co., 2020 U.S. Dist. LEXIS 239208 (D. Md. Dec. 18, 2020).
Roughly 6.6 inches of rain fell in Ellicott City, Maryland, causing extensive flooding. During the storm, a water main broke on Main Street, in relatively close proximity to the insured's two properties on Main Street. The foundations of the two properties washed away.
The insured, David S. Brown Enterprises (DSB), had a business owners' policy with Affiliated with covered 204 named locations. The Main Street Properties were not listed, but the policy also provided certain coverage for unnamed locations. The sub-limit applicable to unnamed locations was $1,000,000. The sub-limit for flood, however, was $50,000, annual aggregate "as respects Errors & Omissions, Off-Premises Service Interruption, Unnamed Locations and Supply Chain combined." Affiliated paid $50,000 for the loss based upon the $50,000 Flood annual aggregated Sub-Limit for Unnamed Locations. DSB disagreed that the $50,000 sub-limit applied and filed suit.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at