Federal District Court Addresses Material Misrepresentation in First Party Property Damage Claim
August 26, 2024 —
James M. Eastham - Traub LiebermanIn Pittsfield Dev. LLC v. Travelers Indem. Co., 2024 U.S. Dist. LEXIS 117530 (N.D. Ill. July 3, 2024), the United States District Court for the Northern District of Illinois addressed an alleged material misrepresentation by an insured during the course of the adjustment of a water loss claim at an insured property. Subsequent to a pipe burst event which caused damage to a number of the floors in the insured building, the insured submitted a claim to Travelers and also submitted, with the assistance of a retained public adjuster, a damage estimate of the damages at the property. Included within the estimate submitted by the insured was a line item for "Lead Paint & Asbestos Removal" with a corresponding dollar amount of $1,140,000. It was this line item which formed the basis of Travelers' claim of misrepresentation.
At his deposition, the public adjuster testified that the $1,140,000 figure was an oral estimate received over the phone from an asbestos remediation company. Travelers disputed the testimony and contended that no such estimate was ever provided. For support, Travelers pointed to deposition testimony from a remediation company employee that while rough estimates were occasionally given verbally, the largest over the phone estimate she could recall was in the $20,000-$25,000 range. It was also disputed that the company would ever provide an oral quote of that magnitude sight unseen, especially since the largest project the remediation company had ever completed was less than $250,000.
Read the court decisionRead the full story...Reprinted courtesy of
James M. Eastham, Traub LiebermanMr. Eastham may be contacted at
jeastham@tlsslaw.com
The Burden of Betterment
February 23, 2017 —
Ryan M. Charlson, Esq. - Florida Construction Law NewsThe concept of betterment has long been used by defendants in cases involving defective design or construction to limit the damages awarded to a plaintiff.[1] The theory behind betterment is that: “if in [the] course of making repairs [an] owner adopts a more expensive design, recovery should be limited to what would have been the reasonable cost of repair according to original design.”[2] Betterment is often raised as an affirmative defense, requiring a defendant to prove that the plaintiff has received a good or service that is superior to that for which the plaintiff originally contracted. A recent South Florida case seems, at first blush, to suggest the burden of establishing the value of betterments may fall to the plaintiff, although a closer reading indicates the decision is likely to have limited applicability.
In Magnum Construction Management Corp. v. The City of Miami Beach, the Third District Court of Appeal was asked to review the damages award to the City for construction defects associated with the redesign and improvement of a park.[3] The completed project contained landscaping deficiencies, along with other “minor defects” in the playground’s construction.[4] After a unilateral audit, and without providing the contractor its contractually required opportunity to cure the defects, the City “removed, redesigned, and replaced the playground in its entirety.”[5] It did so despite no recommendation by the City’s own expert to perform such work.[6] During the bench trial, the “only measure of damages provided by the City was the costs associated with the planning, permitting, and construction of a park that is fundamentally different from the one it contracted with [the contractor] to build.”[7]
Read the court decisionRead the full story...Reprinted courtesy of
Ryan M. Charlson, Cole, Scott & Kissane, P.A.Mr. Charlson may be contacted at
ryan.charlson@csklegal.com
Traub Lieberman Partner Katie Keller and Associate Steven Hollis Obtain Summary Judgment Based on Plaintiff’s Failure to Comply with Policy Conditions
June 12, 2023 —
Kathryn Keller & Steven A. Hollis - Traub LiebermanTraub Lieberman Partner Katie Keller and Associate Steven Hollis obtained summary judgment on behalf of a major homeowners’ insurer in a breach of contract action in the Circuit Court for the Ninth Judicial Circuit in and for Osceola County, Florida. The underlying claim involved a water loss in the kitchen of the Plaintiff’s property allegedly resulting in substantial damage to the home necessitating renovations throughout the residence. The claim was reported seventeen days after the reported date of loss by Plaintiff’s counsel. The Plaintiff had retained counsel and two vendors before giving notice to the insurer. In addition, the insurer’s field adjuster was not provided the opportunity to inspect the plumbing materials which had been allegedly damaged. Specifically, the bottom panel of the sink kitchen cabinet box had been removed. The insurer retained an engineer, who concluded that the removal of the damaged property hindered the ability of the engineer to determine their conditions prior to removal or whether exposure from waste arm leakage occurred. It was later learned that the damaged plumbing fixtures and the bottom of the cabinets had been thrown out by the contractors, which all happened before the claim was reported to the insurer. The insured also failed to provide a signed, sworn proof of loss within sixty days after the loss.
Reprinted courtesy of
Kathryn Keller, Traub Lieberman and
Steven A. Hollis, Traub Lieberman
Ms. Keller may be contacted at kkeller@tlsslaw.com
Mr. Hollis may be contacted at shollis@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Massachusetts Couple Seek to Recuse Judge in Construction Defect Case
September 30, 2011 —
CDJ STAFFAfter seeing their $1 million jury award overturned on appeal by a judge who called the award “against the weight of evidence and likely due to misapprehension, confusion or passion,” Kathryn and Christian Culley are seeking to have him removed from the case. The Massachusetts Supreme Judicial Court has rejected their claim.
