Be Mindful Accepting Payment When Amounts Owed Are In Dispute
August 29, 2022 —
Nicholas Korst - Ahlers Cressman & Sleight PLLCAfter completing work on a project, or even during a project, it is not uncommon for some portion of the contract balance and/or a claim to be in dispute. As a contractor or subcontractor, it is important to be careful what is signed (or not signed) upon receipt of any payment both during and after completion of work on a project. One of the most common documents signed related to a receipt of payment is a lien/claim release document. This can be in the form of a conditional, unconditional, progress and/or final release. The language included in the release document is critically important, especially as it pertains to disputed amounts. As a contractor or subcontractor, if there are known disputes related to amounts owing, whether it be contract balance, disputed change order(s), a delay or inefficiency claim, or any other amounts believed to be owed, it is important to include language in the lien release that expressly carves out the disputed amounts. The same should be done for disputes related to extensions of time. This allows the contractor to accept the payment and release rights for the undisputed work, but continue to reserve its right to pursue the amounts in dispute later. If disputed amounts are not carved out, those amounts may effectively be waived and the subcontractor or contractor may lose all rights to recovery.
As a subcontractor in Alaska recently learned, there are potentially other ways a contractor may waive or lose its rights to recover amounts in dispute – without even signing a waiver or release document. In Smallwood Creek, Inc. v. Build Alaska General Contracting, LLC et al., the general contractor sent the subcontractor a check described as “final payment.” The subcontractor believed it was owed more than what the general contractor had sent and refused to accept the check. Months later, the subcontractor deposited the check. The subcontractor reversed course again and attempted to repay the general contractor the amount deposited. The general contractor refused, claiming the subcontractor’s acceptance of payment constituted satisfaction of all amounts owing to the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas Korst, Ahlers Cressman & Sleight PLLCMr. Korst may be contacted at
nicholas.korst@acslawyers.com
California Assembly Bill Proposes an End to Ten Year Statute of Repose
May 09, 2011 —
CDJ STAFFCalifornia Assemblyman Furutani has introduced a bill that if passed would eliminate the ten year statute of repose in certain construction defect cases. The statute of repose would not apply when “an action in tort to recover damages for damage to real or personal property, or for personal injury or wrongful death from exposure to hazardous or toxic materials, pollution, hazardous waste, or associates environmental remediation activities,” according to the latest amended version of AB 1207.
When Furutani first introduced the bill, it was aimed at small businesses only. However, the description of the bill, which read, “An act to amend Section 14010 of the Corporations Code, relating to small businesses” has been stricken from the bill, and it has been amended to read, “An act to amend Section 337.15 of the Code of Civil Procedure, relating to civil actions.”
The change in the bill’s intent has caused some outcry among attorneys in the blogosphere. For instance, Sean Sherlock of Snell & Wilmer stated that “the proposed amendment is unnecessary, and would upset nearly 50 years of deliberative legislation and judicial precedent on construction defects liability and the 10–year statute — all apparently motivated by a decision in a single, isolated Superior Court lawsuit that has not yet been reviewed by the court of appeal.” Sherlock is referring to Acosta v. Shell Oil Company, in which the Superior Court agreed to dismiss the plaintiffs’ claims against the developer based in part on the ten year statute of repose. AB 1207 was amended five days after the ruling in Acosta v. Shell Oil Company.
California AB 1207 has been re-referred to the Judiciary Committee.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Southern California Lost $8 Billion in Construction Wages
August 17, 2011 —
CDJ STAFFLos Angeles and Orange Counties are first on a list no area wants to be on. According to the Sacramento Bee, reporting on data from the U.S. Bureau of Economic Analysis, LA and Orange Counties saw an $8 billion drop in construction wages in 2010, as compared to 2006. In 2006, the region saw payrolls of $26.8 billion, but in 2010, that was reduced to $18.5 billion.
This was not the largest percentage change. Of the metropolitan areas with the largest declines in construction earnings, Las Vegas saw a $3.6 billion drop, however that represented half of their 2006 totals of $7.2 billion. Conversely, a $3.3 billion drop in the New York area represented only 10% of what had been $33.8 billion in payroll in 2006.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “This Is Sufficient for Your Purposes …”
April 08, 2024 —
Daniel Lund III - Lexology… but just barely.
Federal courts are “notice” pleading courts. One source writes: “Notice pleading refers to pleading standards that merely notify the opposing party and court of the general issues in the case. In contrast to fact pleading standards, notice pleading standards do not require pleadings to include hyper-detailed facts in support of each claim.”
Some state courts – including Louisiana – are fact pleading courts. Ordinarily, no one practicing in Louisiana state courts would describe the fact pleading requirements for initiating a lawsuit as mandating “hyper-detailing” of the facts, but … why risk it?
