The Court of Appeals Holds That Indifference to Safety Satisfies the Standard for a Willful Violation Under WISHA
May 16, 2022 —
Cameron Sheldon - Ahlers Cressman & Sleight PLLCIn March 2022, the Washington State Court of Appeals, Division One, issued Marpac Constr., LLC v. Dep’t of Lab. & Indus., No. 82200-4-I, 2022 WL 896850, at *1 (Wash. Ct. App. Mar. 28, 2022) holding Marpac Construction, LLC (“Marpac”) liable for three willful Washington Industrial Safety and Health Act of 1973 (WISHA) violations pertaining to safe crane operation near energized power lines.
Marpac was the general contractor on an apartment complex construction project in West Seattle. The worksite had high voltage power lines running throughout the site. Seattle City Light had flagged some with a 10-foot offset, but none of the other power lines were flagged. Marpac’s superintendent assumed that the lines were between 26 kilovolts (kV) and 50 kV based on their connection to the lines flagged by Seattle City Light. The superintendent never called Seattle City Light to check the voltage of the lines and the lines remained above ground.
In September 2016, a subcontractor began work on the project’s structural foundation. The subcontractor expressed concerns about working around the power lines, but Marpac promised it was working on mitigation of the power line hazard and directed the subcontractor continue working. At one point, the subcontractor’s employees had to move the crane and concrete forms away from the power lines to allow a cement truck to park in its place. The crane’s line contacted the power lines, causing serious injuries to two of the subcontractor’s employees.
Read the court decisionRead the full story...Reprinted courtesy of
Cameron Sheldon, Ahlers Cressman & Sleight PLLCMs. Sheldon may be contacted at
cameron.sheldon@acslawyers.com
Construction Defect Settlement in Seattle
June 28, 2013 —
CDJ STAFFThe Seattle Post-Intelligencer reports that a settlement has been reached in the Mosler Lofts construction defect claim. The settlement received by the homeowners was for about $8.5 million, which will used for repairs of the construction defects and for paying their legal costs.
Read the court decisionRead the full story...Reprinted courtesy of
Home-Sales Fall in 2014 Has U.S. Waiting for 2015: Economy
January 28, 2015 —
Bloomberg News(Bloomberg) -- A three-year winning streak for sales of previously owned homes in the U.S. ended in 2014 as some investors stepped out of the market and first-time buyers failed to fill the void.
Purchases totaled 4.93 million last year, down 3.1 percent from the 5.09 million houses sold in 2013, figures from the National Association of Realtors showed Friday in Washington.
The share of American homebuyers making their first purchase dropped in 2014 to its lowest level in almost three decades, according to the Realtors group. At the same time, employment gains, growing consumer confidence, mortgage rates at historically low levels and government efforts to lower purchasing costs probably will help bolster demand in 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg News
Accounting for Payments on Projects Became Even More Crucial This Year
September 21, 2020 —
Christopher G. Hill - Construction Law MusingsI discussed
several of the statutory changes affecting the construction industry here at Construction Law Musings in the run-up to July 1, 2020. One of those changes, an amendment to
Virginia Code Section 43-13, may add another arrow to the collection quiver of subcontractors and suppliers. As part of the previously-linked rundown, I highlighted one of the big additions in 2020, namely the amendment making those pesky clauses that let those up the payment chain from you hold money on “this or any other project” void as against public policy.
The other big addition to 43-13 is the change that adds a possible civil cause of action for downstream and unpaid subcontractors and suppliers in the event that funds paid to a general contractor or subcontractor are not first used to pay their downstream contractors and suppliers. Prior to July 1, 2020, this statute provided criminal penalties for such behavior but did not contain the possibility of a civil penalty. The operative language for the change is as follows:
The use by any such contractor or subcontractor or any officer, director, or employee of such contractor or subcontractor of any moneys paid under the contract before paying all amounts due or to become due for labor performed or material furnished for such building or structure for any other purpose than paying such amounts due on the project shall be prima facie evidence of intent to defraud. Any breach or violation of this section may give rise to a civil cause of action for a party in contract with the general contractor or subcontractor, as appropriate; however, this right does not affect a contractor’s or subcontractor’s right to withhold payment for failure to properly perform labor or furnish materials on the project.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
New York Assembly Reconsiders ‘Bad Faith’ Bill
May 17, 2021 —
Copernicus T. Gaza, Adam Krauss, Robert S. Nobel, Craig Rokuson & Eric D. Suben - Traub LiebermanThe New York State Assembly is considering A07285, which creates a private right of action for bad faith “if the insurer unreasonably refuses to pay or unreasonably delays payment without substantial justification.” The bill was first introduced in 2013 but was reintroduced on May 3, 2021 and has received some recent attention. According to the bill, an insurer acts unreasonably when it (among other things):
- Fails to provide the claimant with accurate information regarding policy provisions relating to the coverage at issue; or
- Fails to effectuate in good faith a prompt, fair, and equitable settlement of a claim or portion of a claim and where the insurer failed to reasonably accord at least equal or more favorable consideration to its insured's interests as it did to its own interests, and thereby exposed the insured to a judgment in excess of the policy limits or caused other damage to a claimant; or
- Fails to provide a timely written denial of a claimant's claim, or portion thereof, with a full and complete explanation of such denial, including references to specific policy provisions wherever possible; or
Reprinted courtesy of
Copernicus T. Gaza, Traub Lieberman,
Adam Krauss, Traub Lieberman,
Robert S. Nobel, Traub Lieberman,
Craig Rokuson, Traub Lieberman and
Eric D. Suben, Traub Lieberman
Mr. Gaza may be contacted at cgaza@tlsslaw.com
Mr. Krauss may be contacted at akrauss@tlsslaw.com
Mr. Nobel may be contacted at rnobel@tlsslaw.com
Mr. Rokuson may be contacted at crokuson@tlsslaw.com
Mr Suben may be contacted at esuben@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Performance-Based Energy Code in Seattle: Will It Save Existing Buildings?