The Culleys claim that Judge Thomas R. Murtagh’s decision was influence by him membership in the Andover Country Club which is represented by the opposing counsel in their construction defect case. Justice Margot G. Botsford had denied the Culley’s request, ruling that they had other remedies available to them.
The SJC noted in their ruling that if the Culleys are alleging judicial misconduct a request must be made to the Commission on Judicial Conduct. Their lawyer plans to file a new motion for recusal with the SJC.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Critical Updates in Builders Risk Claim Recovery: Staying Ahead of the "Satisfactory State" Argument and Getting the Most Out of LEG 3
December 11, 2023 —
Gregory D. Podolak & Cheryl L. Kozdrey - Saxe Doernberger & Vita, P.C.Builders risk claims routinely involve complicated and aggressive debate about the interplay between covered physical loss and uncovered faulty work. However, denials on this front have recently experienced a noticeable uptick in frequency, creativity, and aggressiveness. The insurer arguments concentrate in two key areas with a common theme – that any damage associated with a construction defect is not covered:
- Defective construction does not qualify as a “physical” loss to trigger the insuring agreement; and
- Any natural results of defective construction are excluded as faulty workmanship, even with favorable LEG 3 or similar language.
Neither of these arguments should impede access to coverage in the majority of scenarios. To ensure as much, it is incumbent on the savvy policyholder to understand the insurer tactics, be prepared to spot them early, and have thoughtful counter positions at the ready to address them decisively.
Reprinted courtesy of
Gregory D. Podolak, Saxe Doernberger & Vita, P.C. and
Cheryl L. Kozdrey, Saxe Doernberger & Vita, P.C.
Mr. Podolak may be contacted at GPodolak@sdvlaw.com
Ms. Kozdrey may be contacted at CKozdrey@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
SunEdison Gets Shinsei Bank Funding for Japan Solar Power Plant
March 12, 2015 —
Ehren Goossens – Bloomberg(Bloomberg) -- SunEdison Inc., a U.S. solar developer, got financing from Tokyo-based Shinsei Bank Ltd. for a large-scale project in the country.
The 9.6-megawatt Tarumizu project on the southern Japanese island of Kyushu will power about 3,000 homes, Maryland Heights, Missouri-based SunEdison said Wednesday in a statement. The project is under construction and expected to be completed in September. Financial details weren’t disclosed.
Read the court decisionRead the full story...Reprinted courtesy of
Ehren Goossens, BloombergMr. Goossens may be contacted at
egoossens1@bloomberg.net
Question of Parties' Intent Prevents Summary Judgment for Insurer
December 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe insurer's and insured's intent as to which entities were to be insured prevented the insurer's motion for summary judgment. Chaus v. State Farm Fire & Cas. Co., 2015 U.S. Dist. LEXIS 136311 (E.D. La. Oct. 5, 2015).
Water damage from a broken pipe occurred at the insured's building. Blaze Chaus LLC owned the building.The building was occupied by two entities which provided health care services: Dr. Kelly G. Burkenstock, M.D. and Azure Spa, Inc. Dr. Burkenstock was the sole owner of all three entities.
The application for commercial insurance was submitted by "Dr. Kelly G. Burkenstock, d/b/a/ Blaze Chaus LLC." The application requested a "Physicians and Surgeons Endorsement" and reflected that the business activities of the applicant as "Internal Medicine Doctor."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Illinois Earns C- on its 2022 Infrastructure Report Card while Making Strides on Roads and Transit
May 02, 2022 —
American Society of Civil EngineersChicago, Ill. – The Illinois Section of the American Society of Civil Engineers (ASCE) today revealed its 2022 Infrastructure Report Card, giving the state an overall grade of C-. Illinois' civil engineers studied eleven infrastructure categories. Of those eleven, six categories are in mediocre condition, and five categories are in poor condition.
The committee representing more than 2,700 civil engineers across Illinois collected and analyzed data and based its grades on eight criteria, including condition, funding, public safety and resilience. As a major hub for our nation's infrastructure, Illinois has taken considerable steps to improving its transportation and infrastructure networks and several major categories showed improvements – notably transit and roads.
To view the report card and all eleven categories evaluated, visit https://infrastructurereportcard.org/state-item/Illinois/.
ABOUT THE ILLINOIS SECTION OF THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Civil engineering experts in their respective fields from the Illinois Section of ASCE, with assistance from the Central Illinois Section, Quad Cities Section, and the St. Louis Section, prepared The Report Card for Illinois' Infrastructure. The Report Card is created to educate and advise our elected officials and citizens on the condition of our State's infrastructure using sound engineering evaluation criteria and to provide recommendations on how to raise the grade. Since 1915, the Illinois Section has represented Civil Engineers in America's engineering hub and the organization recently celebrated its Centennial Anniversary. ASCE provides a platform for our members to mentor, learn and teach, which enables us to serve as stewards of infrastructure in our state, nation and throughout the world.
Read the court decisionRead the full story...Reprinted courtesy of