In a construction mechanics lien case – the jurisprudence for which requires that courts strictly construe the related law because liens empower lien holders with rights which are “in derogation” of common property ownership rights – the defendant was successful in having the trial court dismiss a lien suit for failing to affirmatively set forth in the complaint (a “petition” in Louisiana) the date of substantial completion. The lien claimant appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Forethought Is Key to Overcoming Construction Calamities
February 10, 2020 —
Mitch Cohen - Construction ExecutiveWithout warning, an under-construction structure in the southern United States suffered a catastrophic collapse. The tragedy resulted in the death of several people. As a result, engineering and construction post-collapse forensics experts engaged in an 18-month investigation.
Those involved in the design and build project included the general contractor hired by the owner, a prime engineer, a consulting peer-review engineer and a prime structural design firm supported by a sub-consulting structural engineer. Although significant cracking was noticed several weeks before the failure, no one sounded the alarm or deemed the cracking worthy of corrective action.
In their findings, forensic experts found the collapse resulted from the combined failure of the general contractor, engineers and even the owner, who all failed to shut down the work once the cracking reached unacceptable levels and/or take the appropriate actions needed to secure the public safety and mitigate the risk. This was even after the general contractor requested that the engineer-of-record and design manager assess the structure’s extreme cracking. Consequently, the choice to not seriously investigate the crack or seek an independent peer review to design a rectification plan contributed directly to the tragedy. This is typically referred to within the industry as a “negligent professional design error.”
Reprinted courtesy of
Mitch Cohen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Cohen may be contacted at
mitch.cohen@rtspecialty.com
Contractor Gets Benched After Failing to Pay Jury Fees
April 11, 2022 —
Garret Murai - California Construction Law BlogTrial by jury is a fundamental right under the U.S. and California Constitutions. However, to avail yourself of this right, you not only have to declare that in advance that you intend to try your case to a jury but post jury fees as well. In TriCoast Builders, Inc. v. Fonnegra, a contractor who failed to timely post jury fees, discovered on the day of trial that it waived the right to insist on a jury trial when the defendant pulled an “I gotcha” and waived his right to a jury trial.
The TriCoast Case
In May 2014, Nathaniel Fonnegra house was damaged by fire. The following month, Fonnegra entered into a construction contract with TriCoast Builders, Inc. to repair the property. Dissatisfied with the work, Fonnegra terminated the contract, and TriCoast in turn filed a complaint against Fonnegra for unpaid work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Constructive Change Directives / Directed Changes
June 06, 2018 —
David Adelstein - Florida Construction Legal Updatesrime contracts typically contain a constructive change directive clause. A constructive change directive also goes by the acronym CCD (and for purposes of this article, such changes will be referred to as a CCD), however it can also be known as a Work Change Directive, Interim Directed Change, or Directed Change, depending on the type of contract beign utilized. An owner can order a CCD, versus issuing the contractor a formalized change order, as a mechanism to direct the prime contractor to perform work if there is a dispute as to contract amount, time, or scope. Just because an owner issues a CCD does not mean the owner is conceding that it owes the contractor a change order. Rather, the owner is ordering the CCD as a mechanism to keep the project moving forward notwithstanding a disagreement with the contractor as to the price or time impact. Standard form construction agreements such as the AIA, EJCDC, or ConsensusDocs, will have a standard provision dealing with change directives where the owner can order the contractor to proceed with work in the absence of a change order. In the federal government context, most construction contracts will contain a changes clause that authorizes the government to formally direct changes; and, there is authority for contractors to equitably pursue a constructive change based on certain directives or instructions issued by the government. Naturally, from the contractor’s perspective, this CCD provision is an important consideration as it could likely require the contractor to finance a change to the owner’s project, particularly if there is a scope dispute where the owner does not believe the contractor is entitled to any change order.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Palm Beach Billionaires’ Fix for Sinking Megamansions: Build Bigger
June 14, 2021 —
Prashant Gopal & Amanda L. Gordon - BloombergThomas Peterffy became one of the world’s richest people by mastering risk on Wall Street. Building his Mediterranean-style mansion seven years ago on a vulnerable stretch of Florida’s Palm Beach Island was a matter of seeing the odds clearly once again. The consequences of climate change will play out over decades, and Peterffy is 76 years old.
“I don’t have a care about it at all,” he said over lunch at Mar-a-Lago earlier this year, just down the street from his home. The founder of Interactive Brokers Group has a fortune of more than $21 billion, according to the Bloomberg Billionaires Index.
“If something needs to be done to save it,” he added, “it’s not going to be my problem.”
The town of Palm Beach is busy adapting to the risks of a warming planet, even if there appear to be fewer worriers among the buyers and speculative builders on the island. Some of the lowest-lying properties in the U.S. are seeing the highest-flying prices. The real estate website Zillow estimates the value of Peterffy’s home at $52 million. This year a new nine-bedroom mansion with toes-in-the-sand views sold to financier Scott Shleifer for a record-breaking price in excess of $122 million.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal & Amanda L. Gordon, Bloomberg