August 11, 2011 —
Douglas Reiser, Builders Council BlogThe City of Seattle has one of the most stringent energy codes in the nation. Based upon the Washington State Energy Code (which has been embroiled in litigation over its high standards), the code demands a lot from commercial developers. But, does it prevent developers from saving Seattle?s classic and old buildings? Perhaps.
The general compliance procedure requires buildings to be examined during the permitting process. This means that buildings are examined before they begin operating. The procedure is not malleable and is applicable to all buildings, old and new, big and small.
The downside of this procedure is that it eliminates awarding compliance to those buildings exhibiting a number of passive features, such as siting, thermal mass, and renewable energy production. This problem has prevented a number of interesting and architecturally pleasing existing building retrofits from getting off the ground. The cost of complying with the current system can be 20% more, and it might prevent builders from preserving a building?s historical integrity.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decision
Read the full story...Reprinted courtesy of
Payne & Fears LLP Recognized by U.S. News & World Report and Best Lawyers in 2023 “Best Law Firms” Rankings
November 28, 2022 —
Payne & Fears LLPPayne & Fears LLP is pleased to announce that the firm has been recognized by U.S. News & World Report and Best Lawyers 2023 “Best Law Firms” list. Firms included in the 2023 edition of U.S. News – Best Lawyers “Best Law Firms” are recognized for professional excellence with consistently impressive ratings from clients and peers. This includes the top 5% of private practicing lawyers in the United States.
Payne & Fears LLP has been ranked in the following practice areas:
- Commercial Litigation
- Employment Law – Management
- Insurance Law
- Labor Law – Management
- Litigation – Labor & Employment
- Litigation – Real Estate
- Litigation – Intellectual Property
Additionally, on August 15, 2022, 11 of our attorneys were selected for inclusion in
The Best Lawyers in America® 2023. Collectively bringing decades of experience and dedication to their practice, Jeffrey K. Brown, Daniel F. Fears, Daniel M. Livingston, Thomas L. Vincent, Benjamin A. Nix, James L. Payne, Scott S. Thomas, and Kelby Van Patten received this respected achievement. Additionally, Leilani E. Jones, Sarah J. Odia, and Matthew C. Lewis were included in Best Lawyers: Ones to Watch 2023.
Read the court decisionRead the full story...Reprinted courtesy of
Payne & Fears LLP
Break out the Neon: ‘80s Era Davis-Bacon “Prevailing Wage” Definition Restored in DOL Final Rule
August 21, 2023 —
A. Scott Hecker & Ted North - The Construction SeytOn August 8, 2023, the U.S. Department of Labor (DOL)
announced its
final rule related to the Davis-Bacon Act (the “Act”), entitled “Updating the Davis-Bacon and Related Acts Regulations.” However, the official final rule must be published in the Federal Register – likely by week’s end – before going into effect 60 days after publication.
DOL issued its notice of proposed rulemaking (“NPRM”) in March 2022 and received more than 40,000 comments from interested stakeholders. Evaluating and addressing those comments took the better part of a year, as DOL did not send the rule to the Office of Information and Regulatory Affairs (“OIRA”) for White House approval until December 16, 2022. After languishing for months, OIRA has now concluded its review, allowing DOL to move forward with its final rule.
Reprinted courtesy of
A. Scott Hecker, Seyfarth and
Ted North, Seyfarth
Mr. Hecker may be contacted at shecker@seyfarth.com
Mr. North may be contacted at enorth@seyfarth.com
Read the court decisionRead the full story...Reprinted courtesy of